The compressors malfunctioned during prolonged subfreezing temperatures last winter.
Read More →
While officials considered Tuesday's test successful, there were two instances of possibly blown gaskets that will require adjustment in the electrical delivery system. Testing will continue this week.
Read More →
Streetcar testing is set to start in November, with revenue operations scheduled to begin by Sept. 15, 2016.
Read More →
CAF USA previously informed the city it will not meet the original deadline, and now plans to deliver the first of five streetcar vehicles on Oct. 30, 43 days late. Under the contract, that would mean CAF USA would be expected to pay $43,000 in fines to the city.
Read More →