Caltrain negotiates extension for electrification project

While the agency awaits a decision from the FTA about the execution of a $647 million funding agreement.

March 1, 2017
Caltrain negotiates extension for electrification project

 

3 min to read


Caltrain announced that it has negotiated an extension of the deadline for contractors to begin construction of the Peninsula Corridor Electrification Project while the agency awaits a decision from the Federal Transit Administration about the execution of a $647 million funding agreement.

The contractors agreed to extend the deadline for four months, from March 1 to June 30. Last week, FTA announced that execution of the grant would be delayed until the President makes decisions about the availability of funds in the Administration’s upcoming budget proposal to Congress. The extension is needed to preserve the electrification project’s contracts during this time. 

Ad Loading...

The extension does not come without cost implications. Buying additional time from the contractors will likely require the utilization of up to $20 million in project contingency that otherwise would have been available for construction related expenses in the future. The sooner the grant agreement is executed, the smaller the impact will be to the project’s contingency.

Caltrain has been working with the FTA since 2009 to ensure that the project meets all of the rigorous statutory and regulatory requirements of the Core Capacity competitive discretionary program. The project was rated highly after thorough evaluation including ridership studies, design assessments, financial analyses and cost benefit evaluations by the FTA and the U.S. Department of Transportation (USDOT). Caltrain, as the project sponsor, also has significant local financial support for this project, demonstrated by the project’s substantial leveraging of local, state and regional funds. 

The federal Core Capacity request makes up only 32% of the total project cost.
Caltrain officials expressed their gratitude to their primary modernization contractors for providing additional time and flexibility to manage the unforeseen delay.

“Every project that has achieved these milestones has received an executed Full Funding Grant Agreement and we don’t expect that this project will be any different,” said Caltrain Executive Director Jim Hartnett.

In September 2016, Caltrain awarded contracts to Balfour Beatty for construction of the corridor’s electrification infrastructure, and to Stadler US Inc. for the manufacture and delivery of high-performance electric commuter rail trains that will increase the system’s ridership capacity and connect Peninsula communities with more frequent service and improved travel times. The contractors have advanced the project’s design and were scheduled to begin construction before FTA announced the delay.

Ad Loading...

“This project will not only transform the aging diesel system into a modern and efficient electric commuter rail system better serving the needs of the region but it will also be the driving force for the creation of a new railcar production facility in the U.S., that will employ several hundred workers,” said Martin Ritter, Stadler US CEO.

Caltrain cautioned that additional extensions may not be possible. “Our contractors have agreed to delay construction for the maximum amount of time possible,” said Hartnett. “Delaying a decision on Federal funding beyond June 30 will be the same as rejecting the grant.”

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →