Rendering of the street level concourse area of the Berryessa BART Station, which is part of Phase I of the project that began construction in April 2012 and is expected to be completed in fall 2017.
2 min to read
Rendering of the street level concourse area of the Berryessa BART Station, which is part of Phase I of the project that began construction in April 2012 and is expected to be completed in fall 2017.
The Federal Transit Administration (FTA) has given Valley Transit Authority (VTA) the green light to to enter the six-mile Bay Area Rapid Transit (BART) Silicon Valley Phase II Extension into the Project Development phase of the Federal New Starts funding program. This milestone signifies that VTA has “pre-award authority” to incur costs to advance engineering and design activities to support the environmental review process.
Activities related to the Project Development phase are necessary to refine a cost estimate and financial plan for the project. VTA must complete a number of activities during this phase which include: clearly defining the project scope after performing an alternatives analysis, known as selecting a locally preferred alternative; identifying a funding plan which is necessary for the project to be included in the regional long range transportation plan; and completing the environmental review process.
Ad Loading...
Phase II of VTA’s BART Silicon Valley Project consists of four stations and a five-mile tunnel through downtown San Jose, completing the 16-mile extension and vital transit solution to highly congested and constrained I-880 and I-680 corridors.
April 2016 marks four years of progress on VTA's BART Silicon Valley Berryessa Extension (Phase I). Just over eighty percent of the construction contract to build the line, track, stations and systems is complete. By spring next year, BART (operator) is expected to begin to test trains on the newly built 10-mile segment. The two station campuses at Milpitas and Berryessa have been visibly taking shape over the past year. A long list of completed milestones related to the eleven grade crossings in the corridor, part of the fully-grade separated $2.3 billion transportation investment, are also keeping the project months ahead of schedule and trending under budget. BART Phase I is expected to be carrying passengers by fall 2017.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.
The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.
The firm will lead the Tier 2 environmental review program for the Coachella Valley Rail Corridor, including the conceptual and preliminary engineering needed to develop project-level environmental clearance.
The ATP board’s approval of ARC enables ATP to begin pre-construction activities and advance final design for Austin Light Rail under the first phase of what will be a multibillion-dollar contract.