SEATTLE – Sound Transit’s tunnel-boring machine “Brenda” punched through the north wall of the future Roosevelt Station on Tuesday — keeping the agency on track to open its Northgate light-rail extension by 2021, The Seattle Times reported.

The 21-foot, 6-inch diameter drill reached daylight around 4:30 p.m., after launching from the Maple Leaf Portal near Northgate in July. A joint venture of Jay Dee, Coluccio, and Michels is building the twin, 3.4-mile train tubes from Maple Leaf to Husky Stadium, plus the Roosevelt and University District stations, under a $462 million contract.

The breakthrough was supposed to happen before 9 a.m., but the machine slowed down while chewing through soil laced with concrete grout, to add stability near the station vault. Shortly after 11 a.m., Brenda took a break to cool off, before proceeding at no more than 5 millimeters per minute. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Alstom receives contract for Ottowa light rail expansion

The contract is worth almost $223.9 million and part of an effort to extend the Confederation Line further east by 7.5 miles and west by 9.3 miles.

MARTA launches initiative to aesthetically enhance rail stations

The authority kicked off the newly established “Artbound” program with an inaugural launch event featuring dancers and musicians at Five Points MARTA Station this week.

Alstom-equipped Bangalore Metro Green Line launches service

It includes the Urbalis 200 Automatic Train Control system, which will ensure optimal safety, flexible operations, and heightened passenger comfort, according to the company.

Bombardier wins major UK rail, maintenance contract

In addition, the company will execute a Technical Services and Spares Supply Agreement for the duration of the seven-year franchise, with an option to extend for 11 periods in line with the existing franchise extension option.

Honolulu legislature to hold special session on rail project funding

The project was expected to cost $5.2 billion just a few years ago but is now estimated to cost as much as $10 billion with financing. The city’s latest figures project a $1.384 billion shortfall from now to 2024.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close