METRO Magazine Logo
MenuMENU
SearchSEARCH

2013 Top Rail Project Profiles

As part of this year's Top Rail Projects feature, METRO focused on three projects in the works in Houston, Detroit and Tucson, Ariz.

by Alex Roman, Managing Editor
May 20, 2013
2013 Top Rail Project Profiles

 

6 min to read


As part of this year's Top Rail Projects feature, METRO focused on three projects in the works in Houston, Detroit and Tucson, Ariz.

Houston Metro Adding 19 Light Railcars
With its rail system surpassing 100 million boardings four years ahead of its projects, Houston’s Metropolitan Transit Authority (Metro) purchased 19 second-generation S-70 Siemens light railcars to deal with the growth.

Ad Loading...

“Nine new Siemens H2 S-70 vehicles have been delivered to Metro and three have achieved Conditional Acceptance and are now in revenue service on the Main St./Red Line,” explains Margaret O’Brien, spokesperson for Metro. “The other six Siemens vehicles on site are in the testing and commissioning phase. Once they achieve Substantial Completion, complete the Burn-In Test and achieve Conditional Acceptance, the vehicles will be placed in revenue service.”

The purchase of the S70s represented a savings of almost a year’s time in getting optimal service to riders. Metro was able to achieve this by exercising a vehicle option with the Utah Transit Authority when it “piggybacked” through an inter-agency agreement to procure the light railcars from Siemens.

The S70 LRV is electrically powered from an overhead wire (catenary) system and carries about 200 passengers per car. The units can be coupled — up to four together — for more efficient service during peak times.

Each new S70 unit is equipped with eight wide-opening, sliding doors all located in the low-floor area, four on each side of the vehicle. The door spacing is optimal for passenger flow — the time necessary to enter and exit the vehicle, which can cause delays in the schedule. The design of the interior maximizes passenger space, using a knee-to-back seating arrangement and a large standing area with extra hand straps and grab bars for passenger safety.

In addition to the amplified passenger space and wide doorways, the updated S70 is also equipped with two designated wheelchair spaces, allowing priority seating for disabled passengers as well as a hydraulic system that permits height control and level boarding.

Ad Loading...

Metro is also responding to requests from cyclists by outfitting each new H2 S70 with two bicycle racks, located at front and rear doorways, which may make travel safer during hours when bikes are permitted on board.

The delivery of the 19 Siemens S70 Vehicles will be completed in August 2013 and used on Metro’s North Line, with testing and commissioning activities already underway, according to O’Brien.

In addition to the new Siemens vehicles, Metro’s remaining Construcciones y Auxiliar de Ferrocarriles (CAF) vehicles are scheduled to arrive in Houston beginning in October 2013. The CAF railcars will also undergo thorough testing prior to Metro accepting them for use in revenue service.[PAGEBREAK]

Ariz.'s streetcar project 80% complete
Tucson, Ariz.’s Sun Link streetcar project is part of the $2.1 billion Regional Transportation Plan, approved by Pima County voters in May 2006. The project is funded by the Regional Transportation Authority (RTA), as well as federal and other regional funds.

Construction of the project began in April 2012 with an aggressive build schedule that calls for completion within 475 days. The City of Tucson and the RTA are co-managing the project, which is currently in phase two of construction and 80% complete.

The 3.9-mile streetcar line represents the Tucson’s largest construction project to date, generating some 500 constructions jobs. Construction of the line segment portion of the project has progressed well and is currently on schedule and within budget, but there are some challenges, explains Project Manager Shellie Ginn.

“A major component of this project has been locating, relocating and upgrading underground utilities along the route — and in some instances, the existing utilities were over 70 years old and were quite compromised,” she says. “Utility-related issues necessitated several redesigns and delayed the project schedule in some areas. Additionally, the production of the vehicles for the system has been delayed due to technical difficulties with the vehicle manufacturer, our nation’s only domestic manufacturer of streetcar vehicles.”

The project team is expecting delivery of the first streetcar vehicle later this summer and the second vehicle sometime in the fall. Because of the requirement to test each vehicle before launching passenger service, which is slated for late summer 2014, passenger service will be impacted by when vehicle tests are complete.

The project has generated more than 500 construction jobs, 1,500 new housing units, and more than $800 million in private investment to-date, with new restaurants, businesses and entertainment venues already opening along the streetcar route, according to Ginn.

“The streetcar is also an important new, ‘green’ transit option that will make it easier to connect to other communities in our region beyond downtown and the University [of Arizona] areas,” she adds. “Sun Link has allowed the university to expand its landlocked campus into Tucson’s downtown, opening a downtown campus and two large student living complexes.” [PAGEBREAK]

Detroit's streetcar project moves forward
In January, U.S. Department of Transportation Secretary Ray LaHood confirmed a $25 million federal grant to Detroit’s M-1 Rail, which will go toward building the 3.3-mile Woodward Avenue Streetcar Project.

Ad Loading...

In April, M-1 received clearance from the Federal Transit Administration for the Woodward streetcar project through the issuance of the Amended Record of Decision. This was the final approval step under the National Environmental Policy Act process and allows the project to move ahead to the next phases of design, right of way acquisition and construction.

The vision for a rail line along the Woodward Corridor has been in existence since 2007, and it has gone through a number of iterations — in technology and actual cars and total distance. This was done as more information on infrastructure, ridership projections, overall safety, financial feasibility and other factors became available, with the final design taking into consideration all of those factors and more, according to Heather Carmona,  M-1’s chief administrative officer.

“The current and final 3.3-mile streetcar circulator plan that is now in place was also one of the earliest iterations of the M-1 Rail plan,” she says. “There was a period of time that a more ambitious 9.3-mile light rail transit plan to 8 Mile that was proposed in partnership with the city, however, that plan eventually stalled when it could not meet key ridership, funding and other criteria. M-1 Rail, as an ambition, did not falter however, as the work for the original plan was still valid and beneficial to the community good.”

M-1 RAIL’s work has become an unprecedented model in the region for public-private will and cooperation, adds Carmona, with the streetcar project becoming central to many people’s thinking as a first step of connective tissue in the geographic heart of the region.

“We are developing a streetcar line that is expected to be an economic driver for the Woodward Corridor, generating more than $500 million worth of economic development,” she says. “For many across our community, the belief is that someday the streetcar will become the centerpiece for a seamless transit system that connects Detroiters and people throughout the region to jobs and prosperity; thriving businesses; and retail, sporting and cultural activities.”

Subscribe to Our Newsletter

More Rail

Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
Ad Loading...
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Ad Loading...
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →
Ad Loading...
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →