Md.'s Light RailLink re-opens 3 days ahead of schedule

Posted on August 20, 2018

To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne
To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne

After permanently stabilizing sections of Light RailLink track that eroded during severe storms on July 21, the Maryland Department of Transportation Maryland Transit Administration (MDOT MTA) resumed service from the Patapsco to Cromwell and BWI Thurgood Marshall Airport stations on Friday — three days ahead of the planned reopening on August 20.

“We thank the men and women of MDOT MTA for their hard work and dedication in completing these much-needed repairs caused by the severe storms and ensuring our Light RailLink system is safe for our riders,” said MDOT MTA COO Sean Adgerson.

To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks. The repair work involved cutting and removing sections of track, gravel, and soil; building a pipe; and excavating an area 40 feet wide and 16 feet deep. A 1,200-foot-long concrete drain also was constructed to minimize potential flooding.

To further stabilize the area, reinforcements were constructed along the hillside next to the tracks. Free shuttle buses were provided to accommodate passengers at all impacted stations while the repairs were being made.

View comments or post a comment on this story. (0 Comments)

More News

Alstom supplying core systems for China's driverless metro line

Nanjing Line 7 is a key metro line in Nanjing’s metro network, which includes 27 stations that connect the southwest to the northeast of the city.

Deutsche Bahn resuming delivery of ICE 4 trains

Siemens and Bombardier reached an agreement with officials on a reworking and testing concept for welds that were occasionally not executed properly.

NYC subway on-time performance passes 80% for first time in 6 years

A contributing factor to the reduction in delays has been the significant progress made in reducing track debris fires.

DART, City of Dallas lock down streetcar operation agreement

It outlines responsibilities related to the planning, design, construction, procurement, operations, and maintenance of the system.

Training program brings Chinese railcar expertise to Chicago

This spring, nineteen electrical and sheet metal workers traveled to China for classroom and hands-on training.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation