Officials: MBTA Orange Line Work 82% Complete

Crews have worked tirelessly to finish tie replacement work between the Dana Bridge and Community College station with current tie replacement work taking place at the North Station portal, which began on September 9.

by Staff
September 13, 2022
Officials: MBTA Orange Line Work 82% Complete

As of this week’s reporting, 82% of the planned work on the MBTA's Orange Line has been completed.

Credit:

MBTA

3 min to read


Boston’s MBTA GM Steve Poftak announced 82% of the work taking place along the Orange Line is complete and track work taking place between Dana Bridge and North Station will allow for the removal of three more slow zones, which will bring the total number of slow zones removed to five.

Work taking place in this area includes track and tie replacement, rail installation, track alignment, and tamping. Crews have worked tirelessly to finish tie replacement work between the Dana Bridge and Community College station with current tie replacement work taking place at the North Station portal, which began on September 9. Tie replacement work involves crews operating hi-rail heavy equipment to remove old ties and install new ties. The critical tie replacement will remove three of the six slow zones that the T aims to address during the shutdown. Crews have already completed work to remove slow zones at Jackson Square and between Downtown Crossing and State. Finishing this important work and removing these slow zones allows for faster, more reliable service for Orange Line riders.

Ad Loading...

MBTA is letting Orange Line riders know that, when Orange Line trains begin running again on Monday, September 19, slow zones will continue to be in place temporarily for about one week where the work was performed. In the rail industry, after new track and ballast installation, and due to the amount of track area disturbed during work, it is a given that slow zones need to temporarily remain in place. This is because it takes time for the new track and ballast to “settle” as trains repeatedly run over these areas.

Additionally, 64 new Orange Line cars are now available when service resumes, supporting riders during peak commuting periods. This is up from 30 cars when the Orange Line shutdown first started. This is also over a full complement of new Orange Line cars ready to serve riders.

As of this week’s reporting, 82% of the planned work has been completed.

Overall, teams have completed approximately 65% of rail replacement and 90% of track replacement. The full depth track replacement includes the ballast, ties, and rail.

About 99% of the special track work is complete. The special track renewal work includes replacing things like crossover areas.

Ad Loading...

About 99% of Cologne eggs and rail fastener work is finished near Tufts Medical Center station. Cologne eggs are the fasteners that allow crews to directly affix rail to the concrete pads, which are also utilized on certain parts of the Orange Line. The MBTA is in the process of installing the final five new eggs with 395 fully complete.

There has also been excellent progress on the ongoing signal testing at Oak Grove and Malden Center stations with about 84% of these signal upgrades complete.

More Rail

A view looking down the rail across the new Portal North Bridge.
Railby Staff and News ReportsMarch 13, 2026

NJ Transit, Amtrak Prepare to Open First Track on New Portal North Bridge

The new bridge will begin carrying passenger trains on March 16, replacing a 116-year-old swing bridge that has long caused delays.

Read More →
Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Ad Loading...
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
Ad Loading...
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →
A TriMet MAX Light Rail vehicle overhead shot
Railby StaffFebruary 24, 2026

STV Finalizes Design for First Phase of TriMet MAX Blue Line Substation Upgrades

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

Read More →
Ad Loading...
HDR rendering of LA to Coachella Valley Rail Project
Railby StaffFebruary 20, 2026

HDR Selected to Advance LA–Coachella Valley Rail Corridor Project

The firm will lead the Tier 2 environmental review program for the Coachella Valley Rail Corridor, including the conceptual and preliminary engineering needed to develop project-level environmental clearance.

Read More →