Chicago Transit awards Red Line contract

The award includes 30% Disadvantaged Business Enterprise participation.

October 10, 2013
2 min to read


The Chicago Transit Authority (CTA) board approved awarding a contract for the new Red Line 95th Street Terminal at 95th Street/Dan Ryan station to Walsh/II in One J.V., which will serve as construction manager/general contractor at risk (CM/GC).

The $240 million project will expand and greatly improve the 95th/Dan Ryan Terminal and bring significant improvements to a bus and rail station that is a vital part of the South Side and serves about 20,000 customers each weekday.

Ad Loading...

Through this arrangement, a construction manager for the entire project is selected to begin work during the design phase of the project, rather than the typical practice of hiring a general contractor after the design of the project is completed.

The benefits include reducing the chances of project delays and cost overruns in complex, heavy civil construction projects like the 95th Street Terminal, because the CM/GC is involved in aspects of the project including resolving complicated constructability issues, materials selection and other critical logistics. It also advances the start of the project’s construction by about five months.

This form of procurement is being used for other Chicago projects including the McCormick Place West Expansion and the new Rental Car Facility at O’Hare International Airport. The same approach has been used by other U.S. transit agencies for large-scale projects, including in Boston, Dallas and Portland.

The value of the contract is not to exceed $648,000. The award includes 30% Disadvantaged Business Enterprise (DBE) participation, including II in One Contractors Inc. (20%), which will serve as a project principal, chief estimator, and estimating and DBE compliance officer for preconstruction services, and The Roderick Group Inc. (10%), which will provide design validation reviews.

Other contracting tasks include cost estimating, 3-D modeling, determining site staging/logistics and other project tasks.

Ad Loading...

The 95th/Dan Ryan Terminal is one of CTA’s busiest, with 24-hour Red Line service and more than 1,000 CTA and Pace bus trips on a typical weekday. The current configuration does not have adequate capacity to efficiently serve customers, which number around 20,000 on an average weekday.

Construction on the new 95th Street Terminal will begin in the spring of 2014 and is expected to be completed by the end of 2016. Funding is provided through a variety of federal, state and local sources.

More Management

AAAHI receiving METRO's Innovative Operator of the Year Award
Motorcoachby Alex RomanSeptember 16, 2026

METRO Opens Submissions for 2026 Motorcoach Awards

Nominations are now being accepted for METRO Magazine’s Operator of the Year and Innovative Operator of the Year awards.

Read More →
A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
Transit Leaders Gather for National Safety Summit
Security and Safetyby Alex RomanSeptember 16, 2026

Transit Agencies Highlight Safety Gains at National Summit

Leaders from 15 major transit systems shared crime-reduction results and safety initiatives while discussing the role of continued federal support.

Read More →
Ad Loading...
A blue and white graphic with text reading "NITA Names New Leadership, Expands Reduced-Fare Program."
Managementby Staff and News ReportsSeptember 14, 2026

NITA Names New Leadership, Expands Reduced-Fare Program at First Board Meeting

The new regional transit authority appointed its first board chair and interim executive director while extending reduced fares across CTA, Metra, and Pace for eligible riders.

Read More →
From Checklists to Better Outcomes
TechnologySeptember 11, 2026

Beyond the Checklist: A Structured Approach to Transit Maintenance

Reliability-Centered Maintenance helps transit agencies move beyond routine checklists to focus limited resources on the assets and failures that have the greatest impact on safety, reliability, and service.

Read More →
A red, white, and blue graphic with the APTA logo and text reading "APTA Nominates 2026-2027 Chair & Vice Chair."
Managementby Staff and News ReportsSeptember 10, 2026

APTA 2026 Nominating Committee Selects Leadership Slate, Names Chair and Vice Chair Nominees

Leadership changes will help shape the association’s priorities and its representation of the transportation industry during the 2026–2027 term.

Read More →
Ad Loading...
DART's light rail station at 8th and Corinth
Security and Safetyby Alex RomanSeptember 10, 2026

DART Launches Major Security, Fare Enforcement Initiative

The 90-day demonstration will deploy coordinated security teams at five light rail stations while testing controlled access and gathering data to guide future investments.

Read More →
STraffic White Paper Cover Learn about delivering 1300 gates at 91 stations while managing fare evasion. Explore the large scale deployment, solution customization and real-world results that affect the region. Prepare for deployment in your region now.
SponsoredSeptember 9, 2026

Advancing Fare Collection Through Technology and Innovation

Learn about delivering 1300 gates at 91 stations while managing fare evasion. Explore the large scale deployment, solution customization and real-world results that affect the region. Prepare for deployment in your region now.

Read More →
A TransLink train goes by a large FIFA World Cup soccer ball structure.
Managementby Elora HaynesSeptember 8, 2026

Game Day in Motion: Moving Millions During the 2026 World Cup

Between packed transit stations and team motorcoaches, see how agencies and operators across North America tackled the transportation demands of the 2026 FIFA World Cup.

Read More →
Ad Loading...
A blue and white graphic with text reading "Surface Transportation Averts Shutdown, Leaves Transit Funding Gap."
Managementby Elora HaynesSeptember 4, 2026

Surface Transportation Extension Averts Shutdown, Leaves Transit Funding Gap

The stopgap keeps federal transportation programs moving, but missing advance funding could complicate the transit and rail projects agencies are planning next.

Read More →