Calif.'s Metrolink puts PTC into revenue service demo mode
With this latest accomplishment, Metrolink remains on track to become the nation’s first passenger rail system to have a fully implemented, interoperable PTC system in place.

Paul Sullivan

Metrolink reached another critical milestone by launching Positive Train Control (PTC) in revenue service demonstration (RSD) along the commuter railroad’s San Bernardino Line between the cities of Los Angeles and San Bernardino. With this latest accomplishment, Metrolink remains on track to become the nation’s first passenger rail system to have a fully implemented, interoperable PTC system in place.
Functional field testing of the integrated PTC system along the San Bernardino Line began in July 2014. More than 150 unique test cases were performed on the subdivision in addition to extensive end-to-end functional testing. The Federal Railroad Administration (FRA) formally approved the commencement of RSD on the San Bernardino Line in mid-February.
Metrolink first launched PTC in revenue service demonstration under the authority of the Burlington Northern Santa Fe (BNSF) railroad in February 2014. That set of tracks includes portions of Metrolink’s Orange County Line, the 91 Line, along with the agency’s Inland Empire-Orange County Line.
The agency recently completed end-to-end testing on the Ventura County Line and just initiated similar testing on the Antelope Valley Line, which are the next two lines expected to go into RSD. Testing and RSD will then take place on the Orange County Line this spring.
RELATED:Metrolink Leads the Way as PTC Deadline Looms
Metrolink intends on having RSD across all track dispatched by the agency by late summer of 2015. Despite monumental challenges, Metrolink is scheduled to meet the federally mandated Dec. 31, 2015 PTC implementation deadline set by the Rail Safety Improvement Act of 2008.
The FRA has authorized Metrolink to operate PTC RSD using Wabtec’s Interoperable Electronic Train Management System (I-ETMS) ®. Wabtec’s I-ETMS® PTC System was selected by the four Class One freight railroads and by Amtrak outside of the northeast corridor as well other commuter railroads including Metra and Coaster.
Parsons Transportation Group, Inc., a business unit of Parsons Corporation, is the primary contractor managing Metrolink’s PTC program.
The estimated cost for developing, installing and deploying PTC on the Metrolink system is expected to be $216.3 million, using a combination of federal, state and local funding sources. Investments were also made to upgrade and expand the existing communication network, which is necessary for PTC and other modern railroad operations.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →