NJ Transit reopens terminal waiting room

It had been closed since Dec. 19, 2012, due to damage from Hurricane Sandy. Work to prepare the waiting room for reopening has included power-washing the walls; replacing heaters and heater motors; replacing electrical panels, outlets and wiring; and stripping and sealing the floors.

January 29, 2013
3 min to read


NJ Transit will reopen its Hoboken Terminal waiting room on Jan. 29, providing a heated shelter and temporary seating for customers as the agency continues with remediation work to address storm-related flood damage from Hurricane Sandy.

At the height of Hurricane Sandy, Hudson River flooding immersed the entire terminal in at least five feet of water. When the water receded, six to eight inches of mud and debris were left behind. Flooding damaged all areas of the main concourse, including the ticket office, customer service office, station operations, transportation operations, vendors and the food court.

Since December 19, 2012, the Hoboken Terminal waiting room has been closed, after NJ Transit rail operations and environmental consultants conducted a post-hurricane assessment of the terminal and determined additional remediation work was required to address mold growth. In response, NJ Transit hired remediation contractors to address mold issues throughout the terminal.

Work to prepare the waiting room for reopening has included power-washing the walls; replacing heaters and heater motors; replacing electrical panels, outlets and wiring; and stripping and sealing the floors. Remaining work includes cleaning, refinishing and resetting benches and other affected woodwork, to be performed in the near future.

In advance of the opening, NJ Transit took all necessary precautions to ensure the waiting room is safe for customers until mold remediation work can be completed. All wooden structures, including the benches, newsstand and shoe shine, will be covered in plastic and sealed, providing a barrier to the mold. Every opening to peripheral rooms, such as the ticket office and crew quarters, will also be taped and sealed in plastic to prevent mold exposure. In addition, barricades will be erected as needed.

In order to restore heating to the waiting room, NJ Transit had to procure a temporary boiler and connect it to the terminal’s intricate piping system. The previous boiler was completely inundated with water during the storm.  Because the boiler is a large, complex unit, it could not be replaced by an “off-the-shelf” unit and took considerable time to procure.

Extensive work is required to address damage in other parts of the terminal. All tenant space, including the recently constructed food court, needs to be completely gutted and rebuilt and all mold-contaminated structure elements need replacing. Similarly, the public restrooms, storage areas and crew quarters — including 550 employee lockers — must be gutted and rebuilt.

To enhance customer comfort while storm recovery work is ongoing, NJ Transit is looking into offering improved interim amenities for customers. Since Jan. 22, NJ Transit has accommodated customers in Hoboken with idling, heated trains equipped with restrooms for customer use. In addition, customers will now have access to four railcars equipped with restrooms that will be parked in the middle of the terminal.

As soon as the storm ended, NJ Transit personnel, together with the Army Corps of Engineers, the U.S. Navy, and the Federal Emergency Management Agency, responded to the site for the initial assessment of storm damage and to begin making any initial cleanup and repairs. A significant portion of the cleanup efforts began even before the water receded.

Due to Hoboken Terminal’s historic status, NJ Transit has coordinated with the State Historic Preservation Office for remediation work on areas of the terminal that have historic significance. NJ Transit is also working with the Department of Community of Affairs on inspections and permitting.

More Bus

A Coach USA Van Hool CX 45 delivered by ABC Companies.
Busby StaffApril 15, 2026

ABC Delivers Van Hools to Coach USA and More in Biz Briefs

In METRO's latest installment, we take a look at the latest news from suppliers including Moovit, CAF, and more.

Read More →
A headshot of Inez Evans Benson
Busby Alex RomanApril 15, 2026

Inez Evans Benson on Rethinking Transit Through Customer Experience

The WSP leader discusses why agencies must look beyond satisfaction metrics and take a more holistic, community-driven approach to service.

Read More →
FlixBus vehicles in a parking garage.
ManagementApril 13, 2026

Intercity Bus Industry Outlook: A Mix of Apprehension & Optimism

Industry leaders see both promise and peril ahead as intercity bus travel rebounds, but unpredictable market forces threaten to reshape the sector.

Read More →
Ad Loading...
Cover Photo for Bus Tech Talk
ManagementApril 9, 2026

Bus Tech Talk: AC Transit’s Cecil Blandon on Leadership, Mentorship, and a Career in Transit

In Part 1, Blandon shares his journey from the U.S. Marines to a leadership role in public transit, along with insights on mentorship and professional growth within the industry.

Read More →
A blurry TransLink R2 rapid bus
Managementby StaffApril 8, 2026

Vancouver's TransLink Fast-Tracks RapidBus Line to Metrotown

Funded through the 2025 Investment Plan, the new R2 Marine–Willingdon RapidBus is expected to begin service in September, more than three months ahead of schedule.

Read More →
Complete Parts logo
Busby StaffApril 1, 2026

Complete Coach Works Unveils Reimagined Parts Department with Expanded Capabilities

Complete Parts features new branding with a new logo, a new contact telephone number, a dedicated order desk, enhanced processes and inventory, all designed to provide the parts bus operations need.  

Read More →
Ad Loading...
frontrunner bus
SponsoredApril 1, 2026

Breaking Accessibility Barriers with the Low Floor Frontrunner Minibus

Accessible transit isn’t a feature—it’s a responsibility. This whitepaper explores how the Low-Floor Frontrunner is redefining mobility with a breakthrough design that removes barriers, empowers riders, and delivers measurable operational advantages for agencies. Discover why this next generation minibus is setting a new standard for inclusive transportation.

Read More →
A shot of ENC's manufacturing facility
Busby StaffMarch 31, 2026

ENC Named 'Partner of Choice' to Support Philadelphia SEPTA’s $43M FTA Grant

SEPTA was awarded $43 million in competitive grant funding from the FTA's FY25 Low and No Emission and Bus and Bus Facilities grant programs to support this procurement.

Read More →
Cover photo for Bus Tech Talk with Cecil Blandon
Managementby Alex RomanMarch 27, 2026

AC Transit’s Cecil Blandon on Leadership, Mentorship, and a Career in Transit

In part 1 of a two-part conversation, AC Transit’s director of maintenance joins co-hosts Alex Roman and Mark Hollenbeck to discuss his journey from the U.S. Marines to public transit and the role mentorship plays in developing the next generation of industry leaders.

Read More →
Ad Loading...
An MBTA bus with a passenger boarding at shelter.
Busby StaffMarch 27, 2026

MBTA Confirms Funding for Upgraded Arborway Bus Facility

When construction is complete, battery-electric buses will operate from the Arborway facility on Day One, providing cleaner, quieter, and more reliable service for riders, the MBTA said. After completion, the old facility will be demolished, and the land will be made available for redevelopment.

Read More →