The Federal Railroad Administration (FRA) released a status update regarding railroads’ self-reported progress toward full implementation of positive train control (PTC) systems as of Dec. 31, 2018.
All required railroads either met the statutory deadline for fully implementing PTC systems, or submitted requests demonstrating they met or exceeded the statutory criteria for an alternative schedule provided for by law, permitting up to two additional years to complete full implementation.
Ad Loading...
Based upon the latest self-reported data, current as of the end of 2018, four railroads have fully implemented PTC systems on their required main lines, and all other railroads subject to the Congressional PTC mandate satisfied the six statutory criteria necessary to qualify for an extension.
Notably, Quarter Four data also show PTC systems are in operation on almost 46,000 of the nearly 58,000 route miles where the technology systems must be deployed, and PTC systems are in revenue service demonstration on an additional 288 route miles.
By the end of 2018, all necessary PTC system hardware had been installed, radio spectrum acquired, employees trained, and testing initiated. The key remaining steps for full implementation include conducting revenue service demonstration (advanced testing on the general rail system), submitting a PTC Safety Plan, and obtaining PTC System Certification from FRA, achieving interoperability between host railroads and tenant railroads, and activating the PTC system so it governs all operations on the required main lines.
As of Dec. 2018, host railroads’ operations are governed by a PTC system on 83% of the freight railroad route miles subject to the mandate and 30% of the required passenger railroad route miles. Of approximately 233 host-tenant railroad relationships, 16% have reportedly achieved PTC system interoperability as of Dec. 31, 2018, which means the locomotives of a host railroad and a tenant railroad operating on the same main line can communicate with and respond to the PTC system, including uninterrupted movements over property boundaries. In addition, FRA has conditionally certified 12 host railroads’ PTC systems, based on their PTC Safety Plans; two PTC Safety Plans are currently under review; and 23 additional PTC Safety Plans must be submitted by June 2020.
Earlier this month, FRA convened the first of six PTC Collaboration Sessions planned through 2020 with all railroads responsible for implementing PTC under the congressional mandate, and major industry associations. At the session, FRA safety specialists outlined major steps the industry must accomplish within the next two years. In addition, FRA explained its approach to certifying railroads’ PTC systems and answered technical questions.
Ad Loading...
As of Dec. 31, 2018, 33 railroads had submitted a written notification formally requesting FRA’s review and approval of an alternative schedule and sequence, and as of Feb. 11, 2019, FRA has formally approved 25 requests. FRA’s decision letters are available in railroads’ public PTC dockets.
The latest data show significant progress from just a year earlier when 15 railroads were considered “at risk” of not implementing PTC or qualifying for an extension. In 2018, FRA made $250 million in grant funding available for PTC implementation, and now four railroads — the Port Authority Trans-Hudson, North County Transit District, Portland & Western Railroad, and the Southern California Regional Rail Authority (Metrolink) — have self-reported that they fully implemented an FRA-certified and interoperable PTC system on all their required main lines.
While their comprehensive analysis of bus stops focused on Massachusetts, the researchers are excited about the generalizability of the findings and application to other locations.
Transit agencies depend on safe, reliable vehicles to deliver consistent service. This eBook examines how next-generation fleet software helps agencies move from reactive processes to proactive operations through automated maintenance, real-time safety insights, and integrated data. Learn how fleets are improving uptime, safety outcomes, and operational efficiency.
The new filters include substantially more activated carbon than traditional HVAC filters, which is especially helpful in providing a better transit riding experience for vulnerable populations, particularly children, seniors, and people with chronic illnesses, according to the CTA.
MCTS officials said the new pilots are part of a broader commitment to improving the rider experience through proactive, visible safety strategies that balance enforcement with customer support.
In a recent episode of METROspectives, LYT CEO Timothy Menard discusses how artificial intelligence, cloud connectivity, and real-time data are transforming traffic management, boosting bus reliability, and enabling system-wide transit optimization across cities.
METRO’s People Movement highlights the latest leadership changes, promotions, and personnel news across the public transit, motorcoach, and people mobility sectors.
In this latest episode of METROspectives, we explore the evolving role of transit standards, including how they're responding to emerging technologies, climate change, and the growing need for equity and sustainability.
USDOT found the Chicago Transit Authority’s safety plan insufficient to safeguard commuters on buses and rail, as crime on Chicago transit approaches a decade-high.