2015 Top Rail Project Cost Reaches $91B

New York City Transit tops this year’s list with $16.5 billion, while several projects, including the Second Avenue Subway and Sound Transit’s University Link, hit major milestones. Meanwhile streetcars continue to make an impact, with one from 2014 successfully launching and three more set to open in the next year or two.  

by Alex Roman, Managing Editor
June 17, 2015
2015 Top Rail Project Cost Reaches $91B

 

5 min to read


With the Second Avenue Subway, East Side Access and several other projects chugging along, the Metropolitan Transportation Authority’s New York City Transit (NYCT) sits at the top spot in METRO’s 2015 Top Rail Projects survey with $16.5 billion in projects, while this year’s total purse, both reported and researched, totals $91 billion.

Rounding out METRO’s top five are the Toronto Transit Commission with $13.2 billion; Seattle’s Sound Transit with $7.8 billion; Boston’s Massachusetts Bay Transportation Authority with $5.6 billion; and the City & County of Honolulu DOT Services’ Rapid Transit Division with $5.2 billion.

Ad Loading...

Overall, this year’s top 10 make up 71% of this year’s total purse with a whopping $65-plus billion in projects. Ranked by state, the top three with the most in rail projects are New York ($19 billion), California ($9.7 billion) and Washington ($7.9 billion). Canada also continues to build with projects totaling $19.2 billion or about 21% of 2015’s total.

Meanwhile, streetcar construction continues to make an impact in the U.S., with four projects totaling $517 million and making major strides toward either opening or finding sources to generate funding.

Construction progress
In New York, construction on Phase One of NYCT’s Second Avenue subway line is at about 82%, with the team on pace to meet its December 2016 target date, MTA Capital Construction Co. officials recently announced.

The Second Avenue Subway is New York City’s first major expansion of the subway system in over 50 years. Being built in four phases, with completion currently set for 2029, the line will stretch 8.5 miles along the length of Manhattan’s East Side, from 125th Street in Harlem to Hanover Square in Lower Manhattan.

All of the stations will have escalator and elevator access, including access for people with disabilities, and will have climate control features to maximize customer comfort.

Ad Loading...

SFMTA

In San Francisco, the Municipal Transportation Agency (SFMTA) completed the Central Subway tunnel portal entrance, which was the final element to the overall tunneling contract, in May, on-time and on-budget.

The Central Subway Project is the second phase of SFMTA’s Third Street Light Rail Transit Project and is slated to open in 2019. The U.S. Department of Transportation announced approval of the Full Funding Grant Agreement of $942.2 million to fund nearly half of the project. The remaining budget is balanced by existing state and local grant funds.

In Seattle, construction on Sound Transit’s 3.15-mile University Link extension, which will connect the University of Washington and Capitol Hill to downtown Seattle and the airport, is about 94% complete.

The $1.9 billion project, slated to open in December 2016, is projected to add 71,000 riders to the system by 2030, bringing the systemwide total to 114,000, according to the agency.

System launches
A few projects have launched since last year’s Top Rail Projects survey, with some also set to open in the very near future.

In Texas, Dallas Area Rapid Transit opened its Orange Line extension to Dallas/Fort Worth International Airport (DFW) in August, four months ahead of schedule.
With the opening, DFW becomes the third-largest American airport with a direct rail connection to the city center.

Ad Loading...

Meanwhile as of press time, Houston Metro was getting ready to launch two rail lines — the 3.3-mile Green Line and the 6.6-mile Purple Line.

The addition of the two new lines brings Houston’s light rail system to nearly 23 miles, with the expansion being looked at as essential in providing residents with much-needed transportation options, while also easing growing traffic congestion in the region.

In Tucson, Ariz., the Sun Link streetcar system launched in July 2014 and celebrated its one millionth boarding passenger this May.

The 3.9-mile, 18-stop system connects the University of Arizona campus to the Mercado District, Arizona Health Sciences Center, 4th Avenue, downtown Tucson and the Convention Center. RATP Dev is tasked with operating and maintaining the line with a three-year contract from the City of Tucson Department of Transportation with options for up to eight years.

Streetcars thriving
Continuing the trend, streetcar projects are thriving in the U.S., with two ready to begin service this year and one reaching a major funding milestone.

Sun Link

In May, the City of Seattle began testing of its First Hill Streetcar line, which will connect with Sound Transit’s Link light rail system, Sounder commuter rail and Amtrak intercity rail. The project had fallen behind schedule because of issues with the vehicles, but officials are optimistic the system will begin regular service this year.

Ad Loading...

Construction on Kansas City’s two-mile KC Downtown Streetcar starter line is on pace to be completed by the fall, with tracking for the system approximately 70% complete, according to officials. Following testing, the streetcar system is set to be open to the public in early 2016.

Finally in Detroit, it was recently announced that Quicken Loans Inc. bought the naming rights for the M-1 Rail streetcar line, which is currently under construction and set to open in late 2016.

As of press time, M-1 officials were getting set to hire a company to aid in naming the line and stations as well as choosing the color of the streetcars and helping with branding and logos for the system.

If you know an agency with plans for the future, but were omitted from this year’s survey, please let us know so that we can include it next year. METRO would also like to send a special thanks to all the agencies for taking the time to fill out our surveys and continuing to participate in this annual feature.   

To view the feature as it appeared in print, click here.

Subscribe to Our Newsletter

More Rail

An OCTA coastal rail line train.
Rail•by Staff and News Reports•November 24, 2026

OCTA Finalizes 30-Year Strategy to Protect Coastal Rail Corridor

The agency approved its coastal rail resiliency study and will begin developing projects to protect seven miles of railroad as emergency stabilization efforts continue.

A VIA CNG bus on the road
Management•by Alex Roman•November 20, 2026

VIA, MBTA Reach Pre-Pandemic Ridership Milestones as Transit Use Climbs

VIA surpasses three million monthly trips for the first time since 2020, while the MBTA tops one million average weekday trips as both agencies report continued ridership growth.

Darren Kettle CEO of Metrolink
Management•by Alex Roman•November 20, 2026

People Movement: Metrolink's Kettle Announces Retirement, Feakins to CEO at UZURV, and More

In this edition, we also cover recent appointments and announcements at King County Metro, SilverRide, and more, showcasing the individuals helping to shape the future of transportation.

Ad Loading...
TTC Line 5
Management•by Alex Roman•November 18, 2026

How Gen Z's Changing Mobility Habits Are Reshaping Public Transit

As younger generations embrace multimodal mobility over private vehicles, transit agencies can rethink station design, the passenger experience, and public transportation's role in building connected communities.

A rendering of Amtrak's Airo trainset
Rail•by Alex Roman•November 18, 2026

Amtrak Expands Airo Fleet with Eight Higher-Capacity Trainsets

The new 10-car trains, expected to enter service in 2031, will provide about 34% more seating capacity to meet growing demand on the Northeast Corridor.

APTA Warns Proposed FTA Guidance Could Delay Major Transit Projects
Management•by Alex Roman•November 18, 2026

APTA Urges FTA to Withdraw Proposed Capital Investment Grants Guidance

The association warns that proposed changes could delay transit projects, reduce federal funding, and create new hurdles for 47 projects currently in the CIG pipeline.

Ad Loading...
New Portal North Bridge Marks Major Milestone for Northeast Corridor Rail Service
Rail•by Alex Roman•November 17, 2026

Amtrak, NJ TRANSIT Launch Full Service on New Portal North Bridge

The completion of the two-track bridge over the Hackensack River eliminates a longstanding source of delays for NJ TRANSIT and Amtrak customers. It marks a major milestone for the Gateway Program.

A Metrolink station with two trains.
Rail•by Alex Roman•November 16, 2026

Southern California’s Metrolink Approves $508.8M Budget, Avoids Service Cuts

A $20 million state allocation allows the regional rail agency to maintain existing weekday and weekend service through fiscal year 2028, although longer-term funding challenges remain.

A wide shot of Alstom's Multilevel III commter railcar for NJ TRANSIT
Rail•by Alex Roman•November 13, 2026

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements

The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.

Ad Loading...
STraffic's John Moon
Technology•by Alex Roman•November 12, 2026

STraffic Expands North American Presence with Fare Collection Technology

John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.