S.F. Muni awards subway tunneling contract

Posted on July 5, 2011

[IMAGE]S-F-Central-Subway-rendering-2.gif[/IMAGE]The San Francisco Municipal Transportation Agency (SFMTA), which operates the Municipal Railway (Muni), approved the tunneling contract for the $1.6B Central Subway project, a light rail extension.

The contract — the largest construction package for the project — was awarded to Barnard Impregilo Healy, as the lowest responsive and responsible bidder in the amount of $233,584,015.00.

Last week, the FTA awarded the agency $20 million in New Starts funds for the 2011 Fiscal Year to keep the project moving forward. For the second year in a row the Project has been included with a specific recommendation for funding in the President’s budget. The Central Subway has received $95.9 million in federal funding to date.

The tunnel contract will allow for the development of approximately 8,240 feet of concrete guideway tunnels and procure two tunnel boring machines to be used for actual construction.

The project has made significant progress over the past few years having completed the first construction contract to relocate underground utilities along the alignment, being halfway finished on the second contract for the Union Square area, and being 95 percent complete in the final designs for the tunnel and stations.

“The progress the SFMTA has made over the past few years proves that the Central Subway Project is shovel-ready and we’re on track to receive the Full Funding Grant Agreement from the FTA by year’s end,” said Executive Director/CEO Nathaniel P. Ford, Sr. “This tunneling contract is a major part of opening a dynamic, new era in rapid transit for the people of San Francisco, and especially for those traveling along the congested Stockton corridor.”

The Central Subway is a $1.57 billion Phase Two of the T Third Line which will extend light rail service with a surface station at 4th and Brannan streets providing a transfer point for Caltrain customers, then travel north up 4th Street before descending underground at the 1-80 Freeway. There will be subway stations at the Moscone Center, Union Square connecting to Powell Street BART and Muni, and in Chinatown.

The extended T Third Line is expected to carry 65,000 passengers daily by the year 2030.  The project will be in revenue service by 2018.

View comments or post a comment on this story. (0 Comments)

More News

New Metra railcar RFP allows for alternative designs

Proposals will be due in August and Metra hopes to finalize a deal by the end of the year for at least 200 new cars.

Sonoma-Marin rail system carries 100,000th bicyclist

Since opening its doors in 2017, SMART passengers have included bicyclists who use their bikes to get to and from stations on a regular basis.

Alstom opens online marketplace for mobility sector

StationOne connects professionals in the railway industry and is designed as an efficient way to both promote and access the broadest possible range of products and services.

LAX breaks ground on automated people mover

Once completed in 2023, the APM will connect with L.A. Metro's light rail system.

MBTA opens $17M rail station on schedule, on budget

The Blue Hill Avenue Station marks the completion of the Fairmount Commuter Rail Line.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation