NYCT completes rail work via service initiative

During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

January 17, 2012
2 min to read


For four consecutive weeknights hundreds of Metropolitan Transportation Authority New York City Transit (NYCT) workers labored through the late night and early morning hours cleaning, inspecting, repairing and replacing subway infrastructure on a nearly seven-mile segment of the normally busy Lexington Avenue Line.

NYCT's new FASTRACK initiative is an entirely new way to perform subway maintenance completely suspending train service over a segment of a subway line, giving workers uninterrupted access to tracks, signals, cables, lighting, third rail components and platform edges. During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

Ad Loading...

Three work trains supported nearly 70 work crews from several divisions within the Department of Subways. Work was performed in the stations along the line segment as well as the tunnels and even into the Joralemon Tube that connects Brooklyn to Manhattan.

In the planning for upwards of three months, the result was a seamless effort that saw maintenance workers specializing in different disciplines working to complete jobs and make improvements that customers would notice by the time service was resumed on the 4, 5 and 6 line for the next morning's rush period. Workers cleaned and replaced lighting fixtures, scraped dry mud from the roadbed while also removing trash and debris, as well as inspected and performed preventative maintenance on components crucial to providing safe and reliable service. They also scraped peeling paint from station ceilings and painted station areas. Rails were replaced in several areas along with a heavily utilized track switch just north of the Brooklyn Bridge Station.

Work also included inspections of equipment along the tracks; scraping and bagging of debris; replacement of tie and rail fastener plates; scraping and painting rubbing board and columns within station limits; cleaning of stations (mobile wash); cleaning of drains; and routine maintenance and performance testing of signals. All work was wrapped up and service restored to customers by 5:00 a.m. each morning.

More Rail

A rendering of a passenger train for California's High-Speed Rail project.
Railby StaffJuly 7, 2026

Keolis and SNCF Voyageurs Bring Rail Expertise to California High-Speed Rail

The CDA establishes a collaborative predevelopment partnership intended to evaluate future delivery opportunities through public-private partnership models.

Read More →
Stadler's expanded Salt Lake City facility
Railby StaffJuly 3, 2026

Stadler Marks 10 Years in the U.S. with Salt Lake City Expansion

The expansion is expected to create up to 300 new local jobs, some of which are youth apprenticeships, said Stadler officials.

Read More →
A purple MBTA train at a Mansfield Station platform.
Railby StaffJune 30, 2026

MBTA Selects STV to Support Battery-Electric Locomotive Procurement

The firm's seven-year contract includes end-to-end support from bid review and selection through procurement, production, and testing.

Read More →
Ad Loading...
California Expands Public Transit Strategy
Technologyby StaffJune 29, 2026

Executive Order Aims to Improve Transit Access Across California

The order directs state agencies to streamline transit project delivery, improve coordination, and expand access to bus and passenger rail services across California.

Read More →
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 26, 2026

California High-Speed Rail Advances Merced–Madera Construction Procurement

The procurement represents a major expansion of active high-speed rail construction.

Read More →
An Amtrak image of Penn Station with streetview.
Railby Staff and News ReportsJune 23, 2026

Amtrak Finalizes Pre-Development Agreement for Penn Station Overhaul

The agreement advances plans for a $7 billion to $8 billion transformation of New York's busiest transit hub, with construction expected to begin by the end of 2027.

Read More →
Ad Loading...
MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →