After a 25-day closure to allow for critical infrastructure repairs and improvement, the Port Authority of New York and New Jersey reopened the Hoboken Path Station. This closure was part of the Port Authority’s $430 million two-year PATH Forward program that seeks to improve the 117-year-old system.
By fully closing the station, the agency was able to perform expedited track and station work, which negated the need for at least a year of severe service reductions and major schedule changes.
Repairing and Refreshing the Station
As part of the station repairs, tracks and a track switch system were replaced. Additional platform and track work will be taking place in the coming weeks, which will be completed within PATH’s existing weekend and overnight schedules.
“The Hoboken station and the PATH system itself turn 117 years old this week, highlighting both its enduring importance in our transit network and its need for continued investment and care,” said Port Authority Chairman Kevin O’Toole. “We thank our riders for their patience and our regional transit partners for their coordination over the last 25 days. The critical infrastructure upgrades we’ve delivered thanks to this work will provide a more reliable commute for years to come.”
The station was closed from January 30 to February 25. During this time, rotating crews worked a total of 600 hours to complete the project. The Port Authority shared detailed progress reports following the first and second weeks of work.
The project included a refurbishment of the station’s concrete platform surface and the replacement of four steep, narrow staircases original to the station from the mezzanine to the platform level. Station walls and ceilings received fresh paint, with columns painted Lackawanna green as an homage to the train terminal’s railroad past. New tiles, lighting, and signage were also installed.
Track work included replacing the track switching system outside the station that allowed trains to move between the station’s three tracks. The previous 35-year-old- the switch was prone to mechanical issues, and the new track and switch infrastructure will lead to more reliable rides with fewer delays and disruptions.
“The massive amount of work that took place over just 25 days is a testament to the Port Authority’s commitment to modernizing a 117-year-old rail system. We thank our regional transportation partners for helping us navigate this closure, and our dedicated staff, who have volunteered their time and energy to make this challenging period as painless as possible for our customers,” said PATH Director/General Manager Clarelle DeGraffe. “We owe our PATH riders service that is safe and reliable, delivered to the best of our ability.”
During the closure, the Port Authority and its regional transit partners offered travel alternatives, including expanded cross-honored ferry service, frequent free shuttle buses to other PATH stations, and supplemental PATH, light rail, and NJ TRANSIT bus service between Hoboken and Manhattan.
February was chosen for the closure due to traditionally lower ridership numbers compared to other times of the year.
Other Aspects of PATH Forward
The PATH Forward program began with rehabilitation work at the Grove St. station in 2024, replacing floor tiles, patching and repainting work, refinishing platform columns, and installing LED lighting and electrical wiring. The Grove St. station bypasses associated with the PATH Forward work concluded ahead of schedule.
In late 2024, PATH also replaced 6,000 feet of track and installed an additional interlocking system between the Harrison and Journal Sq. Station. This improved operational flexibility and reduced the impact of delays on passengers.
The new interlocking enables PATH trains to bypass disabled trains west of the Journal Sq station, allowing for quicker resumption of service on the Newark-World Trade Center line. PATH is also completing a sea wall along the Passaic River to protect the system from flooding.
PATH Forward encompasses a series of projects that include comprehensive track repair and replacement, bridge modernization, railcars and other critical infrastructure, and rehabilitation of four major stations.
Upcoming projects in March and April 2025 include track work requiring weekend train service through the end of April to operate every 20 minutes in both directions on the Journal Sq.-33 St. via Hoboken line. PATH will run temporary supplemental service every 10 minutes between Hoboken and 33 St. in both directions.