L.A. Metro begins tunneling on first section of Purple Line extension
Twin tunnel boring machines will begin by tunneling parallel underground sections between the future Wilshire/La Brea Station and the current Wilshire/Western Purple Line terminus.
Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.
L.A. Metro
2 min to read
Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.
L.A. Metro
In a major milestone for construction of the first section of the Metro Purple Line Extension Project, the Los Angeles County Metropolitan Transportation Authority (Metro) began tunneling work underneath Wilshire Boulevard and La Brea Avenue.
Twin tunnel boring machines (TBMs), named Elsie and Soyeon, will begin by tunneling parallel underground sections between the future Wilshire/La Brea Station and the current Wilshire/Western Purple Line terminus. The TBMs each weigh 1,200 tons, are 450 feet long, have a diameter of 21.8 feet, and will simultaneously be excavating approximately 60 feet per day in the twin tunnels over the next two years.
Ad Loading...
The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet. The two machines will be separated by about 16 feet of soil as their giant cutter heads spin to grind away the soil in their path. Meanwhile, hydraulic arms at the rear of the machines are inserting concrete segments into the newly mined tunnels, which also help propel the machines further forward.
Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega. The $2.82-billion project section is funded by Measure R and federal funds. Stantec will lead management of the construction of this section.
The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet.
L.A. Metro
The first section of the Purple Line Extension Project is scheduled to be operational in 2023 with the second section to Century City in 2025, and the third and final section to the Westwood/VA Hospital in 2026. When complete, the Purple Line will speed transit riders between downtown L.A. and Westwood in 25 minutes, with other stations at Wilshire/Rodeo in Beverly Hills, Century City/Constellation in Century City, and Westwood/UCLA and the Westwood/VA Hospital in Westwood. The subway extension is projected to serve 59,000 riders daily — including 17,000 new riders.
“The Purple Line Extension Project is an important part of Metro’s ambitious plan to improve and expand mobility throughout Los Angeles County and will serve our region’s second-largest job center,” said Metro CEO Phillip A. Washington. “This is one of the most significant transit projects we plan to deliver to the public before the Summer Olympic and Paralympic games arrive in Los Angeles in 2028.”
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.
Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.