L.A. Metro begins tunneling on first section of Purple Line extension

Twin tunnel boring machines will begin by tunneling parallel underground sections between the future Wilshire/La Brea Station and the current Wilshire/Western Purple Line terminus.

October 17, 2018
L.A. Metro begins tunneling on first section of Purple Line extension

Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.

L.A. Metro

2 min to read


Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.

L.A. Metro

In a major milestone for construction of the first section of the Metro Purple Line Extension Project, the Los Angeles County Metropolitan Transportation Authority (Metro) began tunneling work underneath Wilshire Boulevard and La Brea Avenue. 

Twin tunnel boring machines (TBMs), named Elsie and Soyeon, will begin by tunneling parallel underground sections between the future Wilshire/La Brea Station and the current Wilshire/Western Purple Line terminus. The TBMs each weigh 1,200 tons, are 450 feet long, have a diameter of 21.8 feet, and will simultaneously be excavating approximately 60 feet per day in the twin tunnels over the next two years.

Ad Loading...

The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet. The two machines will be separated by about 16 feet of soil as their giant cutter heads spin to grind away the soil in their path. Meanwhile, hydraulic arms at the rear of the machines are inserting concrete segments into the newly mined tunnels, which also help propel the machines further forward.

Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega. The $2.82-billion project section is funded by Measure R and federal funds. Stantec will lead management of the construction of this section.

The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet.

L.A. Metro

The first section of the Purple Line Extension Project is scheduled to be operational in 2023 with the second section to Century City in 2025, and the third and final section to the Westwood/VA Hospital in 2026. When complete, the Purple Line will speed transit riders between downtown L.A. and Westwood in 25 minutes, with other stations at Wilshire/Rodeo in Beverly Hills, Century City/Constellation in Century City, and Westwood/UCLA and the Westwood/VA Hospital in Westwood. The subway extension is projected to serve 59,000 riders daily — including 17,000 new riders.

“The Purple Line Extension Project is an important part of Metro’s ambitious plan to improve and expand mobility throughout Los Angeles County and will serve our region’s second-largest job center,” said Metro CEO Phillip A. Washington. “This is one of the most significant transit projects we plan to deliver to the public before the Summer Olympic and Paralympic games arrive in Los Angeles in 2028.”

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →