Sound Transit's 2nd tunnel boring finished

Posted on April 4, 2012

Seattle-based Sound Transit's second tunnel boring machine (TBM) mining new light rail tunnels between Capitol Hill and the University of Washington (UW) finished its underground journey. When complete, the University Link project will connect the UW and Capitol Hill to downtown Seattle with 3.1 miles of new underground light rail service.

Sound Transit tunneling contractors Traylor Frontier-Kemper will now focus on building 15 cross passages between the two tunnels. A different contractor, JayDee Collucio Michaels joint venture, is scheduled to complete tunneling between Capitol Hill and downtown Seattle in June.

The overall $1.9 billion project is about halfway complete and scheduled to open in 2016. The expansion with stations in the heart of Capitol Hill and the University of Washington will provide unparalleled speed and reliability through Seattle’s most dense neighborhoods. A trip from UW’s Husky Stadium to Westlake will take six minutes and is expected to add 70,000 riders to the system by 2030.

The contractor launched the TBM from the UW station site near Husky Stadium in June, 2011. The TBM passed beneath the Montlake Cut and Montlake, Interlake, Volunteer Park and north Capitol Hill neighborhoods.

View comments or post a comment on this story. (0 Comments)

More News

WSP USA projects recognized with three Calif. transportation awards

The Exposition Line Light Rail in Los Angeles received the California Transportation Foundation's Overall Project of the Year award.

City Council approves transfer of Atlanta Streetcar to MARTA

The $99 million streetcar opened in December 2014 amid sky-high expectations, but ridership failed to meet expectations in its first year and plummeted nearly 60% after the city began charging $1 to ride.

Honolulu officials submit new light rail plan to FTA

The total project cost included in the new plan remains at $8.165 billion for capital costs exclusive of finance charges, with full revenue service scheduled for December 2025.

Alstom to supply traction system in Chengdu, China

The contract is worth approximately $68.3 million. The line is expected to start revenue service by the end of 2019.

Hyperloop One announces 10 winners of 'Global Challenge'

The company will commit meaningful business and engineering resources and work closely with each of the winning teams/routes to determine their commercial viability.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close