MBTA served with default, dispute notices over PTC implementation
Pan Am Southern LLC and Pan Am Railways report that MBTA has disavowed the 2014 agreement, raising questions about the three railroads’ ability to implement PTC on Boston-area rail lines by the federal deadline.

John Phelan

John Phelan
Pan Am Southern LLC (PAS) and Pan Am Railways (PAR) served default and dispute notices concerning important operational safety agreements with Boston’s Massachusetts Bay Transit Authority (MBTA).
A 2014 agreement between the two railroads and MBTA was intended to enable a Positive Train Control (PTC) system to be in place by the federal deadline of Dec. 31, 2018. This safety system would be compliant with federal law and appropriate to the joint passenger and freight rail services conducted over the eastern Massachusetts area. In the notice released this week, PAS and PAR report that MBTA has disavowed the 2014 agreement, raising questions about the three railroads’ ability to implement PTC on Boston-area rail lines by the federal deadline. This throws into doubt the continuation of commuter service on those lines beyond that date, according to the two freight lines.
In addition to providing service across its own lines, MBTA performs commuter service over properties owned by PAS. The 2014 PTC agreement governs the installation of PTC over all of the jointly-operated MBTA, PAS, and PAR lines. The agreement was the result of several years of cooperative discussions, plans, and submissions by MBTA to federal agencies (both for regulatory compliance and financial support purposes). The 2014 agreement also covers installation of locomotive equipment that would be necessary for operations for PAS and PAR freight rail service in the Commonwealth.
Since execution of the 2014 agreement, PAS and PAR have acted in reliance on the agreement to ensure safe and compliant passenger services. MBTA repeatedly has progressed and affirmed plans for PTC installation in accordance with the agreement, including in its 2016 Annual PTC Implementation Progress Report submitted to the Federal Railroad Administration. PAS and PAR are concerned that MBTA’s recent disavowal could set back design and implementation of an integrated PTC system by several years, creating uncertainty about compliance with the federal mandate and the continuation of passenger services, according to a joint PAS and PAR release.
PAS and PAR strongly believe the best path forward lies in reaffirmation of the 2014 PTC agreement and building on the efforts PAS, PAR, and MBTA have taken since PTC was mandated. PAS and PAR pledge to work cooperatively with MBTA to implement a joint freight/passenger PTC system as soon as possible.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →