OCTA Declares Rail Emergency to Protect, Reopen Track Issues

OCTA is working with Metrolink to develop and implement protective measures along the rail line, below Casa Romantica Cultural Center and Gardens just north of the San Clemente Pier.

OCTA Declares Rail Emergency to Protect, Reopen Track Issues

The initial slide near Casa Romantica occurred on April 27, sending debris into the rail right of way and forcing a stop to all passenger rail service

Photo: OCTA

3 min to read


California’s Orange County Transportation Authority (OCTA) voted to declare an emergency and authorize CEO Darrell E. Johnson to take the necessary actions to protect the railroad track near a sliding hillside in San Clemente.

OCTA is working with Metrolink to develop and implement protective measures along the rail line, below Casa Romantica Cultural Center and Gardens just north of the San Clemente Pier, to allow the rail line to be reopened for safe passenger rail service as soon as possible.

Ad Loading...

That effort will include designing and constructing a temporary barrier wall at the bottom of the slope, within the rail right of way owned by OCTA. The purpose of the temporary wall would be to keep any additional debris from the slide from interfering with safe passenger rail movement on the track. Metrolink is expected to hire a contractor to design and build the wall on an emergency basis to speed up construction.

Taking Precautions to Protect Passenger Rail Line

At the same time, the city of San Clemente is leading efforts to determine the cause of the slide and to stabilize the hillside above the track. The city has indicated that effort will take several weeks but has not given a more detailed timeline.

There is no timeline yet to resume rail service. That decision will be made when OCTA, Metrolink, and the LOSSAN Rail Corridor Agency, which operates Pacific Surfliner service, jointly determine that it is safe for passenger rail travel to resume.

“As always, passenger safety will guide every action we take,” OCTA CEO Johnson said. “We understand how difficult this closure is for the people who rely on rail service through San Clemente and we will work hard to get service running again safely.”

The initial slide near Casa Romantica occurred on April 27, sending debris into the rail right of way and forcing a stop to all passenger rail service. The city of San Clemente collaborated with geotechnical experts and with a contractor to grade and stabilize the slope. Passenger rail service had resumed through the area on May 27.

Ad Loading...

However, on June 5, the hillside significantly slid again, sending debris, including large clumps of dirt and a tree, into the area near the tracks below, forcing another indefinite stoppage of rail service. Two days later, on June 7, freight rail traffic resumed — at a significantly reduced speed of 10 mph. But Metrolink, along with OCTA and LOSSAN, determined that, out of an abundance of caution, rail service should remain halted until more significant measures can be taken to protect the track.

The rail partners will work with the California Coastal Commission for emergency permitting for the temporary barrier wall. The size of the wall will be determined at a later date, in consultation with an engineering contractor.

Photo: OCTA

Next Steps

The rail partners will work with the California Coastal Commission for emergency permitting for the temporary barrier wall. The size of the wall will be determined at a later date, in consultation with an engineering contractor.

The location of the falling debris near Casa Romantica is approximately two miles north of where OCTA is completing construction work to secure another hillside near the Cyprus Shore Homeowners Association in San Clemente. This instance of falling debris from the Casa Romantica hillside is unrelated to that effort.

Currently, Metrolink regional passenger rail service is operating as far south as San Juan Capistrano on weekends, while weekday Metrolink service will continue to operate only as far south as the Laguna Niguel/Mission Viejo Station until further notice.

The Pacific Surfliner is implementing cost-cutting measures to preserve as much service as possible during the track closure. This includes a reduction in service south of Irvine. Three daily round trips to and from San Diego are available with corresponding bus connections to transport passengers around the closure between Irvine and Oceanside. All service north of Irvine remains unchanged.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →