San Francisco completes tunneling work

Two TBMs excavated and constructed the Central Subway’s 1.5 mile-long tunnels at an average pace of 40 feet per day and will be retrieved in North Beach at the site of the former Pagoda Palace Theatre on Powell Street.

June 17, 2014
San Francisco completes tunneling work

SFMTA

2 min to read


SFMTA

The San Francisco Municipal Transportation Agency (SFMTA) celebrated the completion of tunneling work for the Central Subway Project, the major extension of the Municipal Railway (Muni) Metro T Third Line.

The two 350-foot-long tunnel boring machines (TBMs) each tunneled 8,500 feet to construct two Central Subway tunnels, which will allow the T Third Line trains to travel quickly beneath SoMa, Union Square and Chinatown when the Central Subway opens in 2019, cutting travel times by more than half along the busy corridor.

Ad Loading...

The 750 ton, identical TBMs are named “Mom Chung” after Dr. Margaret “Mom” Chung, the country’s first female Chinese-American physician and a surrogate mother to thousands of veterans in World War II, and “Big Alma” after 19th century San Francisco philanthropist and socialite “Big Alma” de Bretteville Spreckels.

Mom Chung launched in June 2013 and Big Alma followed in November 2013, traveling beneath 4th Street, Stockton Street and Columbus Avenue to excavate and construct San Francisco’s first new subway tunnel in more than 30 years.

The TBMs excavated and constructed the Central Subway’s 1.5 mile-long tunnels at an average pace of 40 feet per day and will be retrieved in North Beach at the site of the former Pagoda Palace Theatre on Powell Street. Over the next few months, both Big Alma and Mom Chung will be dismantled and removed from the tunnels to be reused in tunneling efforts in other cities around the world.

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →