M-1 completes first phase of streetcar construction
Construction Manager/General Contractor Stacy and Witbeck Inc., in partnership with the Michigan Department of Transportation and local construction companies and suppliers, began construction of the downtown portion of the rail system in late July
A rendering of the M-1 project.
M-1 RAIL completed its first phase of construction in downtown Detroit in time for America’s Thanksgiving Parade. After the floats, clown corps and spectators have departed on Thursday, vehicle traffic will once again be able to travel the downtown stretch of Woodward Avenue.
“We had an aggressive schedule, along with a high standard for maintaining a clean and safe work site; and our skilled construction crews rose to the challenge,” said Paul Childs, M-1 RAIL chief operating officer. “We’re pleased to be ready to kick off the holiday season in Detroit.”
Ad Loading...
Construction Manager/General Contractor Stacy and Witbeck Inc., in partnership with the Michigan Department of Transportation (MDOT) and local construction companies and suppliers, began construction of the downtown portion of the rail system in late July. Several Detroit-based firms, including Hart & Associates Construction and Farrow Group have been part of the construction.
After securing the work zone and erecting pedestrian fencing and bridges, detailed surveying was performed by crews prior to moving in heavy machinery to remove layers of asphalt and concrete to make way for the new track slabs. Over the course of four months in downtown, crews:
Installed electrical and telecommunications conduit
Received and welded steel track into 560-foot sections, then moved it onto Woodward Ave.
Reinforced the steel track with an elastromeric grout pad or “rubber boot,” which provides vibration dampening and noise reduction.
Ad Loading...
Strengthened the imbedded rail with special thermite rail welds.
Built and installed a supportive rebar substructure over the track to better support the concrete.
Poured, levelled and texturized a high-performance, faster-curing type of concrete.
Removed layers of old asphalt, and then resurfaced with high-quality asphalt.
Installed granite curbs, reinforced manholes and completed temporary pavement striping.
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.
Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.