METRO Magazine Logo
MenuMENU
SearchSEARCH

2013 Top Rail Project Profiles

As part of this year's Top Rail Projects feature, METRO focused on three projects in the works in Houston, Detroit and Tucson, Ariz.

by Alex Roman, Managing Editor
May 20, 2013
2013 Top Rail Project Profiles

 

6 min to read


As part of this year's Top Rail Projects feature, METRO focused on three projects in the works in Houston, Detroit and Tucson, Ariz.

Houston Metro Adding 19 Light Railcars
With its rail system surpassing 100 million boardings four years ahead of its projects, Houston’s Metropolitan Transit Authority (Metro) purchased 19 second-generation S-70 Siemens light railcars to deal with the growth.

Ad Loading...

“Nine new Siemens H2 S-70 vehicles have been delivered to Metro and three have achieved Conditional Acceptance and are now in revenue service on the Main St./Red Line,” explains Margaret O’Brien, spokesperson for Metro. “The other six Siemens vehicles on site are in the testing and commissioning phase. Once they achieve Substantial Completion, complete the Burn-In Test and achieve Conditional Acceptance, the vehicles will be placed in revenue service.”

The purchase of the S70s represented a savings of almost a year’s time in getting optimal service to riders. Metro was able to achieve this by exercising a vehicle option with the Utah Transit Authority when it “piggybacked” through an inter-agency agreement to procure the light railcars from Siemens.

The S70 LRV is electrically powered from an overhead wire (catenary) system and carries about 200 passengers per car. The units can be coupled — up to four together — for more efficient service during peak times.

Each new S70 unit is equipped with eight wide-opening, sliding doors all located in the low-floor area, four on each side of the vehicle. The door spacing is optimal for passenger flow — the time necessary to enter and exit the vehicle, which can cause delays in the schedule. The design of the interior maximizes passenger space, using a knee-to-back seating arrangement and a large standing area with extra hand straps and grab bars for passenger safety.

In addition to the amplified passenger space and wide doorways, the updated S70 is also equipped with two designated wheelchair spaces, allowing priority seating for disabled passengers as well as a hydraulic system that permits height control and level boarding.

Ad Loading...

Metro is also responding to requests from cyclists by outfitting each new H2 S70 with two bicycle racks, located at front and rear doorways, which may make travel safer during hours when bikes are permitted on board.

The delivery of the 19 Siemens S70 Vehicles will be completed in August 2013 and used on Metro’s North Line, with testing and commissioning activities already underway, according to O’Brien.

In addition to the new Siemens vehicles, Metro’s remaining Construcciones y Auxiliar de Ferrocarriles (CAF) vehicles are scheduled to arrive in Houston beginning in October 2013. The CAF railcars will also undergo thorough testing prior to Metro accepting them for use in revenue service.[PAGEBREAK]

Ariz.'s streetcar project 80% complete
Tucson, Ariz.’s Sun Link streetcar project is part of the $2.1 billion Regional Transportation Plan, approved by Pima County voters in May 2006. The project is funded by the Regional Transportation Authority (RTA), as well as federal and other regional funds.

Construction of the project began in April 2012 with an aggressive build schedule that calls for completion within 475 days. The City of Tucson and the RTA are co-managing the project, which is currently in phase two of construction and 80% complete.

The 3.9-mile streetcar line represents the Tucson’s largest construction project to date, generating some 500 constructions jobs. Construction of the line segment portion of the project has progressed well and is currently on schedule and within budget, but there are some challenges, explains Project Manager Shellie Ginn.

“A major component of this project has been locating, relocating and upgrading underground utilities along the route — and in some instances, the existing utilities were over 70 years old and were quite compromised,” she says. “Utility-related issues necessitated several redesigns and delayed the project schedule in some areas. Additionally, the production of the vehicles for the system has been delayed due to technical difficulties with the vehicle manufacturer, our nation’s only domestic manufacturer of streetcar vehicles.”

The project team is expecting delivery of the first streetcar vehicle later this summer and the second vehicle sometime in the fall. Because of the requirement to test each vehicle before launching passenger service, which is slated for late summer 2014, passenger service will be impacted by when vehicle tests are complete.

The project has generated more than 500 construction jobs, 1,500 new housing units, and more than $800 million in private investment to-date, with new restaurants, businesses and entertainment venues already opening along the streetcar route, according to Ginn.

“The streetcar is also an important new, ‘green’ transit option that will make it easier to connect to other communities in our region beyond downtown and the University [of Arizona] areas,” she adds. “Sun Link has allowed the university to expand its landlocked campus into Tucson’s downtown, opening a downtown campus and two large student living complexes.” [PAGEBREAK]

Detroit's streetcar project moves forward
In January, U.S. Department of Transportation Secretary Ray LaHood confirmed a $25 million federal grant to Detroit’s M-1 Rail, which will go toward building the 3.3-mile Woodward Avenue Streetcar Project.

Ad Loading...

In April, M-1 received clearance from the Federal Transit Administration for the Woodward streetcar project through the issuance of the Amended Record of Decision. This was the final approval step under the National Environmental Policy Act process and allows the project to move ahead to the next phases of design, right of way acquisition and construction.

The vision for a rail line along the Woodward Corridor has been in existence since 2007, and it has gone through a number of iterations — in technology and actual cars and total distance. This was done as more information on infrastructure, ridership projections, overall safety, financial feasibility and other factors became available, with the final design taking into consideration all of those factors and more, according to Heather Carmona,  M-1’s chief administrative officer.

“The current and final 3.3-mile streetcar circulator plan that is now in place was also one of the earliest iterations of the M-1 Rail plan,” she says. “There was a period of time that a more ambitious 9.3-mile light rail transit plan to 8 Mile that was proposed in partnership with the city, however, that plan eventually stalled when it could not meet key ridership, funding and other criteria. M-1 Rail, as an ambition, did not falter however, as the work for the original plan was still valid and beneficial to the community good.”

M-1 RAIL’s work has become an unprecedented model in the region for public-private will and cooperation, adds Carmona, with the streetcar project becoming central to many people’s thinking as a first step of connective tissue in the geographic heart of the region.

“We are developing a streetcar line that is expected to be an economic driver for the Woodward Corridor, generating more than $500 million worth of economic development,” she says. “For many across our community, the belief is that someday the streetcar will become the centerpiece for a seamless transit system that connects Detroiters and people throughout the region to jobs and prosperity; thriving businesses; and retail, sporting and cultural activities.”

Subscribe to Our Newsletter

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →