S.F. MTA begins phase 2 of light rail project
The $9.3 million utility relocation, to be completed by Synergy Project Management Inc, is expected to continue through June 2012.
The San Francisco Municipal Transportation Agency (SFMTA), which operates the Municipal Railway (Muni), and contractor Synergy Project Management Inc, will begin utility relocation for the Union Square/Market Street area on Jan. 31. This will require relocating all underground utilities from the street to underneath the sidewalks along Stockton Street.
The “Utility Relocation & Moscone Station Portal contract” was awarded to Synergy Project Management Inc., a San Francisco company, for $9.3 million.
The SFMTA anticipates that construction on Stockton Street and on nearby streets will continue through June 2012. The Central Subway utility relocation is part of the $1.58 billion Central Subway project, Phase 2 of the Third Street Light Rail Project.
The Union Square utility relocation work includes moving underground utilities from under the street to under the sidewalk. Sidewalks along Stockton Street will be removed in phases for this work. At the end of the utility relocation work, the sidewalks will be restored with temporary standard city concrete sidewalks in anticipation of the future Central Subway Union Square station construction. The removal of utilities from underneath the street allows for the future excavation of the subway station without impacting utility service for nearby residents and businesses.
The first section of the utility relocation began with 4th Street last January. The finishing work on that portion of the project between Bryant and Howard streets will be completed by the end of April. This work prepares the street and surrounding area for the construction of the Moscone Station and the subway portal under I-80.
The Central Subway has received $72 million in New Starts federal funding to date. Environmental clearance of the project was granted by the FTA in November 2008, while approval to begin final design was granted last January. The total project cost (with contingency) is expected to be $1.57 billion, with the federal government contributing close to $1 billion. The Central Subway is scheduled to open to the public in 2018.
More Rail

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements
The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.
Read More →
STraffic Expands North American Presence with Fare Collection Technology
John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.
Read More →
Study: Denver RTD Generates $2.1 Billion in Annual Economic Activity
An economic impact study finds the agency supports approximately 17,500 jobs, delivers $1.6 billion in annual community and mobility benefits, and generates $2.42 in economic value for every dollar invested.
Read More →
Mark Aesch Nominated to Lead Federal Transit Administration
The former Rochester transit chief and TransPro founder, who has also contributed to METRO Magazine, brings decades of industry experience and a focus on performance, accountability, and financial sustainability to the nomination.
Read More →
Transit Expands Agency Partnerships, Reaching 200 Official App Partners
COO Jake Sion discusses Transit’s growth, the success of its Transit Royale program, and how technology is helping agencies improve the rider experience.
Read More →
Trinity Metro Breaks Ground on $270M TEXRail Extension
The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.
Read More →
Bringing Austin’s First Light Rail System to Life
Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.
Read More →
Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail
The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.
Read More →
Amtrak Completes First Street Tunnel Upgrades, Restores Service
The nine-day construction project included replacing aging track infrastructure and modernizing switch systems near Washington Union Station.
Read More →
FRA Announces $2.3B for Passenger, Freight Rail Projects Nationwide
The CRISI Grant Program funding will support rail infrastructure improvements, safety upgrades, and projects aimed at improving freight and passenger rail service across 45 states and Washington, D.C.
Read More →