Accenture Study Finds Infrastructure, Capital Projects Regularly Cost $570M More Than Planned
Accenture's recent study finds a startling gap in project cost when organizations miss their targets for infrastructure and capital projects. However, an analysis of the few companies consistently hitting and exceeding their goals reveals that AI may be the key to keeping projects on schedule.

Bryan Carruthers recently helped assemble a report looking into the staggering number of projects that are missing targets, leading to increased costs.
Photo: Accenture/Canva
Accenture’s recent Blueprint for Success research report reveals that most organizations overspend massively on infrastructure and capital projects. The minority of projects completed ahead of plan save stakeholders hundreds of millions of dollars.
The Costs of Missing Targets
The study was done by surveying 700 leaders globally responsible for infrastructure and capital projects in 23 countries and 12 industries.
With 92% of projects finishing late and costing more than initially planned, 66% of organizations are missing targets. This leads to organizations overspending by almost 29% on an average $2 billion project, which is $570 million.
This data was gathered after Accenture noticed some concerning trends in infrastructure and capital projects.
“We saw the rising spending and increasing demand for infrastructure and capital projects,” Bryan Carruthers, Americas infrastructure and capital projects co-lead at Accenture, told METRO. “At the same time, staggering deviations in schedules and budgets seem almost expected. Yet, from working with clients we know that delays and spiraling costs can be avoided. We decided to systematically assess what makes certain organizations and their projects perform significantly better than others, so we could bring those insights to our clients. Particularly, as demand for projects is increasing over the coming decade, which, in turn, will lead to even greater challenges for organizations.”
While two-thirds of organizations are missing targets, 28% are consistently hitting budget and schedule goals within a 10% margin.
The remaining 6% of organizations are the few that consistently finish projects ahead of schedule and under budget, which can save 275 million or around 14% on a typical project.
“The staggering deviations to schedules and budgets we’ve identified can materially impact an organization, cause stakeholder tensions, and carry inherent financial risk,” said Andy Webster, global lead for infrastructure and capital projects at Accenture. “The fact that there are ten times as many organizations significantly missing their targets than those delivering ahead, shows that the industry must reinvent how it plans and executes large-scale infrastructure projects. Our research provides a great opportunity for almost every organization to learn from the 6% that consistently deliver ahead of project targets.”
What Organizations Are Doing to Get Ahead
Accenture identified what the few consistently ahead-of-schedule organizations are doing to keep costs low.
Attracting and developing a skilled workforce to handle the projects is one step companies are taking to keep costs down. With a currently declining labor pool for such projects, recruitment timelines, and costs can increase.
The shortage is particularly noticeable when looking for experienced capital project leaders. This makes keeping and training those who are interested in leading capital projects more important than ever.
Integrating sustainability into the core of projects is also an important step to take early on. By using data-driven environmental insights, organizations can be 65% more likely to complete projects according to plan.
Managing internal and external stakeholders is also important to a project’s success. The research revealed that 59% of infrastructure project executives name “increased project scrutiny from stakeholders” as one of the top three factors contributing to cost overruns and schedule delays.
Making Use of AI
The biggest factor that can affect the success of a project is using AI to help during the process.
With such a significant performance gap, Accenture turned to the data to determine what factors could be causing successful companies to succeed.
“The full extent of the performance gap we identified is quite staggering,” said Carruthers. “More than nine in ten projects don’t meet their targets. Then there is this huge difference of almost $850 billion on average between organizations missing their targets on a typical $2 billion project and that small, 6%-group of organizations that consistently outperforms their peers. They are the North Star. When we assessed what they do differently, a key factor was their technological capabilities, particularly applying AI to planning, managing and evaluating projects.”
By generating project insights and turning them into foresight, organizations can use AI to plan projects that are 40% more likely to meet their intended outcomes.
AI models trained on historical project schedule data can identify and manage risks and uncertainties. This is most useful when project teams lack prior internal reference experience in certain project elements.
“AI is emerging as a key enabler of project success,” said Webster. “For example, generative AI tools can analyze past data and current market trends to give accurate estimates, which reduces the risk to the budget and schedule. As project conditions shift, AI can provide dynamic updates to help teams stay on track. Combined with human ingenuity, the technology will drive reinvention and add value in an industry experiencing skill gaps and significantly lagging in using technology to plan, manage and execute multi-million to multi-billion investments.”
With these discoveries in mind, Accenture is looking to further research how organizations can get the most out of AI and what it takes to build a strong digital core to support it.
More Management

FIFA World Cup Matches Are Driving Record Transit Ridership Nationwide
See how World Cup matches are generating record transit demand across North America, with ridership surpassing Super Bowls, concerts, and Olympic-era events.
Read More →
The Hidden Cost of Fuel Data Inaccuracy in Public Transit Fleets
In today's transit environment, accurate fuel and mileage data are critical to reducing costs, minimizing downtime, and improving fleet performance.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
Latinos In Transit Seeks Host Organization for 2027 Leadership Summit
The selected host organization will showcase its transit system, projects, and community while welcoming hundreds of industry leaders and emerging professionals during Hispanic Heritage Month.
Read More →
Bipartisan BUSES Act Seeks Changes to New York City's Bus Idling Enforcement Program
Backed by motorcoach operators, the legislation seeks to balance emissions goals with passenger safety by allowing limited idling for inspections, accessibility needs and extreme weather conditions.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Q4 Travel Data Reveals Drop in Vehicle Traffic to Manhattan Congestion Zone
NYMTC’s quarterly Travel Patterns Report provides a snapshot of travel activity throughout New York City, Long Island, the Lower Hudson Valley, and northern New Jersey using data collected from the agencies operating the region’s bridges, tunnels, and public transit systems.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →