The draft business plan transparently identifies the project’s challenges, which include longer schedules and higher costs due in large part to inflation, increased contingencies and construction delays in the Central Valley.
California High-Speed Rail Authority
3 min to read
The draft business plan transparently identifies the project’s challenges, which include longer schedules and higher costs due in large part to inflation, increased contingencies and construction delays in the Central Valley.
California High-Speed Rail Authority
With its new leadership in place, the California High-Speed Rail Authority release the Draft 2018 Business Plan that “transparently acknowledges the project’s challenges and outlines a sensible path forward that will continue to put thousands of Californians to work building the nation’s first high-speed rail system.”
“The Draft 2018 Business Plan presents a strategy to implement the nation’s first truly high-speed rail system in the face of challenges that projects around the world of similar magnitude and complexity faced and successfully overcome," said the authority’s CEO Brian Kelly. “The plan reflects our commitment to apply lessons learned and make organizational improvements necessary to deliver this project to initiate high-speed rail service between the Silicon Valley and the Central Valley as soon as possible, while completing environmental work and making important investments in Southern California.”
Ad Loading...
The draft business plan acknowledges cost increases affecting each segment of the project ranging from 20% to 35% and revised schedules that would push out delivery dates for the Silicon Valley to Central Valley Line and Phase 1 System. The draft plan acknowledges and responds to changed circumstances and emphasizes a new way of doing business moving forward.
In the face of these challenges, the plan proposes to continue an investment strategy that builds infrastructure, linked over time, to provide mobility, economic and environmental benefits to Californians, and initiate high-speed rail service as soon as possible, according to the authority.
Toward that end, the draft business plan identifies the following investment priorities:
Meet its Commitments to Federal Funding Partner: The authority will complete the 119-mile segment in the Central Valley and complete environmental review for the entire Phase 1 System between San Francisco to Los Angeles/Anaheim by 2022, as required by the federal grant agreement.
Extend the Valley-to-Valley Service from San Francisco to Bakersfield: The draft business plan recognizes the high ridership and revenue potential of linking the Silicon Valley with the Central Valley between San Francisco and Bakersfield.
Deliver 224 Miles of High-Speed Rail Ready Infrastructure for Use by 2027: The draft business plan proposes to construct high-speed rail ready infrastructure in the Central Valley (Madera to Bakersfield) and in Silicon Valley (San Francisco to Gilroy) to reduce travel times for existing passenger rail systems, expand clean, electrified service, and prepare the corridors for testing and potential early high-speed rail operations.
Continue Bookend Investment in Southern and Northern California: The draft business plan continues to prioritize improving Los Angeles Union Station, the Burbank to Anaheim corridor and the electrification of the Caltrain corridor in the Bay Area.
The draft business plan transparently identifies the project’s challenges, which include longer schedules and higher costs due in large part to inflation, increased contingencies and construction delays in the Central Valley.
Ad Loading...
Although high-speed rail continues to face many challenges — major progress has been made on many fronts, including:
20 active construction sites with thousands of Californians working along 119 miles in the Central Valley.
Completion of three structures.
Hundreds of businesses planning, designing and building the system — including small businesses, disadvantaged businesses and disabled veteran businesses — with more than 1,699 craft laborers dispatched to work on Central Valley construction projects.
The positive economic benefits from the program are tremendous, including $6 billion in total economic activity in California to date. Once operational, high-speed rail will breathe new life into local economies by encouraging the movements of residents and visitors between the major regions of the state like never before, while at the same time, protecting California’s environment.
Ad Loading...
“Building the nation’s first high-speed rail system, consistent with the will of the California voters, remains a tremendous challenge, but it is achievable if we remain committed to getting this transformative project done,” said Kelly.
The authority is now seeking public comment as part of a 60-day public comment period that began March 9 and closes May 7, 2018.
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.