Rendering of the street level concourse area of the Berryessa BART Station, which is part of Phase I of the project that began construction in April 2012 and is expected to be completed in fall 2017.
2 min to read
Rendering of the street level concourse area of the Berryessa BART Station, which is part of Phase I of the project that began construction in April 2012 and is expected to be completed in fall 2017.
The Federal Transit Administration (FTA) has given Valley Transit Authority (VTA) the green light to to enter the six-mile Bay Area Rapid Transit (BART) Silicon Valley Phase II Extension into the Project Development phase of the Federal New Starts funding program. This milestone signifies that VTA has “pre-award authority” to incur costs to advance engineering and design activities to support the environmental review process.
Activities related to the Project Development phase are necessary to refine a cost estimate and financial plan for the project. VTA must complete a number of activities during this phase which include: clearly defining the project scope after performing an alternatives analysis, known as selecting a locally preferred alternative; identifying a funding plan which is necessary for the project to be included in the regional long range transportation plan; and completing the environmental review process.
Ad Loading...
Phase II of VTA’s BART Silicon Valley Project consists of four stations and a five-mile tunnel through downtown San Jose, completing the 16-mile extension and vital transit solution to highly congested and constrained I-880 and I-680 corridors.
April 2016 marks four years of progress on VTA's BART Silicon Valley Berryessa Extension (Phase I). Just over eighty percent of the construction contract to build the line, track, stations and systems is complete. By spring next year, BART (operator) is expected to begin to test trains on the newly built 10-mile segment. The two station campuses at Milpitas and Berryessa have been visibly taking shape over the past year. A long list of completed milestones related to the eleven grade crossings in the corridor, part of the fully-grade separated $2.3 billion transportation investment, are also keeping the project months ahead of schedule and trending under budget. BART Phase I is expected to be carrying passengers by fall 2017.
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.
Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.