Following derailment, Metro North to resume full service Wednesday

Posted on May 21, 2013

The track itself, including the stone, ties, rail and fasteners, is the first order of business and that job is complete on one of the two sections.
The track itself, including the stone, ties, rail and fasteners, is the first order of business and that job is complete on one of the two sections.
Reconstruction of track infrastructure damaged in a derailment last Friday has progressed to such a degree that Metro-North plans to resume regular train service on the New Haven Line in time for the peak morning service on Wednesday.

At approximately 6:10 p.m. Friday, a Metro-North train (the 4:41 p.m. departure from Grand Central, due to New Haven at 6:32 p.m.) traveling to New Haven with an estimated 300 passengers derailed in the vicinity of the I-95 overpass in Bridgeport, Conn.

A passenger train traveling in the opposite direction carrying an estimated 400 passengers on the adjacent track (the 5:30 p.m. departure from New Haven-State Street, due Grand Central at 7:18 p.m.) then struck the derailed train. 

About 100 workers are on the job, which has been ongoing around the clock since Saturday night when the National Transportation Safety Board completed its initial investigation of the scene and allowed Metro-North to begin removing the two, eight-car trains.

About 100 workers are on the job, which has been ongoing around the clock since Saturday night when the National Transportation Safety Board completed its initial investigation of the scene.
About 100 workers are on the job, which has been ongoing around the clock since Saturday night when the National Transportation Safety Board completed its initial investigation of the scene.
“We are confident that the reconstruction work, inspection and testing will be completed in time for a normal rush hour on Wednesday,” said Metro-North President Howard Permut. “We are grateful for the tireless work of all departments and employees engaged in this huge task.”

The shuttle train operation from New Haven to Bridgeport, with a bus connection to Stamford, where customers can board a train for New York, continued on Tuesday.

The bus operation went according to plan on Monday with 120 buses on hand and no crowding reported.
The bus operation went according to plan on Monday with 120 buses on hand and no crowding reported.
The bus operation went according to plan on Monday with 120 buses on hand and no crowding reported.

"The local municipalities offered tremendous support, with signs, special lanes, satellite parking and police assistance and Metro-North is grateful for this very high level of cooperation, which ensured the operation’s success,” said Susan Doering, Metro-North’s VP, customer service and stations.

About 750 people rode the shuttle trains and boarded buses at Bridgeport to Stamford, just 20% of the 4,000 people who ordinarily board trains at New Haven, Milford and Stratford during the morning peak period.  However, overall morning peak period ridership on the entire New Haven Line was down just 20%, which means, many people drove to other stations to catch a train.  And a 6% increase in ridership was counted on the Harlem Line.

In Bridgeport, work to rebuild two sections of track totaling 2,000 feet continues at a brisk pace. The track itself, including the stone, ties, rail and fasteners, is the first order of business and that job is complete on one of the two sections. Next comes restringing the overhead catenary wire and appropriate connections to the substations. 

The signal system is the final component followed by vigorous inspection and a period of operating test trains over the rail. This critical work will continue overnight.

View comments or post a comment on this story. (0 Comments)

More News

Chicago Transit replacing airport escalator damaged in train wreck

The train wreck, which occurred in the early morning of March 24, 2014, when the operator allegedly fell asleep, injured more than 30 people and caused roughly $9 million in damage. The lead railcar had to be cut up to remove it from the escalator.

DART takes delivery of first streetcar for new service

The vehicle, which was a designed and built by Brookville Equipment Corp., will be the first streetcar in the U.S. that utilizes wireless traction power.

NJ TRANSIT marks Newark Penn Station's 80th year

Opened in 1935, Newark Penn Station is listed on both the State and National Registers of Historic Places. The station was originally designed and still operates as an intermodal facility serving pedestrian, taxi, bus and private vehicle traffic generated by the more than 50,000 transit customers who use the station each day.

Calgary Transit trains, buses breaking down more often

Part of the problem is an aging fleet, according to officials. Calgary Transit placed a $200-million deal in 2013 to buy 60 new light rail vehicles; however, those vehicles will not be operational until 2016.

Alstom to develop zero-emission train

The new trains for Hermann-Hesse railway line will be completely emission-free. In times of increasing energy costs and higher level of pollution, the development of this technology is essential.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The resource for managers of class 1-7 truck Fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close