Improperly used train approach warning led to LIRR worker’s death

The accident occurred when a Long Island Rail Road train, on track three in multiple track territory, approached a five-member crew of roadway workers in the Queens Interlocking.

May 18, 2020
Improperly used train approach warning led to LIRR worker’s death

The photo depicts the accident scene on June 11, 2017.The photo was taken at track level from the east end of the Queens Village Station. The point where the roadway worker was struck by the train is marked with the red circle.

NTSB

2 min to read


The photo depicts the accident scene on June 11, 2017.The photo was taken at track level from the east end of the Queens Village Station. The point where the roadway worker was struck by the train is marked with the red circle. NTSB

The National Transportation Safety Board issued the final report for its investigation of the June 10, 2017, Queens Village, N.Y., railroad accident in which a railroad roadway worker was struck and killed by a train.

Ad Loading...

The accident occurred when a Long Island Rail Road train, on track three in multiple track territory, approached a five-member crew of roadway workers in the Queens Interlocking. The foreman and two roadway workers were conducting a walking inspection and making repairs on track one. They were accompanied by the watchman. The fifth roadway worker was clear of the tracks. The watchman noticed the train approaching on track three, sounded a handheld horn, called out to the other workers and raised a paddle as a visual signal to the LIRR’s locomotive engineer to sound the train’s horn. When the engineer sounded the horn, three of the roadway workers remained on track one but the foreman stepped into the path of the traveling train on track three and was struck and killed. The train was traveling about 78 mph when the locomotive engineer applied the emergency brakes just before impact.

The NTSB noted in its report the train approach warning method was particularly dangerous for the crew working on the Queens Village Interlocking. Several factors, such as the multiple tracks at the interlocking, trains operating at high speeds in both directions, and the crew having limited areas to clear trains, combined with the additional train traffic due to the Belmont Stakes, increased the risk of the work crew being struck by a train. The watchmen on duty at the time should have given the workers timely warning of approaching trains and all workers should have cleared to the tracks before the train’s arrival, the NTSB concluded.

Contributing to the accident was the railroad’s and union’s allowance of overtime work schedules without properly considering and mitigating workers’ risk of fatigue. The NTSB noted the watchmen and foreman had consecutive overtime shifts that disrupted their opportunities for restorative sleep during the 48 hours prior to the accident.

The NTSB issued five safety recommendations with two recommendations each issued to the FRA and the Metropolitan Transportation Authority. One recommendation was issued to the International Association of Sheet Metal, Air, Rail, and Transportation Workers. These recommendations address safety issues including roadway worker protection, roadway worker on-track safety briefings, management oversight, FRA oversight and worker fatigue.

The final report is available here.


More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →