Calif.'s Metrolink puts PTC into revenue service demo mode
With this latest accomplishment, Metrolink remains on track to become the nation’s first passenger rail system to have a fully implemented, interoperable PTC system in place.

Paul Sullivan

Paul Sullivan
Metrolink reached another critical milestone by launching Positive Train Control (PTC) in revenue service demonstration (RSD) along the commuter railroad’s San Bernardino Line between the cities of Los Angeles and San Bernardino. With this latest accomplishment, Metrolink remains on track to become the nation’s first passenger rail system to have a fully implemented, interoperable PTC system in place.
Functional field testing of the integrated PTC system along the San Bernardino Line began in July 2014. More than 150 unique test cases were performed on the subdivision in addition to extensive end-to-end functional testing. The Federal Railroad Administration (FRA) formally approved the commencement of RSD on the San Bernardino Line in mid-February.
Metrolink first launched PTC in revenue service demonstration under the authority of the Burlington Northern Santa Fe (BNSF) railroad in February 2014. That set of tracks includes portions of Metrolink’s Orange County Line, the 91 Line, along with the agency’s Inland Empire-Orange County Line.
The agency recently completed end-to-end testing on the Ventura County Line and just initiated similar testing on the Antelope Valley Line, which are the next two lines expected to go into RSD. Testing and RSD will then take place on the Orange County Line this spring.
RELATED:Metrolink Leads the Way as PTC Deadline Looms
Metrolink intends on having RSD across all track dispatched by the agency by late summer of 2015. Despite monumental challenges, Metrolink is scheduled to meet the federally mandated Dec. 31, 2015 PTC implementation deadline set by the Rail Safety Improvement Act of 2008.
The FRA has authorized Metrolink to operate PTC RSD using Wabtec’s Interoperable Electronic Train Management System (I-ETMS) ®. Wabtec’s I-ETMS® PTC System was selected by the four Class One freight railroads and by Amtrak outside of the northeast corridor as well other commuter railroads including Metra and Coaster.
Parsons Transportation Group, Inc., a business unit of Parsons Corporation, is the primary contractor managing Metrolink’s PTC program.
The estimated cost for developing, installing and deploying PTC on the Metrolink system is expected to be $216.3 million, using a combination of federal, state and local funding sources. Investments were also made to upgrade and expand the existing communication network, which is necessary for PTC and other modern railroad operations.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →