D.C. Metro plans multiyear project to reconstruct 20 station platforms

Will use extended shutdowns during summer months-rather than single tracking-to provide 24-hour access to work sites.

May 9, 2018
D.C. Metro plans multiyear project to reconstruct 20 station platforms

Platform condition at Metro's National Airport rail station. Photo: D.C. Metro

2 min to read


Platform condition at Metro's National Airport rail station. Photo: D.C. Metro

Washington, D.C.'s Metro is planning a three-year capital project that will reconstruct the outdoor platforms at 20 Metrorail stations to address structural deficiencies after decades of exposure to the elements.

At many of these stations, temporary measures have been installed to stabilize the platforms to ensure passenger safety until reconstruction can take place. The project is estimated to cost between $300-400 million and will be the first major construction project to benefit from dedicated capital funding recently approved by the legislatures in Virginia, Maryland and the District of Columbia.

Rebuilding platforms is heavy construction activity that requires that tracks be taken out of service to allow for demolishing existing structures, access to the construction area, and concrete pouring.

Ad Loading...

Metro has already rebuilt platforms at 10 of the system's 45 outdoor stations; however, the process used previously resulted in years of single tracking and customer inconvenience. Rebuilding the two most recently reconstructed platforms, at Minnesota Avenue and Deanwood stations, took approximately three years.

Following extensive internal planning and consultation with construction contractors with the goal of minimizing customer impact, Metro developed a program that advances the reconstruction of the next 20 platforms primarily using extended shutdowns during summer months-rather than single tracking-to provide contractors with 24-hour access to selected work sites. The approach improves safety while significantly reducing project duration because workers do not have to repeatedly set-up and break down their equipment. The approach also minimizes customer impact by allowing Metro to continue to provide normal rail service elsewhere on the system.

Under the first phase of the plan, beginning next year, Metro is planning to demolish and rebuild the station platforms at Braddock Road, King Street and Eisenhower Avenue stations, resulting in a shutdown of rail service south of Reagan National Airport during the summer of 2019.

Metro will partner with the jurisdictions and other transportation agencies to develop traffic mitigations and customer travel alternatives. Metro customers will be given at least three months of advance notice prior to any service change under the program.





More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →