All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.
Metrolink
3 min to read
All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.
Metrolink
The Federal Railroad Administration (FRA) released a status update reflecting railroads’ self-reported progress toward fully implementing positive train control (PTC) systems as required by Congress.
Based upon railroad’s First Quarter 2019 PTC Progress Reports submitted to FRA by April 30, those required to implement PTC continue to make significant progress toward its full implementation on the required main lines. As of March 31, PTC systems were in operation on almost 48,050 of the nearly 58,000 route miles subject to the statutory mandate — a 3% increase from last quarter. Also, railroads are conducting advanced field testing, known as revenue service demonstration (RSD), on an additional 341 route miles.
With approximately 19 months remaining until the statutory implementation deadline, FRA continues to conduct comprehensive and vigorous regulatory oversight of railroad efforts to meet it. It is doing so by providing technical assistance to all host and tenant railroads, and coordinating with PTC system component suppliers and vendors.
All 41 railroads subject to the statutory mandate complied with the law by either fully implementing a PTC system by Dec. 31, 2018, or demonstrating they qualified for FRA approval of an alternative schedule, permitting up to two additional years to finish fully implementing PTC systems on all their required main lines.
Specifically, four railroads had fully installed PTC and 37 others sufficiently demonstrated they met or exceeded the six statutory criteria necessary to qualify for an alternative schedule.
All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.
With all necessary PTC system hardware installed, spectrum acquired, and testing having been initiated, the key remaining steps for full implementation include: (1) conducting RSD of uncertified PTC systems on the general rail network; (2) submitting a PTC Safety Plan and obtaining PTC System Certification from FRA (host railroads only); (3) achieving interoperability between host railroads and tenant railroads; and (4) activating the PTC system so it governs all operations on the required main lines. FRA has also developed a new set of graphics to track railroad progress, focusing on each of these significant remaining elements of full implementation.
A key requirement of the original statutory mandate is interoperability, meaning the controlling locomotives and cab cars of any host railroad and tenant railroad operating on the same main line will communicate with and respond to the PTC system, including uninterrupted movements over property boundaries.
In April, FRA sent a letter to each freight, non-Class I tenant railroad that operates on at least one main line subject to the mandate, emphasizing the importance of timely implementation, and inviting them to meet with FRA in Washington, D.C., this summer. FRA plans to meet individually with each tenant railroad to offer technical assistance with respect to PTC system implementation. On June 5, FRA will host the second PTC Collaboration Session to share best practices with industry and jointly address any challenges.
The Plan is CTA's formal response to an FTA Special Directive issued in December and details how the agency will significantly expand the law enforcement surge it launched.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
During a safety blitz, Metra employees will visit one of the railroad’s 243 stations during the morning rush hour, distributing educational materials on train and grade-crossing safety, answering questions, and listening to riders’ safety concerns.
Operated in partnership with Tech Valley Security, trained CDTA Ambassadors will be on select routes and will rotate throughout CDTA’s route network. Their presence is intended to provide customers with an approachable, visible resource focused on assistance and engagement.
Customers have always been able to report concerns through the CATS Customer Service line or the “Report a Problem to CATS” feature in the CATS-Pass mobile app; however, CATS has also integrated a Text-a-Tip line, giving riders multiple, easy-to-use channels to get support.