The Expertise Behind Constructing the San Diego Mid-Coast Trolley

WSP USA representatives discuss the behind-the-scenes of The Mid-Coast Trolley Project’s completion, the role of a consultant, and the overall benefits of the project itself.

by Louis Prejean
February 3, 2022
The Expertise Behind Constructing the San Diego Mid-Coast Trolley

The UC San Diego Blue Line now provides a one-seat connection from UTC to downtown San Diego, and south to the U.S.-Mexico border.

Photos courtesy WSP USA

5 min to read


The Mid-Coast Trolley Project, an 11-mile light rail extension of the University of California (UC) San Diego Trolley Blue Line, celebrated its official opening in November 2021.

The extension provides a critical new connection for San Diego, extending the light rail line from the Old Town Transit Center north to the University Towne Center (UTC) Transit Center in University City.

Ad Loading...

The UC San Diego Blue Line now provides a one-seat connection from UTC to downtown San Diego, and south to the U.S.-Mexico border.

What Makes This Project Unique

In addition to 11 miles of new double tracks, the project included the design and construction of eight bridge crossings, nearly seven miles of at-grade alignment in or near existing railroad right- of-way, more than four miles of aerial viaduct structures, and nine stations — five at-grade and four aerial.

WSP representatives, including Project Managers Kristin Carlson and Kimberly Jaskot, Area Manager/VP Patti Boekamp, and Sr. Manager Vladimir Kanevskiy discuss just how much went into completing this extension.

“The Mid-Coast project is one of very few major rail transit projects successfully delivered via alternative delivery methods, such as construction manager/general contractor (CM/GC),” say WSP representatives. “The project had numerous technical challenges associated with difficult geologic conditions.”

Ad Loading...

According to WSP, there were challenges of active fault lines; major utility relocations involving local and federal owners such as the U.S. Navy aviation fuel line; and construction along the Los Angeles-San Diego-San Luis Obispo (LOSSAN) rail corridor.

Other challenges included construction on the University of California, (UC) San Diego campus with a student and faculty population of over 35,000 and bringing an electrified transit system in close proximity to major health care facilities with sensitive medical equipment.

The Impact Of COVID-19

The COVID-19 pandemic provided another challenge for The Mid-Coast project.

“The project has been a major boost to the local economy since construction began in the fall of 2016, employing over 5,200 on-site workers,” say WSP representatives. “There were some shortages or extended procurement times associated with certain materials as a result of the COVID-19 pandemic, but these challenges did not effect on-time opening of the project.”

Ad Loading...

The firm managed a safe construction process and was able to provide employment during the pandemic, benefiting the local economy.

Now open for service, the trolley extension will offer alternatives to commuters while also improving public transportation services and further enhancing access to jobs, schools, and hospitals.

The extension provides a critical new connection for San Diego, extending the light rail line from the Old Town Transit Center north to the University Towne Center Transit Center in University City.

Behind the Funding

WSP USA was responsible for environmental, planning, preliminary, and final engineering; New Starts funding advisory services; and design services during construction of the light rail extension operated by the San Diego Metropolitan Transit System.

“The Mid-Coast project is particularly complex and required a wide range of planning and design capability, as well as flexibility, to address the needs of two rail operators and various stakeholders including the City of San Diego, UC San Diego, Caltrans, Veterans Affairs San Diego Healthcare System, and several private property owners,” says WSP representatives.

Ad Loading...

As the designer of record, WSP was charged with advancing the $2.1 billion project from environmental clearance and conceptual engineering through construction, including track and systems design and operations analysis, station design, traffic engineering, civil and utilities design, and structures design.

WSP also provided grant procurement services that led to a $1 billion Federal Transit Administration Full Funding Grant Agreement in 2016, clearing the way for construction to begin. The project was completed on time and on budget.

“WSP played a key role on the project starting as the environmental and preliminary engineering consultant by getting the project environmentally cleared in late 2014 from the San Diego Association of Governments (SANDAG) board of directors and the Federal Transit Administration (FTA), while simultaneously proceeding with advanced preliminary engineering,” WSP representatives say.

This allowed SANDAG to proceed with selection of the CM/GC, bringing the entity early in the final design phase, and allowing for a collaboration between the design team and CM/GC contractor. It also optimizes the design and reduces risk of change orders during construction.

The Importance of a Consultant

Ad Loading...

The Mid-Coast project was the largest program undertaken in the region’s history, according to WSP USA.

WSP brought together and managed a team of sub-consultants, closely coordinating with SANDAG’s team and consultant partners to advance and deliver this project.

The team included TYLin International in partnership with HDR, program management; Jacobs and PGH Wong, construction management; and the Mid-Coast Transit Constructors CM/GC team, a joint venture of Stacy and Witbeck, Herzog, and Skanska.

“The ability to ramp up and down and utilize technical specialists was also critical during construction when responding to Requests for Information and working with the contractor,” says WSP representatives. “WSP and the rest of the consultant team on the project management consultant and construction manager side were key in supporting SANDAG with on time and on budget delivery of the project.”

The firm says it required expertise and resources to deliver over 30,000 pages of the environmental documentation and nearly 7,000 pages of drawings in a short period of time.

Ad Loading...

Mid-Coast Trolley Project Benefits

In addition to the 1,170 new parking spaces at five of the new stations, the Mid-Coast Trolley Project’s benefits have a bigger impact within the community.

“Transportation capacity expansion was needed along the corridor to accommodate existing and future travel demand resulting from the expected growth in population and job opportunities,” says WSP representatives. “Additionally, there was increasing residential development in the university community, considered to be San Diego’s second downtown.”

The Mid-Coast Light Rail Transit (LRT) Extension has connected the densely populated University City community of San Diego with the rest of the LRT system, while also providing direct access to the UC San Diego campus and major medical facilities serving the broader county population, according to WSP USA.

The project also provides a connection with the City’s “Golden Triangle” situated between three freeways, I-5 on the West, I-805 on the West, and SR-52 on the South.

Ad Loading...

“This trolley extension will transform regional transit connectivity and enhance cross-border opportunities,” WSP representatives say. “The main need for the project was to help address the increase in regional growth by providing improved access to growing employment, education, and residential areas.”

Subscribe to Our Newsletter

More Rail

High-Speed Rail Partners Align on High Desert Corridor
Railby Alex RomanJuly 21, 2026

California High-Speed Rail Authority Signs MOU to Advance High Desert Corridor

The agreement deepens collaboration between the California High-Speed Rail Authority and the High Desert Corridor Joint Powers Agency, supporting design integration, cost savings, and faster delivery of a key Southern California rail link.

Read More →
TechnologyJuly 20, 2026

Building the Next Generation of Transit Technology

In this edition of METROspectives, Luminator CEO Magnus Friberg discusses the company's transformation, the growing role of AI and software, and what's next for transit technology.

Read More →
What Transit Agencies Get Wrong About Data METROspectives episode with strada360's Steve Lassey
Sponsoredby Alex RomanJuly 20, 2026

How Data, Strategy, and Community Engagement Are Reshaping Transit

In this edition of METROspectives, strada360 CEO Steve Lassey discusses how transit agencies can better align planning with operations, leverage data to improve decision-making, and build public trust as they prepare for the future of mobility.

Read More →
Ad Loading...
TTC streetcar on tracks

TTC Launches Camera Pilot to Curb Illegal Passing of Streetcars

During the pilot, the cameras will measure how often illegal streetcar passing occurs and test the technology's reliability for future automated enforcement.

Read More →
An NJ TRANSIT River Line light rail vehicle.
Managementby Staff and News ReportsJuly 17, 2026

NJ TRANSIT Secures Capital Funding, Adopts FY2027 Budget

The budgets continue investments in infrastructure and equipment to maintain the system in a state of good repair and enhance the overall customer experience.

Read More →
A rider validating a tap payment on a Masabi validator.
Technologyby Staff and News ReportsJuly 17, 2026

Biz Briefs: Masabi Teams with St. Louis Metro and More

In METRO's latest installment, we take a look at recent news from Transdev, Hitachi, and more partnerships making headlines across the transportation sector.

Read More →
Ad Loading...
Two Metra locomotives on rail tracks.
Railby StaffJuly 16, 2026

Metra Begins Drone Pilot Project to Boost Safety and Security

The project is funded through a $620,000 grant from FEMA’s Transit Security Grant Program, which provides transit agencies with funding for projects intended to protect critical transportation infrastructure and the traveling public.

Read More →
A rendering of ATP's light rail system in Pleasant Valley
Railby StaffJuly 16, 2026

Austin Transit Partnership Selects Stadler to Manufacture Light Rail Vehicles

The award marks the conclusion of a series of major procurements over 18 months, as outlined in ATP’s delivery plan, and keeps Austin Light Rail on track.

Read More →
A rendering of a child looking out the window of a light rail car with a city skyline in the background.
Railby Elora HaynesJuly 15, 2026

The Heart Behind Austin's Light Rail

Why Austin Transit Partnership's Operations and Maintenance Facility could become the most important building in the city's first light rail system.

Read More →
Ad Loading...
Crowd waiting for LA Metro bus
Managementby Staff and News ReportsJuly 15, 2026

June LA Metro Ridership Surges 2 Million Year Over Year

Total June ridership increased for both weekdays and weekends. Weekday ridership was 953,820, which grew 8.4% from June 2025; Saturdays increased nearly 13% year-over-year to 708,826; and Sundays increased 7.7% to 611,534 from June 2025, according to LA Metro. 

Read More →