FTA issues new ultimatum on Honolulu rail project

Posted on September 24, 2018

If HART and the city miss those deadlines, the FTA “may proceed with the remedies set forth” in its 2012 full funding grant agreement.
Via HART
If HART and the city miss those deadlines, the FTA “may proceed with the remedies set forth” in its 2012 full funding grant agreement.Via HART

HONOLULU — In a letter, the Federal Transit Administration (FTA) set a deadline for the Honolulu Authority for Rapid Transportation (HART) to update its road map to rescue the light rail project financially so that it reflects the FTA’s new, higher cost estimate for rail, the Honolulu Civil Beat reports.

The FTA’s estimate puts rail’s price tag at $8.3 billion, which is $134 million more than the city’s budget estimate. HART now needs to find that additional money in the next 60 days.

The letter also asks that HART and the city decide in the next 30 days whether it will use a public-private partnership to complete rail’s final and most challenging stretch into town. It also demands the city commit its first $44 million contribution to rail, as outlined in the 2017 recovery plan, sometime in the next 60 days.

If HART and the city miss those deadlines, the FTA “may proceed with the remedies set forth” in its 2012 full funding grant agreement, the letter stated. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

NJ TRANSIT awards $40M contract for 'Long Slip' rail project

When completed, the project will allow the agency to operate train service longer leading into, and recover more quickly from, storm events.

Valley Link feasibility report approved by Calif. rail board

Phase 1 of the proposed rail service would cover 41 miles connecting the existing Dublin/Pleasanton BART Station to the proposed ACE North Lathrop Station.

NJ TRANSIT seeks partners to advance TOD projects near light rail

The 37-mile River LINE right-of-way includes 21 station areas across 15 municipalities.

N.Y. MTA report finds subway can speed up by as much as 50%

An agency task force initiated a study that would lead to faster trains while prioritizing customer and employee safety.

Metra's proposed 2020 budget includes $480M in capital spending

Funding will make major investments in locomotives and railcars, stations, bridges, and yards.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation