FRA completes Amtrak Vermonter Line upgrades

Included heavier continuously-welded rail, bridge work, new tie installation and ballast work. Improvements enable the scheduled running time for the line to be reduced by about a half hour and passenger-train track speeds in signaled territory to increase from 50 to 79 miles per hour.

October 10, 2012
2 min to read


The two-year project making upgrades and repairs along 190 miles of track between St. Albans and Vernon on Amtrak’s Vermonter line was completed on-time and on-budget.

The project is one of the first major rail corridor projects to be completed under the Federal Railroad Administration’s High-Speed and Intercity Passenger Rail program, part of the American Recovery and Reinvestment Act. The project received $52.7 million in Recovery Act funds. The improvements will result in increased speeds, reduced travel time, greater reliability and an increased number of trains traveling each day.

Upgrades to the rail track included heavier continuously-welded rail, bridge work, new tie installation and ballast work. These improvements enable the scheduled running time for the Vermonter to be reduced by about a half hour, and passenger-train track speeds in signaled territory to increase from 50 to 79 miles per hour.

The upgraded track increased weight capacity from 263,000-pound to 286,000-pound freight cars. The project also repaired and strengthened more than 50 bridges and improved 52 highway-rail grade crossings on track owned by the New England Central Railroad.

The U.S. Department of Transportation has made more than $315 million in rail investments throughout New England. Other FRA grants on the Vermonter line include $72.8 million to Massachusetts for improvements between Springfield and East Northfield, Mass., which will reduce travel times by an additional 30 minutes upon project completion. Additionally, $191 million is being invested on the rail line between New Haven, Conn., and Springfield, Mass., which is also used by the Vermonter.

Ad Loading...

All of these improvements will reduce travel times, improve reliability and add capacity. The Vermonter runs daily between Washington, D.C., and St. Albans, Vt.


More Rail

Graphic from Amtrak promoting the B&P Tunnel Replacement and Frederick Douglass Tunnel project, featuring the Amtrak logo, project title and an illustration of a high-speed train near the West Baltimore MARC Station.
Railby News/Media ReleaseMarch 17, 2026

Amtrak Announces Community Grants for Projects Near Baltimore’s New Frederick Douglass Tunnel

Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.

Read More →
Amtrak train with logo
Railby StaffMarch 16, 2026

Amtrak Marks Restoration of Two South Carolina Stations

The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.

Read More →
A view looking down the rail across the new Portal North Bridge.
Railby Staff and News ReportsMarch 13, 2026

NJ Transit, Amtrak Prepare to Open First Track on New Portal North Bridge

The new bridge will begin carrying passenger trains on March 16, replacing a 116-year-old swing bridge that has long caused delays.

Read More →
Ad Loading...
Caltrain trains on tracks
Railby StaffMarch 6, 2026

Caltrain Adopts Corridor-Wide Right-of-Way Safety Strategy

Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.

Read More →
A photo of rail tracks in Ottawa, Canada

Building a National Framework for Transit Safety and Consistency

On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.

Read More →
Stairs in a New York rail station with text reading "USDOT Invests $686 Million to Modernize Aging Rail Stations."
Railby StaffMarch 2, 2026

FTA Invests $686M to Modernize Aging Rail Stations

Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.

Read More →
Ad Loading...
A purple MBTA train at a Mansfield Station platform.
Railby StaffFebruary 27, 2026

MBTA Updates Rail Modernization Plan to Expand Reliability and Accessibility

The strategy outlines near- and long-term upgrades to ease congestion, support housing growth, and advance statewide climate goals.

Read More →
LA Metro underground station with vehicle
Railby StaffFebruary 27, 2026

LA Metro Sets D Line Subway Extension Launch Date

The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.

Read More →
MBTA railcars
Railby StaffFebruary 26, 2026

Boston's MBTA Marks Progress in Regional Rail Modernization

The procurement advances the agency's broader efforts to modernize its rail fleet and position Regional Rail for long-term improvement.

Read More →
Ad Loading...
An Amtrak Acela
Railby StaffFebruary 26, 2026

Amtrak Sets New Course for Long-Distance Fleet Renewal

Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.

Read More →