New York MTA Reports $300M in Capital Savings
The report comes as the agency prepares to move forward on a major slate of vital capital projects to be funded by congestion pricing.

In 2023, the MTA completed more than $7 billion in capital projects, the highest in MTA history.
Photo: MTA/Patrick Cashin
The New York MTA Construction & Development (MTA C&D) outlined details of nearly $300 million in capital program cost savings as part of its 2023 Year in Review and 2024 Strategic Plan, which outlines initiatives to improve the delivery of capital projects and modernize the transit system better, faster, and cheaper.
The report comes as the agency prepares to move forward on a major slate of vital capital projects to be funded by congestion pricing.
MTA Driving Down Costs
The Strategic Plan lays out initiatives for the MTA C&D to drive down costs and deliver the ambitious capital program at scale, including innovative delivery models, bundling projects together, and cutting red tape, and shares results of those efforts.
In 2023, the MTA completed more than $7 billion in capital projects, the highest in MTA history. It also awarded more than $8 billion in new commitments, with those awards coming in 6.2% below the engineer’s estimate, saving nearly $300 million.
The completions represent the full promise of C&D’s new way of delivering projects better, faster, and cheaper, for example the completion of the following projects:
Canarsie L Tunnel rehabilitation phase completed ahead of schedule and under budget.
Resiliency upgrades at the Coney Island Yard, completed on budget.
LIRR Third Track completed on time and $100 million under budget.
LIRR Penn Station 33rd Street Concourse completed on time and under budget.
28 projects completed since 2020 to make stations accessible to all under the Americans with Disabilities Act.
On-time delivery of major projects that bring MTA infrastructure into a state of good repair, including tunnel and infrastructure renewal on the Concourse B, D Line tunnel in the Bronx and a project to upgrade track on the 63rd Street Tunnel under the East River used by the F subway line.
“MTA C&D is developing into a world-class capital delivery organization and has the results to prove it,” said MTA Construction & Development President Jamie Torres-Springer. “This Strategic Plan catalogs the progress we’ve made in the few short years since C&D was created and lays out a plan to accelerate it going forward.”
Continuing to Find Savings
Funding from Congestion Pricing will help continue the agency’s progress.
In addition to reducing traffic and improving air quality, it is also the source of $15 billion for transit and commuter rail projects, representing 30% of the total 2020-2024 Program, and more than 50% of remaining projects in the program.
The funding will pay for vital reliability, accessibility, sustainability, and state of good repair projects throughout the entire transit system.
MTA C&D’s report also provides an update on the recommendations put forward by the consultant firm Crowe, which performed a forensic evaluation of the MTA’s capital planning process in 2019.
Since the audit, which coincided with the creation of MTA C&D as a new unified capital delivery agency, the MTA has doubled down on cost containment, with 90% of 2020-2024 capital projects costs within budget. MTA has also reduced project schedules by an average of four months and accelerated the scale of work in construction, tripling the number of accessibility upgrade projects underway, for example.
Impact on MTA’s Long-Term Planning
In addition to managing projects efficiently, these changes have transformed the long-term planning process.
The 20-Year Needs Assessment released last year was the most comprehensive in MTA history, evaluating nearly six million assets across the entire MTA system. It laid out in detail the urgent need for continued investment and set the stage for the creation of the 2025-2029 Capital Program as the MTA continues to meet the transit system’s needs.
Underscoring MTA C&D’s continuing efforts to transform the way it does business to deliver projects faster, better, and cheaper, the agency recently awarded its first “Progressive Design-Build” (PDB) contract, a type of contract that engages a contractor earlier in the design phase of a project, allowing for greater collaboration, efficiency, and reduced risks later during construction.
More Management

FIFA World Cup Matches Are Driving Record Transit Ridership Nationwide
See how World Cup matches are generating record transit demand across North America, with ridership surpassing Super Bowls, concerts, and Olympic-era events.
Read More →
The Hidden Cost of Fuel Data Inaccuracy in Public Transit Fleets
In today's transit environment, accurate fuel and mileage data are critical to reducing costs, minimizing downtime, and improving fleet performance.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
Latinos In Transit Seeks Host Organization for 2027 Leadership Summit
The selected host organization will showcase its transit system, projects, and community while welcoming hundreds of industry leaders and emerging professionals during Hispanic Heritage Month.
Read More →
Bipartisan BUSES Act Seeks Changes to New York City's Bus Idling Enforcement Program
Backed by motorcoach operators, the legislation seeks to balance emissions goals with passenger safety by allowing limited idling for inspections, accessibility needs and extreme weather conditions.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Q4 Travel Data Reveals Drop in Vehicle Traffic to Manhattan Congestion Zone
NYMTC’s quarterly Travel Patterns Report provides a snapshot of travel activity throughout New York City, Long Island, the Lower Hudson Valley, and northern New Jersey using data collected from the agencies operating the region’s bridges, tunnels, and public transit systems.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →