Rail

Tunnel boring work set to begin for L.A. Metro rail extension

Posted on July 18, 2018

Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026.
L.A. Metro
Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026.
L.A. Metro

Two state-of-the-art tunnel boring machines (TBMs) will soon begin work on Section 2 of the Los Angeles County Metropolitan Transportation Authority’s (Metro) Purple Line Project, aided by the engineering and design services provided by STV, a transportation and infrastructure firm.

Working as part of the design-build team led by Tutor Perini and O&G Industries, STV is serving as the engineer-of-record and principal design firm for the 2.6-mile-long Purple Line Section 2 extension that will link Section 1 running through the Miracle Mile District with Section 3 connecting Century City to Westwood. Overall, the $6.3 billion Purple Line extension will run 9.1 miles from Koreatown to Westwood.

STV’s services include the design of stations at Beverly Hills and Century City along with the running tunnels. The firm also engineered and designed the so-called “launch box” in Century City where the two 400-foot-long TBMs will be lowered into excavations extending more than 70 feet below Constellation Boulevard to begin their 14- month journeys.

The construction of the Beverly Hills and Century City stations will use a cut-and-cover method to build entrances, platforms, and concourses along with additional space for power, ventilation systems, and communications. STV will also be providing engineering and design services for the trackwork, traction power, train control, and communications systems.

Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026. Once completed, the subway ride from downtown Los Angeles to Westwood is expected to take about 25 minutes.

View comments or post a comment on this story. (1 Comment)

More News

Bombardier wins S.F. airport people mover ops, maintenance contract

The 10-year contract is valued at $220 million and includes an option for an additional five years.

3 spatial tools to help you maintain your wayside PTC assets

With thousands of pieces of new infrastructure, railroads are asking: How are we going to manage all these safety-critical PTC assets?

VTA partners with FTA to pilot expedited project delivery program

VTA discussing participation for BART Phase II Project, a five-mile underground subway through downtown San Jose. 

 

Final report on Wash. Amtrak derailment urges 'System Safety' plan

In all, the NTSB issued 26 new safety recommendations and reiterated three existing safety recommendations in the report.

DART renames Cotton Belt commuter rail service

The Silver Line will interface with three DART light rail lines.

See More News

Post a Comment

Post Comment

Comments (1)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation