Amtrak announces summer New York infrastructure renewal work

The total cost of the projects is estimated between $45 and $50 million, which will keep this important infrastructure in a state of good repair for Amtrak and benefit New York State with an upgraded, state-of-the art railroad.

April 11, 2018
Amtrak announces summer New York infrastructure renewal work

 

2 min to read


Amtrak will continue its Infrastructure Renewal program at New York Penn Station during Summer 2018 by performing critical reconstruction of three major railroad infrastructure assets in New York City: The Empire Tunnel and the Spuyten Duyvil Bridge, which provides train access between Upstate New York and New York Penn Station, as well as renewal work on Track 19 in New York Penn Station that will help provide commuters with more reliable service. The total cost of the projects is estimated between $45 and $50 million, which will keep this important infrastructure in a state of good repair for Amtrak and benefit New York State with an upgraded, state-of-the art railroad.

Due to the work on the Empire Connection and Spuyten Duyvil Bridge, Empire Service, Ethan Allen Express, Adirondack, and Maple Leaf trains will all be rerouted from New York Penn Station to Grand Central Terminal between May 26 to Sept. 4. The Lake Shore Limited will only operate between Boston and Chicago, with New York City and Hudson Valley customers connecting from Empire Service trains at Albany-Rensselaer.

Ad Loading...

While the schedules have yet to be finalized, there will be fewer service impacts and schedule changes compared to summer 2017. The work on Track 19 will occur between June 8 to July 20. The modified schedule Amtrak announced in January 2018 will continue until the work on Track 19 is complete.

“Amtrak is continuing to prioritize updating the infrastructure in and around New York Penn Station to improve our service reliability,” said Amtrak Executive VP/COO Scot Naparstek. “We thank our partners for their coordination and flexibility as we continue this important and necessary work.”

Specifics of the work include:

  • Empire Connection – Amtrak will be replacing track in the Empire Tunnel, as well as replacing cross ties, grade crossings and 8,000 feet of continuous rail, including the track between the tunnel and the Spuyten Duyvil Bridge.

  • Spuyten Duyvil Bridge – Amtrak will be updating the bridge’s mechanical and electrical equipment, which was corroded by Hurricane Sandy.

  • Track 19 at New York Penn Station – Amtrak will replace three turnouts and conduct total ballasted track and wood tie track replacement.

While Amtrak has maintained and repaired this aging infrastructure, some of which dates to the 1970s, full replacement is now required. During the summer of 2017, Amtrak kicked off its Infrastructure Renewal at New York Penn Station, and continued it in early 2018. The Infrastructure Renewal program is one element of Amtrak’s plan to modernize stations, infrastructure, and equipment on the Northeast Corridor.

More Rail

MTA and ASCE officials at plaque celebrating earning the New York Metropolitan Historic Civil Engineering Landmark designation.
Railby StaffMay 15, 2026

New York MTA's Hugh L. Carey Tunnel Lands ASCE Landmark Status

The Hugh L. Carey Tunnel is the fourth MTA-owned property to be granted landmark status by the ASCE.

Read More →
Cover photo for METROspectives with HDR's Brian Buchanan
Managementby Alex RomanMay 15, 2026

Managing Complexity: HDR’s Brian Buchanan on Delivering Major Transit Programs

HDR’s transit program management lead discusses the challenges of overseeing large capital projects, adapting to cost and supply chain pressures, and the capabilities agencies need to build for the future.

Read More →
Operation Lifesaver rail safety grant graphic displayed over railroad tracks, highlighting federal funding for crossing safety and trespass prevention campaigns.
Railby News/Media ReleaseMay 14, 2026

Operation Lifesaver Awards Nearly $198,000 in Rail Safety Grants

Operation Lifesaver and the FHWA awarded nearly $198,000 in grants to 10 state programs for rail safety education campaigns focused on crossing safety, trespass prevention, and public awareness initiatives.

Read More →
Ad Loading...
STV's Garo Hovnanian
Managementby Alex RomanMay 13, 2026

The Expanding Role of Advisory in Transit Delivery

Garo Hovnanian explores how agencies can better navigate competing priorities, strengthen decision-making, and prepare for a future shaped by electrification and emerging mobility.

Read More →
An image of empty railroad tracks in Minnesota with white text reading "Federal Railroad Administration Finalizes Rail Rules Aimed at Efficiency and Safety."
Railby Staff and News ReportsMay 13, 2026

Federal Railroad Administration Finalizes Rail Rules Aimed at Efficiency and Safety

See what deregulatory rail rules were finalized to reduce outdated requirements, support innovation, and streamline rail operations without compromising safety.

Read More →
An NJ TRANSIT bus.
Managementby StaffMay 13, 2026

NJ TRANSIT to Expand Cleanliness, Safety, and Accessibility Under New Action Plan

The plan includes investments in cleaner vehicles and upgraded stations, NJT LiveView to provide real-time GPS tracking of train and light rail service, enhanced safety initiatives through a new Real Time Crime Center, and the debut of a redesigned NJ TRANSIT mobile app.

Read More →
Ad Loading...
METRO Biz Briefs cover photo

STV Launches Power Practice and More in Biz Briefs

In METRO's latest installment, we take a look at the latest news from SilverRide, Complete Coach Works, and more.

Read More →
Local, Federal, State, and LA Metro officials at the opening of the D Line.
Railby StaffMay 10, 2026

LA Metro Opens D Line Extension

The only new subway opening in the US this year, the D Line Extension represents one of Metro’s top transit priorities and a historic milestone for Los Angeles, with Sections 2 and 3 set to open in 2027.

Read More →
Governor Moore in a ceremony placing the last track
Railby StaffMay 8, 2026

Maryland Governor Installs Final Purple Line Rail During Tour

The moment marks the completion of 193,100 feet of track linking Prince George’s and Montgomery counties.

Read More →
Ad Loading...
PATCO's New Control Center
Managementby StaffMay 7, 2026

PATCO Opens New Operations Control Center

The new center serves as the central hub for monitoring and managing PATCO train operations, communications, customer service coordination, incident response, and overall operational oversight across the transit system.

Read More →