Brookville completes Detroit's QLINE streetcar delivery early
The streetcars have been gradually undergoing testing in preparation for the forthcoming line opening.

A BROOKVILLE Liberty Streetcar undergoes testing procedures along Detroit-based M-1 RAIL’s QLINE in early 2017. (Photo Courtesy of M-1 RAIL)

Brookville Equipment Corp. delivered its fifth and sixth off-wire capable Liberty Streetcars to Detroit in March, wrapping up vehicle deliveries to the new QLINE streetcar line ahead of contractual delivery dates and prior to the QLINE’s recently announced May 12 start of revenue service.
Throughout the project, Brookville’s deliveries occurred an average of 57 days ahead of their contractual dates, beginning with the pilot vehicle’s arrival in September 2016. Since that time, the streetcars have been gradually undergoing testing in preparation for the forthcoming line opening.
Designed and manufactured at Brookville’s Pennsylvania manufacturing plant, the QLINE streetcar vehicles will traverse a 6.6-mile loop on Woodward without the aid of an overhead contact system (OCS) for 60 percent of the route, instead using the Liberty Streetcar’s battery onboard energy storage system (OESS).
Other key features of the 66.5-foot-long, 8-foot, 8-inch-wide vehicles include over 70 percent low-floor area, station-level passenger boarding, and the capability to comfortably transport up to 125 total passengers at a time to key business, shopping, entertainment, and dining centers along the route.
In addition to the M-1 RAIL order, Brookville has delivered Liberty Streetcars to Dallas Area Rapid Transit and is also currently under contract with the City of Oklahoma City and the City of Milwaukee for the production of similar Liberty Streetcar vehicles.
More Rail

Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →
Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet
The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.
Read More →
When Routine Fails: How Public Transit Must Adapt for the World Cup
The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.
Read More →
California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract
The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.
Read More →
Seattle's Sound Transit Launches New Sounder Railcars into Service
Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.
Read More →