Report says NY MTA misled public for years about subway delays

MTA said "report is more history and politics than news, focusing on rejected practices of the past while glossing over recent reforms."

February 13, 2019
Report says NY MTA misled public for years about subway delays

A new report released by the New York City Comptroller reveals that the MTA has misrepresented subway performance and delay data for years and shifted the focus from the subways’ real operational problems. Photo: Patrick Cashin/MTA

5 min to read


A new report released by the New York City Comptroller reveals that the MTA has misrepresented subway performance and delay data for years and shifted the focus from the subways’ real operational problems. Photo: Patrick Cashin/MTA

A new report released by the New York City Comptroller reveals that the MTA has misrepresented subway performance and delay data for years and shifted the focus from the subways’ real operational problems. These practices endured despite repeated warnings from agency insiders that much of the delay data released to the public was all but meaningless.

The MTA responded that the report did not recognize the progress the agency has made since 2017, Crain's New York Businessreported. Byford assumed his post in January 2018.

Ad Loading...

"We appreciate the comptroller's focus on subway performance," an MTA statement said, "but this report is more history and politics than news, focusing on rejected practices of the past while glossing over recent reforms and NYC Transit's aggressive pursuit of additional transparency and accountability."

The investigation, based on internal documents primarily prepared by the MTA’s Performance Analysis Unit, as well as interviews with key MTA officials, makes clear that a history of distorted metrics has prevented transparency into what is going on underground in the subways. More specifically, the investigation found that the MTA failed to provide clear guidance on how to identify the causes of millions of delays, relied on distorted metrics to report system progress, and hid delay data where causes were unknown.

“While the new leadership deserves credit for trying to clean things up, the MTA still has a long way to go to ensure accuracy and reliability and to regain the public’s trust,” said Comptroller Scott M. Stringer. 

The Comptroller’s investigation found:

Incomplete and Unreliable Delay Data: From mid-2015 forward, numerous in-house MTA analyses concluded that the Authority’s internal systems could not accurately identify the causes of delays and, in particular, chronically misattributed delays to “Overcrowding.” A July 2015 internal MTA memo described the methodological breakdowns in stark terms: “No policy or guidance exists on how dispatchers should properly identify the cause of a particular delay or on how delays should be assigned to incidents… Dispatchers rely on train crews to report the cause of delays, and these explanations are suspect.”

Ad Loading...

Meanwhile, in January 2016, another memo noted that “much of the delay data is incomplete or unreliable, particularly the classification/categorization of delays and the assignment of delays to particular incidents.” Despite multiple warnings, MTA officials continued for years to publicly promote misleading information around delays, resulting in the agency being portrayed in a more positive light.

Meaningless and Disappearing “Wait Assessment” Results: Throughout 2016, MTA officials repeatedly asserted that subway service was improving based on apparent increases in “Wait Assessment” scores, a metric intended to measure the reliability and consistency of train service and touted by the MTA as its most important indicator of customer service quality.

However, internal analyses obtained by the Comptroller’s Office showed MTA analysts warning that alleged improvements in “Wait Assessment” were statistically insignificant and likely the result of “sample error.” After technological advancements in data collection finally made clear that “Wait Assessment” scores had actually gotten worse, not better, the MTA quietly stopped touting the metric without ever acknowledging that the prior reporting had been incorrect, according to the report.

Hidden “Unknown” Delay Causes: For nearly a decade, the MTA further distorted its disclosures by effectively hiding delays it had chalked up internally to “Unknown” causes. Instead of publicly listing these delays simply as “Unknown” in a separate category, MTA officials folded them into other publicly identified delay causes – burying the “Unknowns” without any explanation.

In this way, in Monthly Operations Reports provided to the public and the MTA Board from 2013 through mid-2018, the MTA hid 525,710 delays internally grouped under “Unknown.”

Ad Loading...

Flaws in New Metrics: Similar to the MTA’s misattribution of “Unknown” delays, the MTA’s current reporting of “Major Incidents” – defined as any event that delays 50 or more trains – conceals critical information. Specifically, “Major Incidents” exclude a large category of service disruptions tracked internally by the MTA – “Planned Work,” which includes track and signal maintenance that regularly bogs down whole subway lines. To date, the MTA has yet to acknowledge publicly that its “Major Incidents” metric excludes such work and, as such, fails to capture what is actually going on underground.

Under New York City Transit President Andy Byford, the MTA has recently acknowledged some of these issues, introduced reforms, and begun to reduce delays. Yet the report reveals systemic deficiencies, some of which remain embedded in the MTA’s performance reporting and continue to obscure the true causes of delays.

Comptroller Stringer is calling on the MTA to:

  • Structure public reporting of delay data to maximize transparency, reliability and accountability.

  • Publicly define all delay categories, specifically indicating what each one includes and, as necessary, omits.

Ad Loading...
  • Ensure that all protocols relevant to performance reporting are formally codified in official policies and procedures, including establishing written definitions and instructions for all key terms, data categories, and work protocols.

  • Adequately train all relevant personnel on protocols relevant to performance reporting.

  • In the context of public reports of “Major Incidents,” provide the public with information about all categories of service disruptions tracked as incidents within its Subway Incident Reporting System (SIRS) that cause 50 or more delays, including specifically “Planned Work.”

  • Transparently disclose in each Monthly Operations Report and on the MTA’s subway performance dashboard, the methodologies used to calculate performance metrics, including all exceptions and revisions to those methodologies, and including methodological weaknesses.

  • Make available on the MTA’s website or through an Open Data portal each month all data in the SIRS database and any other databases relied on for public reporting.


More Management

A TransLink train goes by a large FIFA World Cup soccer ball structure.
Managementby Elora HaynesSeptember 8, 2026

Game Day in Motion: Moving Millions During the 2026 World Cup

Between packed transit stations to team motorcoaches, see how agencies and operators across North America tackled the transportation demands of the 2026 FIFA World Cup.

Read More →
A blue and white graphic with text reading "Surface Transportation Averts Shutdown, Leaves Transit Funding Gap."
Managementby Elora HaynesSeptember 4, 2026

Surface Transportation Extension Averts Shutdown, Leaves Transit Funding Gap

The stopgap keeps federal transportation programs moving, but missing advance funding could complicate the transit and rail projects agencies are planning next.

Read More →
Bus Tech Talk: Transit Tech Training...What's Changed?
Busby Alex RomanSeptember 4, 2026

Bus Tech Talk: Keeping Transit Technicians Ahead of the Technology Curve

LA Metro’s Obed Mejia discusses technician training, evolving maintenance technology, fleet replacement, and strategies for getting the most out of today’s transit fleets.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Holly Arnold
Managementby Alex RomanSeptember 2, 2026

People Movement: Holly Arnold Joins Transdev and More

In this edition, we also cover recent appointments and announcements at Pace, CamTran, MCI, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
A Chicago rail and rail car in the city.
Managementby Staff and News ReportsSeptember 1, 2026

NITA Launches New Era of Regional Transit in Chicago

The new authority replaces the RTA and brings CTA, Metra, and Pace under a strengthened regional framework for funding, planning, fares, safety, and service coordination.

Read More →
Ad Loading...
Canada-Qatar match fans underneath a TransLink SkyTrain overpass.
Managementby Elora HaynesSeptember 1, 2026

How World Cup Mobility Put Transit and Motorcoaches to the Test

Behind the seamless trips were months of planning, multimodal partnerships, and lessons agencies and operators can carry into the next mega-event.

Read More →
DART light rail and transit bus.
Managementby Staff and News ReportsAugust 31, 2026

DART Introduces Dashboard to Track Ridership Data

The initial release represents the first phase of DART’s efforts to expand access to ridership information. Additional dashboard features, data, and functionality will be introduced in future phases.

Read More →
Six people hold shovels in dirt at the SEPTA 11th Street Station ground breaking.
Managementby Staff and News ReportsAugust 31, 2026

SEPTA Breaks Ground on $44M Accessibility Upgrade at 11th Street Station

The project will add elevators and other upgrades to make the busy L station fully ADA accessible, with a yearlong closure expected to accelerate construction and save up to $3 million.

Read More →
Ad Loading...
A lineup of four public transit vehicles.
SponsoredAugust 28, 2026

FTA Opens $610M for Transit Fleet Modernization

Propane autogas gives transit agencies a reliable, funding-eligible option for fleet upgrades.

Read More →