Keolis/MBTA make strides with commuter rail snowstorm recovery

Posted on February 25, 2015

MBTA Snow Removal Red Line, Quincy, February 18, 2015. MassDOT photo.
MBTA Snow Removal Red Line, Quincy, February 18, 2015. MassDOT photo.

Keolis, the operator of MBTA commuter rail, announced several milestones Tuesday, including the completion of snow and ice removal from all platforms and critical rail switches system-wide, as well as the addition of supplemental trains, doubledecker and standard passenger cars to increase capacity and combat overcrowding.

Over the weekend, 700 tons of snow were melted with the assistance of a snowmelter on loan from the Commonwealth of Massachusetts, and more than 180 truckloads of snow were removed from key maintenance facilities, while 184 railway switches were cleaned of snow and ice. Keolis employees have removed 10.6 million cubic feet of snow from station platforms since January 27th and 594 million cubic feet from tracks and track infrastructure.

MBTA Commuter Rail continues to operate on a limited-service schedule (www.mbta.com/winter) as it begins repairs on its locomotive fleet and passengers should continue to plan accordingly for delays and cancelations. Keolis will remain vigilant with snow again in the forecast for Tuesday night into Wednesday, but commuter rail customers are advised to be aware of possible delays and cancelations under an already-reduced schedule.

Keolis has begun adding extra trains to service commuter rail lines experiencing overcrowding on trains and platforms due to the reduced schedule. These trains will be used sporadically system-wide as extra trains become available and announced via station platform signs and T-Alerts. The recovery plan intends to return three locomotives to service every week on the path to restoring regular weekday service.

Keolis recognizes the extremely hard work of its employees as the recovery process continues, many of whom have been working around the clock since January 27th to keep and/or return trains in service, clear tracks and switches and get the system back to full service as soon as possible for our customers, said a company statement.

View comments or post a comment on this story. (0 Comments)

More News

New Metra railcar RFP allows for alternative designs

Proposals will be due in August and Metra hopes to finalize a deal by the end of the year for at least 200 new cars.

Sonoma-Marin rail system carries 100,000th bicyclist

Since opening its doors in 2017, SMART passengers have included bicyclists who use their bikes to get to and from stations on a regular basis.

Alstom opens online marketplace for mobility sector

StationOne connects professionals in the railway industry and is designed as an efficient way to both promote and access the broadest possible range of products and services.

LAX breaks ground on automated people mover

Once completed in 2023, the APM will connect with L.A. Metro's light rail system.

MBTA opens $17M rail station on schedule, on budget

The Blue Hill Avenue Station marks the completion of the Fairmount Commuter Rail Line.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation