TEXRail tests Stadler trains at DFW Airport
Trinity Metro ordered eight diesel-electric low-floor multiple unit FLIRT from Stadler in June 2015 for the TEXRail project.

Trinity Metro ordered eight diesel-electric low-floor multiple unit FLIRT from Stadler in June 2015 for the TEXRail project. Photo: Stadler

Trinity Metro ordered eight diesel-electric low-floor multiple unit FLIRT from Stadler in June 2015 for the TEXRail project. Photo: Stadler
The first Stadler FLIRT model trains have passed TEXRail’s dynamic train testing at the Dallas/Fort Worth (DFW) International Airport in Texas bringing TEXRail one step closer to putting the trains into service.
TEXRail conducted testing, which took place October 10, 2018, with the support of the Federal Aviation Administration. Tests consisted of a train clearance test and test activities to verify any impacts to the ASR 9 radar tower due to train operations. The test section covered the alignment from the Dallas Fort Worth Junction to the DFW Airport Terminal B station. Next steps in the testing process will include a system-wide test to certify the commuter rail system before testing is completed in December.
Trinity Metro ordered eight diesel-electric low-floor multiple unit FLIRT from Stadler in June 2015 for the TEXRail project. The trains will operate on the commuter route in the corridor between downtown Fort Worth and the northern railway terminus of the Dallas/Fort Worth International Airport in Texas. The design of the vehicles allows operation of a mixed fleet including freight trains with the vehicles meeting the new AVT requirements of the Federal Railroad Administration and Buy America.

The first Stadler FLIRT model trains have passed TEXRail’s dynamic train testing at the Dallas/Fort Worth International Airport. Photo: Stadler
Last week, the FAA and TEXRail tested the trains for clearance to wayside equipment and the infrastructure as well as for train vibration and reflectivity impact to the DFW ASR9 tower radar operation. Train clearance tests such as this one are a function of the project safety and security certification process and will support the system certification. Tests are scheduled based on the track allocation program managed by the commuter rail service operator.
“Essentially, this particular test is part of the overall certification by the FRA that we need to place TEXRail in service,” said TEXRail spokesperson Linda Thornton.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →