Chicago Updates All Stations Accessibility Program

The comprehensive plan was first unveiled in 2018 and is an evolving document that will be updated over time to reflect the ongoing planning, modernization, and construction work as envisioned by CTA’s capital program.

August 1, 2024
Chicago Updates All Stations Accessibility Program

The updated ASAP plan incorporates new external input, changes to project phasing, updates cost estimates, new information about additional funding sources, and various other updates to ensure the plan reflects the region’s current needs.

Photo: CTA

2 min to read


The Chicago Transit Authority (CTA) released the first update to its All Stations Accessibility Program (ASAP) Strategic Plan, reaffirming the agency’s commitment to serving customers with disabilities by becoming the first completely accessible legacy transit system within the next 20 years.

The comprehensive plan was first unveiled in 2018 and is an evolving document that will be updated over time to reflect the ongoing planning, modernization, and construction work as envisioned by CTA’s capital program.

Ad Loading...

CTA’s ASAP Plan

The updated ASAP plan incorporates new external input, changes to project phasing, updates cost estimates, new information about additional funding sources, and various other updates to ensure the plan reflects the region’s current needs.

“Since the ASAP plan launched in 2018, we have secured $740.8 million in funding and construction has begun at numerous stations,” said CTA President Dorval R. Carter Jr. “We look forward to welcoming our customers to six newly accessible CTA rail stations in 2025: Lawrence, Berwyn, Bryn Mawr, and Argyle as part of the Red Purple Modernization Project in addition to the Forest Park Branch Racine and Lake Street Line — Austin stations.”

The program is broken into four phases. Stations with higher needs and lower complexity scores were prioritized for near-term improvement plans.

More complex stations that require more time for planning, design, construction, agency coordination, and community input are listed as part of long-term project plans.

Phase One is fully funded at $423.5 million and will be completed by 2027.

Ad Loading...

Phase Two projects are currently 45% funded and projected to be completed by 2028. The total projected budget for Phase Two is $617.5 million.

The ASAP Plan

The ASAP plan exceeds federal requirements and includes the rehabilitation and/or replacement of all 162 existing station elevators, as well as enhancements to rail system signage and wayfinding to make it easier and more intuitive for people who are DeafBlind, blind, and visually impaired.

The plan also creates spaces that support riders with a range of physical, sensory, and cognitive abilities to be able to independently use CTA services.

Systemwide elevator replacement has $37 million funded to-date. It is expected that elevator replacements will also start in 2025.

While updating the plan CTA also updated the overall cost for the program. When the plan was published in 2018, the program cost was estimated at $2.1B.

Ad Loading...

The revised cost of the ASAP program is $4.9B, which is reflective of industry trends and largely the result of market conditions and cost escalation.

The CTA has not yet received funding for stations in Phases Three and Four of the project. CTA continues to seek out available funding options for remaining projects outlined in the ASAP Plan.

More Paratransit

paratransit bus
SponsoredMarch 16, 2026

Measuring the True Cost of Paratransit Fleets

What truly drives the cost of a paratransit fleet? Beyond the purchase price, seven operational factors quietly determine maintenance frequency, downtime, and long-term service reliability. This whitepaper explores how these factors shape lifecycle cost and what agencies should evaluate when selecting paratransit vehicles.

Read More →
A next-generation HART paratransit SUV.
Paratransitby StaffMarch 3, 2026

Florida's HART Launch First Next-Generation Paratransit Vehicles into Service

The new HARTPlus SUVs — 2025 Ford Interceptor Utility models — represent a significant step toward modernizing mobility and enhancing service for paratransit riders throughout Hillsborough County.

Read More →
title of the webinar over an image of a transit van on the road
SponsoredFebruary 25, 2026

The Future of Paratransit: How to Thrive in an Uncertain Era

See how leading agencies integrate eligibility, operations, staffing, and rider access to protect service and public dollars.

Read More →
Ad Loading...
SponsoredJanuary 22, 2026

5 Costly Myths About Paratransit Vehicles

What agencies often overlook when selecting vehicles.

Read More →
Busby StaffJanuary 22, 2026

Biz Briefs: BART, Uber Launch Partnership and More

Stay informed with these quick takes on the projects and companies driving progress across the transportation landscape.

Read More →
SponsoredJanuary 19, 2026

Fleet Software ROI: Boost Uptime & Safety

Transit agencies depend on safe, reliable vehicles to deliver consistent service. This eBook examines how next-generation fleet software helps agencies move from reactive processes to proactive operations through automated maintenance, real-time safety insights, and integrated data. Learn how fleets are improving uptime, safety outcomes, and operational efficiency.

Read More →
Ad Loading...
Railby Staff and News ReportsJanuary 15, 2026

Biz Briefs: Alstom Supplying TTC Subways, SilverRide Lands California Contracts, and More

Stay informed with these quick takes on the projects and companies driving progress across the transportation landscape.

Read More →
New Mobilityby Alex RomanJanuary 5, 2026

Forest River Working to Redefine Reliability, Responsibility in the Bus Industry

As the transportation landscape continues to evolve in the wake of the pandemic, few manufacturers have faced, or embraced, change as decisively as Forest River Bus.

Read More →
Managementby StaffJanuary 5, 2026

New York MTA Marks Record Year for Ridership, Performance in 2025

The subway, Long Island Rail Road, and Metro-North Railroad all recorded record-highs for on-time performance in 2025.

Read More →
Ad Loading...
A white and blue graphic with text reading "Milwaukee County Transit Plus Riders Join WisGo in 2026."
Paratransitby StaffJanuary 5, 2026

Milwaukee County Transit Plus Riders Join WisGo in 2026

Transit Plus riders gain access to WisGo cards and mobile fare payment through the Umo app in 2026.

Read More →