D.C. Metro plans multiyear project to reconstruct 20 station platforms
Will use extended shutdowns during summer months-rather than single tracking-to provide 24-hour access to work sites.

Platform condition at Metro's National Airport rail station. Photo: D.C. Metro

Washington, D.C.'s Metro is planning a three-year capital project that will reconstruct the outdoor platforms at 20 Metrorail stations to address structural deficiencies after decades of exposure to the elements.
At many of these stations, temporary measures have been installed to stabilize the platforms to ensure passenger safety until reconstruction can take place. The project is estimated to cost between $300-400 million and will be the first major construction project to benefit from dedicated capital funding recently approved by the legislatures in Virginia, Maryland and the District of Columbia.
Rebuilding platforms is heavy construction activity that requires that tracks be taken out of service to allow for demolishing existing structures, access to the construction area, and concrete pouring.
Metro has already rebuilt platforms at 10 of the system's 45 outdoor stations; however, the process used previously resulted in years of single tracking and customer inconvenience. Rebuilding the two most recently reconstructed platforms, at Minnesota Avenue and Deanwood stations, took approximately three years.
Following extensive internal planning and consultation with construction contractors with the goal of minimizing customer impact, Metro developed a program that advances the reconstruction of the next 20 platforms primarily using extended shutdowns during summer months-rather than single tracking-to provide contractors with 24-hour access to selected work sites. The approach improves safety while significantly reducing project duration because workers do not have to repeatedly set-up and break down their equipment. The approach also minimizes customer impact by allowing Metro to continue to provide normal rail service elsewhere on the system.
Under the first phase of the plan, beginning next year, Metro is planning to demolish and rebuild the station platforms at Braddock Road, King Street and Eisenhower Avenue stations, resulting in a shutdown of rail service south of Reagan National Airport during the summer of 2019.
Metro will partner with the jurisdictions and other transportation agencies to develop traffic mitigations and customer travel alternatives. Metro customers will be given at least three months of advance notice prior to any service change under the program.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →