NTSB releases 4th update on D.C. train crash

To date, significant work has been done to determine why the presence of train 214 was not identified on the train control circuit that allowed train 112 to crash into it. The NTSB's accident investigation is continuing, and more work is needed to fully understand why the train control system did not perform as designed.

July 30, 2009
2 min to read


The National Transportation Safety Board (NTSB) continues its investigation of the June 22, 2009, collision of two Washington Metropolitan Area Transit Authority (WMATA) trains on the Red Line in Washington, D.C.

According to a press release, the NTSB has developed the following factual information:

Ad Loading...

To date, significant work has been done to determine why the presence of train 214 was not identified on the train control circuit that allowed train 112 to crash into it. The NTSB's accident investigation is continuing, and more work is needed to fully understand why the train control system did not perform as designed.

Most of the electrical components on this system are original equipment from the mid-1970s. NTSB investigators, along with personnel from WMATA, the Federal Transit Administration, and the equipment manufacturers, are carefully examining all components to understand how any change or degradation in component performance might affect the train control system.

The train control room at Fort Totten Station contains dozens of modules for the track circuits north and south of the station. Investigators have been concentrating on the two track circuit modules for the accident site. Both of these modules contain twenty circuit boards with capacitors, resistors, and transistors. Each of these components is being tested extensively to determine component operating values, tolerances, circuit interactions, and the effect of their performance on the train control system. As part of the process for replacing impedance bonds at the site before the accident, adjustments were made to track circuit signal strength. The investigation is evaluating any effect that these track circuit adjustments may have had on the performance of track circuit modules located at Fort Totten.

The two modules that were in place at the time of the accident were removed from the Fort Totten train control room for examination by the accident investigation team at WMATA's laboratory. Two replacement modules were installed at the Fort Totten station that showed similar anomalies and they were removed and preserved for further testing. Two additional modules were then installed by WMATA at the Fort Totten station that did not display these anomalies.

The NTSB's investigation will continue at the accident site at Fort Totten, at WMATA's laboratory facility in Landover, Md., and at WMATA's Operations Control Center to determine why the automatic train control system failed to prevent the collision on June 22, 2009.

 

 

 

 

 

More Rail

A Coach USA Van Hool CX 45 delivered by ABC Companies.
Busby StaffApril 15, 2026

ABC Delivers Van Hools to Coach USA and More in Biz Briefs

In METRO's latest installment, we take a look at the latest news from suppliers including Moovit, CAF, and more.

Read More →
A photo of an Amtrak train with a logo
Technologyby StaffApril 15, 2026

Amtrak Advances Plan for New Long-Distance Fleet

The railroad has issued a formal request for proposals to manufacturers for more than 800 new passenger railcars that will serve 14 long-distance routes nationwide.

Read More →
A headshot of Inez Evans Benson
Busby Alex RomanApril 15, 2026

Inez Evans Benson on Rethinking Transit Through Customer Experience

The WSP leader discusses why agencies must look beyond satisfaction metrics and take a more holistic, community-driven approach to service.

Read More →
Ad Loading...
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Technologyby StaffApril 14, 2026

Alstom Delivers First Multilevel III NJ TRANSIT Commuter Railcar

The delivery marks the first car in a 374‑vehicle order and begins the arrival of a new generation of higher‑capacity, more reliable, and more comfortable trains for one of the country’s busiest commuter rail systems.

Read More →
A BART train on the tracks.
Railby StaffApril 13, 2026

San Francisco's BART Breaks Multiple Records for Post-Pandemic Ridership in March

BART recorded 5,403,140 exits in March, making it the highest monthly ridership since the pandemic and surpassing the previous high set in October 2025 (5,346,890 exits).

Read More →
Ribbon cutting photo celebrating SEPTA's new Ardmore Station
Railby StaffApril 13, 2026

Philadelphia's SEPTA Celebrates New Ardmore Station

The station was rebuilt as part of SEPTA’s Station Accessibility Program, making it fully ADA accessible with new elevators, ramps, and high-level platforms.

Read More →
Ad Loading...
Two Metra locomotives on rail tracks.
Railby StaffApril 10, 2026

Metra Reaches New 10-Year Agreement with BNSF

The announcement highlights the long-standing partnership between the Class I railroad and the commuter rail system, dating back to Metra's creation in 1983.

Read More →
Ribbon cutting at Siemens' new North Carolina facility.
Railby StaffApril 9, 2026

Siemens Opens North Carolina Railcar Manufacturing Facility

Site construction is complete, production is underway, and the first locally built passenger coaches are on track for delivery in Summer 2026.

Read More →
Two MBTA railcars in station.
Railby StaffApril 9, 2026

MBTA Completes Key Red Line Signal Upgrade Weeks Early

Crews completed a significant portion of the testing required before commissioning the new, digital signaling system, which will bring important upgrades that strengthen Red Line service reliability for riders and provide Red Line Operations the ability to route trains more quickly, turn trains around faster, and recover from unplanned disruptions more efficiently, said MBTA officials. 

Read More →
Ad Loading...
A Metra train on the rails
Railby StaffApril 8, 2026

Metra Reveals 2026 Construction Program

In addition to new projects, progress continues on a multiyear effort to upgrade track, electrical, and signal systems on the Metra Electric Line to accommodate the expansion of service on the South Shore Line.

Read More →