NTSB releases 4th update on D.C. train crash

To date, significant work has been done to determine why the presence of train 214 was not identified on the train control circuit that allowed train 112 to crash into it. The NTSB's accident investigation is continuing, and more work is needed to fully understand why the train control system did not perform as designed.

July 30, 2009
2 min to read


The National Transportation Safety Board (NTSB) continues its investigation of the June 22, 2009, collision of two Washington Metropolitan Area Transit Authority (WMATA) trains on the Red Line in Washington, D.C.

According to a press release, the NTSB has developed the following factual information:

Ad Loading...

To date, significant work has been done to determine why the presence of train 214 was not identified on the train control circuit that allowed train 112 to crash into it. The NTSB's accident investigation is continuing, and more work is needed to fully understand why the train control system did not perform as designed.

Most of the electrical components on this system are original equipment from the mid-1970s. NTSB investigators, along with personnel from WMATA, the Federal Transit Administration, and the equipment manufacturers, are carefully examining all components to understand how any change or degradation in component performance might affect the train control system.

The train control room at Fort Totten Station contains dozens of modules for the track circuits north and south of the station. Investigators have been concentrating on the two track circuit modules for the accident site. Both of these modules contain twenty circuit boards with capacitors, resistors, and transistors. Each of these components is being tested extensively to determine component operating values, tolerances, circuit interactions, and the effect of their performance on the train control system. As part of the process for replacing impedance bonds at the site before the accident, adjustments were made to track circuit signal strength. The investigation is evaluating any effect that these track circuit adjustments may have had on the performance of track circuit modules located at Fort Totten.

The two modules that were in place at the time of the accident were removed from the Fort Totten train control room for examination by the accident investigation team at WMATA's laboratory. Two replacement modules were installed at the Fort Totten station that showed similar anomalies and they were removed and preserved for further testing. Two additional modules were then installed by WMATA at the Fort Totten station that did not display these anomalies.

The NTSB's investigation will continue at the accident site at Fort Totten, at WMATA's laboratory facility in Landover, Md., and at WMATA's Operations Control Center to determine why the automatic train control system failed to prevent the collision on June 22, 2009.

 

 

 

 

 

More Rail

A rendering of a child looking out the window of a light rail car with a city skyline in the background.
Railby Elora HaynesJuly 15, 2026

The Heart Behind Austin's Light Rail

Why Austin Transit Partnership's Operations and Maintenance Facility could become the most important building in the city's first light rail system.

Read More →
Crowd waiting for LA Metro bus
Managementby Staff and News ReportsJuly 15, 2026

June LA Metro Ridership Surges 2 Million Year Over Year

Total June ridership increased for both weekdays and weekends. Weekday ridership was 953,820, which grew 8.4% from June 2025; Saturdays increased nearly 13% year-over-year to 708,826; and Sundays increased 7.7% to 611,534 from June 2025, according to LA Metro. 

Read More →
A rendering of a passenger train for California's High-Speed Rail project.
Railby StaffJuly 7, 2026

Keolis and SNCF Voyageurs Bring Rail Expertise to California High-Speed Rail

The CDA establishes a collaborative predevelopment partnership intended to evaluate future delivery opportunities through public-private partnership models.

Read More →
Ad Loading...
Stadler's expanded Salt Lake City facility
Railby StaffJuly 3, 2026

Stadler Marks 10 Years in the U.S. with Salt Lake City Expansion

The expansion is expected to create up to 300 new local jobs, some of which are youth apprenticeships, said Stadler officials.

Read More →
A purple MBTA train at a Mansfield Station platform.
Railby StaffJune 30, 2026

MBTA Selects STV to Support Battery-Electric Locomotive Procurement

The firm's seven-year contract includes end-to-end support from bid review and selection through procurement, production, and testing.

Read More →
California Expands Public Transit Strategy
Technologyby StaffJune 29, 2026

Executive Order Aims to Improve Transit Access Across California

The order directs state agencies to streamline transit project delivery, improve coordination, and expand access to bus and passenger rail services across California.

Read More →
Ad Loading...
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 26, 2026

California High-Speed Rail Advances Merced–Madera Construction Procurement

The procurement represents a major expansion of active high-speed rail construction.

Read More →
An Amtrak image of Penn Station with streetview.
Railby Staff and News ReportsJune 23, 2026

Amtrak Finalizes Pre-Development Agreement for Penn Station Overhaul

The agreement advances plans for a $7 billion to $8 billion transformation of New York's busiest transit hub, with construction expected to begin by the end of 2027.

Read More →
MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Ad Loading...
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →