Caltrain negotiates extension for electrification project

While the agency awaits a decision from the FTA about the execution of a $647 million funding agreement.

March 1, 2017
Caltrain negotiates extension for electrification project

 

3 min to read


Caltrain announced that it has negotiated an extension of the deadline for contractors to begin construction of the Peninsula Corridor Electrification Project while the agency awaits a decision from the Federal Transit Administration about the execution of a $647 million funding agreement.

The contractors agreed to extend the deadline for four months, from March 1 to June 30. Last week, FTA announced that execution of the grant would be delayed until the President makes decisions about the availability of funds in the Administration’s upcoming budget proposal to Congress. The extension is needed to preserve the electrification project’s contracts during this time. 

Ad Loading...

The extension does not come without cost implications. Buying additional time from the contractors will likely require the utilization of up to $20 million in project contingency that otherwise would have been available for construction related expenses in the future. The sooner the grant agreement is executed, the smaller the impact will be to the project’s contingency.

Caltrain has been working with the FTA since 2009 to ensure that the project meets all of the rigorous statutory and regulatory requirements of the Core Capacity competitive discretionary program. The project was rated highly after thorough evaluation including ridership studies, design assessments, financial analyses and cost benefit evaluations by the FTA and the U.S. Department of Transportation (USDOT). Caltrain, as the project sponsor, also has significant local financial support for this project, demonstrated by the project’s substantial leveraging of local, state and regional funds. 

The federal Core Capacity request makes up only 32% of the total project cost.
Caltrain officials expressed their gratitude to their primary modernization contractors for providing additional time and flexibility to manage the unforeseen delay.

“Every project that has achieved these milestones has received an executed Full Funding Grant Agreement and we don’t expect that this project will be any different,” said Caltrain Executive Director Jim Hartnett.

In September 2016, Caltrain awarded contracts to Balfour Beatty for construction of the corridor’s electrification infrastructure, and to Stadler US Inc. for the manufacture and delivery of high-performance electric commuter rail trains that will increase the system’s ridership capacity and connect Peninsula communities with more frequent service and improved travel times. The contractors have advanced the project’s design and were scheduled to begin construction before FTA announced the delay.

Ad Loading...

“This project will not only transform the aging diesel system into a modern and efficient electric commuter rail system better serving the needs of the region but it will also be the driving force for the creation of a new railcar production facility in the U.S., that will employ several hundred workers,” said Martin Ritter, Stadler US CEO.

Caltrain cautioned that additional extensions may not be possible. “Our contractors have agreed to delay construction for the maximum amount of time possible,” said Hartnett. “Delaying a decision on Federal funding beyond June 30 will be the same as rejecting the grant.”

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →