Two TBMs excavated and constructed the Central Subway’s 1.5 mile-long tunnels at an average pace of 40 feet per day and will be retrieved in North Beach at the site of the former Pagoda Palace Theatre on Powell Street.
The San Francisco Municipal Transportation Agency (SFMTA) celebrated the completion of tunneling work for the Central Subway Project, the major extension of the Municipal Railway (Muni) Metro T Third Line.
The two 350-foot-long tunnel boring machines (TBMs) each tunneled 8,500 feet to construct two Central Subway tunnels, which will allow the T Third Line trains to travel quickly beneath SoMa, Union Square and Chinatown when the Central Subway opens in 2019, cutting travel times by more than half along the busy corridor.
Ad Loading...
The 750 ton, identical TBMs are named “Mom Chung” after Dr. Margaret “Mom” Chung, the country’s first female Chinese-American physician and a surrogate mother to thousands of veterans in World War II, and “Big Alma” after 19th century San Francisco philanthropist and socialite “Big Alma” de Bretteville Spreckels.
Mom Chung launched in June 2013 and Big Alma followed in November 2013, traveling beneath 4th Street, Stockton Street and Columbus Avenue to excavate and construct San Francisco’s first new subway tunnel in more than 30 years.
The TBMs excavated and constructed the Central Subway’s 1.5 mile-long tunnels at an average pace of 40 feet per day and will be retrieved in North Beach at the site of the former Pagoda Palace Theatre on Powell Street. Over the next few months, both Big Alma and Mom Chung will be dismantled and removed from the tunnels to be reused in tunneling efforts in other cities around the world.
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.
Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.