NYCT completes rail work via service initiative

During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

January 17, 2012
2 min to read


For four consecutive weeknights hundreds of Metropolitan Transportation Authority New York City Transit (NYCT) workers labored through the late night and early morning hours cleaning, inspecting, repairing and replacing subway infrastructure on a nearly seven-mile segment of the normally busy Lexington Avenue Line.

NYCT's new FASTRACK initiative is an entirely new way to perform subway maintenance completely suspending train service over a segment of a subway line, giving workers uninterrupted access to tracks, signals, cables, lighting, third rail components and platform edges. During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

Ad Loading...

Three work trains supported nearly 70 work crews from several divisions within the Department of Subways. Work was performed in the stations along the line segment as well as the tunnels and even into the Joralemon Tube that connects Brooklyn to Manhattan.

In the planning for upwards of three months, the result was a seamless effort that saw maintenance workers specializing in different disciplines working to complete jobs and make improvements that customers would notice by the time service was resumed on the 4, 5 and 6 line for the next morning's rush period. Workers cleaned and replaced lighting fixtures, scraped dry mud from the roadbed while also removing trash and debris, as well as inspected and performed preventative maintenance on components crucial to providing safe and reliable service. They also scraped peeling paint from station ceilings and painted station areas. Rails were replaced in several areas along with a heavily utilized track switch just north of the Brooklyn Bridge Station.

Work also included inspections of equipment along the tracks; scraping and bagging of debris; replacement of tie and rail fastener plates; scraping and painting rubbing board and columns within station limits; cleaning of stations (mobile wash); cleaning of drains; and routine maintenance and performance testing of signals. All work was wrapped up and service restored to customers by 5:00 a.m. each morning.

More Rail

Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
Ad Loading...
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
Ad Loading...
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →
A TriMet MAX Light Rail vehicle overhead shot
Railby StaffFebruary 24, 2026

STV Finalizes Design for First Phase of TriMet MAX Blue Line Substation Upgrades

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

Read More →
HDR rendering of LA to Coachella Valley Rail Project
Railby StaffFebruary 20, 2026

HDR Selected to Advance LA–Coachella Valley Rail Corridor Project

The firm will lead the Tier 2 environmental review program for the Coachella Valley Rail Corridor, including the conceptual and preliminary engineering needed to develop project-level environmental clearance.

Read More →
Ad Loading...
Rendering of Austin Transit Partnership's light rail line.
Railby StaffFebruary 19, 2026

Contractor Chosen to Help Build Austin Light Rail

The ATP board’s approval of ARC enables ATP to begin pre-construction activities and advance final design for Austin Light Rail under the first phase of what will be a multibillion-dollar contract.

Read More →