METRO Magazine Logo
MenuMENU
SearchSEARCH

MBTA Completes Expedited Track Work on Green Line

With unencumbered access to Green Line stations, crews were able to accomplish station enhancements and amenity upgrades like new flooring and lighting, which further improved the customer experience.

MBTA Completes Expedited Track Work on Green Line

Crews accomplished track work and other upgrades along the Green Line.

Photo: MBTA

3 min to read


The Massachusetts Bay Transportation Authority (MBTA) announced the successful and on-time completion of track work on the Green Line, which removed 16 safety-related speed restrictions.

Additionally, a 17th speed restriction on the Green Line between Haymarket and Government Center stations was shortened by over 500 feet.

Ad Loading...

How the MBTA Crew Accomplished the Track Work

Crews accomplished this work due to unencumbered access to track areas while Green Line train service was suspended on the B branch from Babcock Street to Kenmore, on the E branch between Heath Street and Copley, and in the downtown area between Kenmore and North Station for 10 days from Jan. 3-12 and for 13 days from Jan. 16-28. 

Additionally, during scheduled weekend and evening service diversions over the last several weeks between North Station and Union Square as well as Medford/Tufts, crews from GLXC, the design-build contractor, have completed track work that has alleviated all current tight gauge conditions along both Green Line Extension branches.

“Our team was able to lift even more speed restrictions than were planned and significantly shorten another. This continues to be indicative of the new way the MBTA is doing business," said MBTA GM/CEO Phillip Eng. "I thank our riders for their patience as we know shuttle bus service replacement can be challenging, especially in the winter months. Thank you as well to the MBTA forces, working side by side with our crews from multiple contractors to deliver on the commitments we made.”

With unencumbered access to Green Line stations, crews were able to accomplish station enhancements and amenity upgrades like new flooring and lighting, which further improved the customer experience.

Through planning and coordination between contractor crews and multiple MBTA Operations departments, the MBTA was able to maximize the shutdown time by having numerous contractor crews and MBTA personnel working side-by-side and collaboratively within the underground Green Line tunnel area.

Ad Loading...

Crews performed tie replacement work during the Green Line shutdown.

Photo: MBTA

Critical Work on Green Line

Among this critical work:

  • Over 1,300 ties were replaced.

  • Nearly 10,800 feet of rail was replaced.

  • Nearly 8,900 feet of track was resurfaced and tamped.

  • 12 switches were replaced/rehabilitated.

  • Approximately 7,300 feet of overhead catenary wire was replaced between Haymarket and Boylston stations.

  • Structural repairs were completed on the roofs of Boylston and Copley stations.

  • Tunnel inspections were performed between Haymarket and North Station.

  • At Copley station, repair work was completed on three in-station columns with additional infrastructure upgrades accomplished.

  • A new elevator sump pump was installed at Arlington station.

  • Substation maintenance and electrical repairs were completed. 

  • Water infiltration repairs were completed within the Green Line tunnel.

  • Critical signal and power system repairs were completed. 

  • Improvements were accomplished at the Park Street communication room.

  • Structural inspections were accomplished at stations throughout the Green Line shutdown.

Other in-station work also took place along the Green Line to further enhance the rider experience, including cleaning, sanding, and painting wood benches; performing tactile repairs; stairway upgrades and repairs, including handrail repairs; installing/replacing station signage; painting columns and ceilings at station platforms; painting stair risers, doors, and door frames; performing flooring/tile repairs; replacing lights; patching spalls on concrete columns; replacing/cleaning light covers; and more.

The MBTA further maximized this shutdown by coordinating site access with utility partners. With the service shutdown, Comcast was able to access property adjacent to the MBTA to expand maintenance access points and upgrade existing equipment, which was a project that had been previously delayed nine months.

The Boston Water and Sewer Commission (BWSC) also completed CCTV inspections of 20 maintenance access points and connecting sewer lines of the utility network between Brigham Circle and Health Street stations along Huntington and South Huntington Avenues. 

More Rail

A TriMet MAX Light Rail vehicle overhead shot
Railby StaffFebruary 24, 2026

STV Finalizes Design for First Phase of TriMet MAX Blue Line Substation Upgrades

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

Read More →
HDR rendering of LA to Coachella Valley Rail Project
Railby StaffFebruary 20, 2026

HDR Selected to Advance LA–Coachella Valley Rail Corridor Project

The firm will lead the Tier 2 environmental review program for the Coachella Valley Rail Corridor, including the conceptual and preliminary engineering needed to develop project-level environmental clearance.

Read More →
Rendering of Austin Transit Partnership's light rail line.
Railby StaffFebruary 19, 2026

Contractor Chosen to Help Build Austin Light Rail

The ATP board’s approval of ARC enables ATP to begin pre-construction activities and advance final design for Austin Light Rail under the first phase of what will be a multibillion-dollar contract.

Read More →
Ad Loading...
The Gold Line Logo
Railby StaffFebruary 18, 2026

LA Metro A Line Claremont Extension Study Projects $1.1B in Economic Output

Additionally, construction activity is estimated to generate more than $154 million in tax revenue, including more than $20 million for Los Angeles County.

Read More →
SFRTA TOD groundbreaking event
Railby StaffFebruary 17, 2026

SFRTA Breaks Ground on Its First Transit-Oriented Development

The project represents a significant milestone in the agency’s ongoing efforts to enhance connectivity, activate publicly owned land, and create walkable communities centered around transit.

Read More →
UTA FrontRunner vehicles.
Railby StaffFebruary 12, 2026

STV Tapped to Join Progressive Design-Build Team for UTA Rail Expansion 

The nearly $1 billion FrontRunner 2X project is a transformative investment to modernize and expand the 89-mile commuter rail corridor between Ogden and Provo.

Read More →
Ad Loading...
A rendering of Alstom's LRV for the Toronto Transit Commission.
RailFebruary 9, 2026

Alstom to Supply New Subway Trains for Toronto

Manufactured and tested in Canada, the vehicles will operate in tandem with a cutting-edge signaling system also supplied by Alstom.

Read More →
A 7000-series WMATA railcar at Navy Yard.
Railby StaffFebruary 6, 2026

WMATA and Kawasaki Resolve 7000-Series Railcar Disputes

A multiparty investigation, led by the NTSB and that included WMATA and KRC, found that wheel migration in the 7000-series railcars contributed to the derailment.

Read More →
Photo for METROspectives episode with Ana-Maria Tomlinson
ManagementFebruary 4, 2026

Establishing Standards & Codes in Canada, with CSA’s Ana-Maria Tomlinson

In this episode of METROspectives, METRO’s Executive Editor Alex Roman sits down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the Canadian Standards Association (CSA Group).

Read More →
Ad Loading...
David Carol, Baker Alloush, and Jesse Lazarus from METRO's People Movement February 4 edition.
Managementby Staff and News ReportsFebruary 4, 2026

New Rolling Stock Strategy Lead at New York MTA and More in People Movement

In this edition, we cover recent appointments and announcements at HDR, NCTD, STV, and more, showcasing the individuals helping to shape the future of transportation.

Read More →