The U.S. Department of Transportation released a comprehensive compliance review by the Federal Railroad Administration (FRA) concluding that the California High-Speed Rail Authority (CHSRA) is in default of the terms associated with two major federal grant agreements totaling approximately $4 billion.
The report outlines nine key findings, citing missed deadlines, funding gaps, and overly optimistic ridership projections among the project’s ongoing challenges.
Background on FRA’s Report
The 310-page report stems from a detailed investigation by Transportation Secretary Sean P. Duffy in February 2025.
The review focused on two cooperative agreements: a $929 million award issued in 2010 and a $3.07 billion grant finalized in 2024. In a letter to CHSRA CEO Ian Choudri, the FRA outlined that the agency has 37 days to formally respond to the findings, which could lead to further federal action, including potential grant termination.
Among the FRA’s central findings:
The CHSRA is facing a $7 billion funding gap for completing the Early Operating Segment (EOS), and it has “no credible plan to close it.”
The agency has missed key deadlines, including finalizing its rolling stock procurement.
It lacks adequate budget contingency for anticipated contractor claims and change orders.
The project's current scope is unlikely to meet 2033 completion commitments laid out in the federal agreements.
Ridership projections have been significantly overrepresented, and the project now risks connecting endpoints far removed from the proposed initial metropolitan links.
“Given CHSRA’s past performance and risk profile, there is no viable path to completing the EOS by 2033,” the FRA report stated. It also flags the agency’s dependence on uncertain non-federal funding sources and limited capacity to manage large-scale infrastructure.
Transportation Secretary Duffy emphasized fiscal responsibility: “This report makes clear that CHSRA is far from delivering the vision it promised to taxpayers. If it cannot meet its commitments, it may be time to redirect these funds to projects better positioned to deliver meaningful high-speed rail infrastructure.”
About California’s High-Speed Rail Project
The California High-Speed Rail project, envisioned as the nation’s first true high-speed rail corridor, has faced mounting scrutiny amid rising construction costs, scope reductions, and shifting timelines in recent years.
The FRA said that despite receiving approximately $6.9 billion in federal funds over 15 years, the project has yet to complete any high-speed segments or deliver full-service rail operations.
As METRO Magazine has previously reported, CHSRA has defended its progress in advancing foundational infrastructure in California’s Central Valley. Construction activity has continued amid ongoing challenges with third-party coordination, land acquisition, and state-level funding certainty. The FRA’s findings now cast further uncertainty over the timeline and scope of what was once billed as a transformative national infrastructure initiative.
The CHSRA is expected to issue a formal response in the coming weeks. The FRA’s final decision could have broad implications for the future of high-speed rail development in the U.S.