METRO Magazine Logo
MenuMENU
SearchSEARCH

Caltrain negotiates extension for electrification project

While the agency awaits a decision from the FTA about the execution of a $647 million funding agreement.

March 1, 2017
Caltrain negotiates extension for electrification project

 

3 min to read


Caltrain announced that it has negotiated an extension of the deadline for contractors to begin construction of the Peninsula Corridor Electrification Project while the agency awaits a decision from the Federal Transit Administration about the execution of a $647 million funding agreement.

The contractors agreed to extend the deadline for four months, from March 1 to June 30. Last week, FTA announced that execution of the grant would be delayed until the President makes decisions about the availability of funds in the Administration’s upcoming budget proposal to Congress. The extension is needed to preserve the electrification project’s contracts during this time. 

Ad Loading...

The extension does not come without cost implications. Buying additional time from the contractors will likely require the utilization of up to $20 million in project contingency that otherwise would have been available for construction related expenses in the future. The sooner the grant agreement is executed, the smaller the impact will be to the project’s contingency.

Caltrain has been working with the FTA since 2009 to ensure that the project meets all of the rigorous statutory and regulatory requirements of the Core Capacity competitive discretionary program. The project was rated highly after thorough evaluation including ridership studies, design assessments, financial analyses and cost benefit evaluations by the FTA and the U.S. Department of Transportation (USDOT). Caltrain, as the project sponsor, also has significant local financial support for this project, demonstrated by the project’s substantial leveraging of local, state and regional funds. 

The federal Core Capacity request makes up only 32% of the total project cost.
Caltrain officials expressed their gratitude to their primary modernization contractors for providing additional time and flexibility to manage the unforeseen delay.

“Every project that has achieved these milestones has received an executed Full Funding Grant Agreement and we don’t expect that this project will be any different,” said Caltrain Executive Director Jim Hartnett.

In September 2016, Caltrain awarded contracts to Balfour Beatty for construction of the corridor’s electrification infrastructure, and to Stadler US Inc. for the manufacture and delivery of high-performance electric commuter rail trains that will increase the system’s ridership capacity and connect Peninsula communities with more frequent service and improved travel times. The contractors have advanced the project’s design and were scheduled to begin construction before FTA announced the delay.

Ad Loading...

“This project will not only transform the aging diesel system into a modern and efficient electric commuter rail system better serving the needs of the region but it will also be the driving force for the creation of a new railcar production facility in the U.S., that will employ several hundred workers,” said Martin Ritter, Stadler US CEO.

Caltrain cautioned that additional extensions may not be possible. “Our contractors have agreed to delay construction for the maximum amount of time possible,” said Hartnett. “Delaying a decision on Federal funding beyond June 30 will be the same as rejecting the grant.”

More Rail

An overhead view of APTA EXPO's show floor.
Management•by Alex Roman•October 9, 2026

Scenes from APTA TRANSform & EXPO 2026

Transit leaders, manufacturers, and industry professionals gathered in Chicago to explore new technologies, share ideas, and discuss the future of public transportation.

Read More →
METRO Magazine graphic featuring officials at a Florida rail funding announcement, with the headline “$416M Awarded for Florida Rail Crossing Upgrades and More.”
Rail•by Staff and News Reports•October 8, 2026

USDOT Awards $416 Million for Florida Rail Crossing Safety Upgrades, New Brightline Station

The projects aim to reduce risks for motorists and pedestrians at rail crossings while expanding passenger rail access along Florida’s Space Coast.

Read More →
Coastal railroad tracks run between a steep bluff and the Pacific Ocean in San Clemente, California, with rock barriers protecting portions of the shoreline.
Rail•by Elora Haynes•October 1, 2026

OCTA Declares Emergency to Protect Rail Corridor From Coastal Erosion

The California agency is accelerating shoreline protection and plans to place approximately 690,000 cubic yards of sand along the San Clemente coast to protect a key passenger and freight rail link.

Read More →
Ad Loading...
DRPA interns with program swag.
Management•by Alex Roman•October 1, 2026

More Than a Summer Job: Building the Next Generation of Transit Talent

The Delaware River Port Authority and PATCO have transformed their internship program into a hands-on professional development experience that introduces students to the breadth of transportation careers — and creates a pipeline for future employees.

Read More →
An Amtrak Airo trainset on the Cascades line
Rail•by Alex Roman•September 30, 2026

Airo Trains Make Their Amtrak Cascades Debut in the Pacific Northwest

Effective immediately, two cutting-edge Airo trainsets will join the Amtrak Cascades route, operating four daily trips between Vancouver, B.C., Seattle, Portland, and Eugene, Oregon, marking the first introduction of Airo trains into passenger service anywhere in the country.

Read More →
Rail•by Alex Roman•September 29, 2026

Florida's Brightline Announces Financial Restructuring

Brightline Florida says train operations will continue as normal as certain parent entities enter Chapter 11 and financial stakeholders provide $490 million in new long-term capital.

Read More →
Ad Loading...
Bus manufacturing image from ENC
Technology•by Alex Roman•September 25, 2026

ENC Lands MATA Contract and More in Biz Briefs

In this edition of Biz Briefs, we spotlight the latest developments shaping the future of mobility.

Read More →
Turning transit data into better decisions
Management•by Alex Roman•September 23, 2026

Strada360’s Steve Lassey on Turning Transit Data Into Better Decisions

From breaking down data silos to preparing for AI, Strada360 CEO Steve Lassey discusses how transit agencies can use technology to improve operations, customer information, and long-term decision-making.

Read More →
SEPTA Accelerate press conference
Management•by Staff and News Reports•September 23, 2026

SEPTA Details Accelerate Vision for Transit System

The plan outlines investments in trolley modernization, new Metro and Regional Rail vehicles, accessible stations, and more frequent bus and rail service.

Read More →
Ad Loading...
Two MBTA railcars in station.

FTA Ends Direct Oversight of MBTA Safety Actions

The federal agency closed its remaining special directive to the Massachusetts Department of Public Utilities following a safety review that began in 2022.

Read More →