MBTA Completes Expedited Track Work on Green Line

With unencumbered access to Green Line stations, crews were able to accomplish station enhancements and amenity upgrades like new flooring and lighting, which further improved the customer experience.

MBTA Completes Expedited Track Work on Green Line

Crews accomplished track work and other upgrades along the Green Line.

Photo: MBTA

3 min to read


The Massachusetts Bay Transportation Authority (MBTA) announced the successful and on-time completion of track work on the Green Line, which removed 16 safety-related speed restrictions.

Additionally, a 17th speed restriction on the Green Line between Haymarket and Government Center stations was shortened by over 500 feet.

Ad Loading...

How the MBTA Crew Accomplished the Track Work

Crews accomplished this work due to unencumbered access to track areas while Green Line train service was suspended on the B branch from Babcock Street to Kenmore, on the E branch between Heath Street and Copley, and in the downtown area between Kenmore and North Station for 10 days from Jan. 3-12 and for 13 days from Jan. 16-28. 

Additionally, during scheduled weekend and evening service diversions over the last several weeks between North Station and Union Square as well as Medford/Tufts, crews from GLXC, the design-build contractor, have completed track work that has alleviated all current tight gauge conditions along both Green Line Extension branches.

“Our team was able to lift even more speed restrictions than were planned and significantly shorten another. This continues to be indicative of the new way the MBTA is doing business," said MBTA GM/CEO Phillip Eng. "I thank our riders for their patience as we know shuttle bus service replacement can be challenging, especially in the winter months. Thank you as well to the MBTA forces, working side by side with our crews from multiple contractors to deliver on the commitments we made.”

With unencumbered access to Green Line stations, crews were able to accomplish station enhancements and amenity upgrades like new flooring and lighting, which further improved the customer experience.

Through planning and coordination between contractor crews and multiple MBTA Operations departments, the MBTA was able to maximize the shutdown time by having numerous contractor crews and MBTA personnel working side-by-side and collaboratively within the underground Green Line tunnel area.

Ad Loading...

Crews performed tie replacement work during the Green Line shutdown.

Photo: MBTA

Critical Work on Green Line

Among this critical work:

  • Over 1,300 ties were replaced.

  • Nearly 10,800 feet of rail was replaced.

  • Nearly 8,900 feet of track was resurfaced and tamped.

  • 12 switches were replaced/rehabilitated.

  • Approximately 7,300 feet of overhead catenary wire was replaced between Haymarket and Boylston stations.

  • Structural repairs were completed on the roofs of Boylston and Copley stations.

  • Tunnel inspections were performed between Haymarket and North Station.

  • At Copley station, repair work was completed on three in-station columns with additional infrastructure upgrades accomplished.

  • A new elevator sump pump was installed at Arlington station.

  • Substation maintenance and electrical repairs were completed. 

  • Water infiltration repairs were completed within the Green Line tunnel.

  • Critical signal and power system repairs were completed. 

  • Improvements were accomplished at the Park Street communication room.

  • Structural inspections were accomplished at stations throughout the Green Line shutdown.

Other in-station work also took place along the Green Line to further enhance the rider experience, including cleaning, sanding, and painting wood benches; performing tactile repairs; stairway upgrades and repairs, including handrail repairs; installing/replacing station signage; painting columns and ceilings at station platforms; painting stair risers, doors, and door frames; performing flooring/tile repairs; replacing lights; patching spalls on concrete columns; replacing/cleaning light covers; and more.

The MBTA further maximized this shutdown by coordinating site access with utility partners. With the service shutdown, Comcast was able to access property adjacent to the MBTA to expand maintenance access points and upgrade existing equipment, which was a project that had been previously delayed nine months.

The Boston Water and Sewer Commission (BWSC) also completed CCTV inspections of 20 maintenance access points and connecting sewer lines of the utility network between Brigham Circle and Health Street stations along Huntington and South Huntington Avenues. 

More Rail

Tri-Rail Train
Railby StaffMay 22, 2026

SFRTA Partners on “Are You OK?” Mental Health Awareness Campaign

Supported by a $56,500 grant from the Federal Railroad Administration, the program will combine targeted public education campaigns with specialized training for SFRTA employees, contractors, and regional partners.

Read More →
The inside of a rail car with passengers, and a surveillance camera fixed to the ceiling.
RailMay 22, 2026

Major Rail Projects Don’t Have to Mean Major Security Gaps

Crowded platforms. Temporary routes. New risks. Discover why video tech is critical during rail upgrades.

Read More →
An Amtrak Acela train at New York Penn Station
Railby StaffMay 21, 2026

Penn Transformation Partners Named as Master Developer Team for New York Penn Station Renovation

The team of Halmar and Skanska will build a brand-new station that will provide daily commuters and tourists with a more seamless travel experience through a vibrant gateway into America’s largest city, said Amtrak.

Read More →
Ad Loading...
A man stands at a podium in front of a large crowd.
Railby Staff and News ReportsMay 21, 2026

REM West Island Extension Opens, Expanding Montreal Automated Rail Network

The expansion adds four stations and extends Montreal’s automated REM network deeper into the region with a new all-electric transit service.

Read More →
Richard Andreski, Maggie Adams, and Lilia Montoya
Managementby StaffMay 21, 2026

People Movement: Montoya to Lead Delaware, Andreski Extended in Fort Worth, and More

In this edition, we cover recent appointments and announcements at Trinity Metro, SilverRide, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Managementby StaffMay 21, 2026

California's OCTA Proposes 2026-27 Balanced Budget to Advance Transportation

The proposed budget, totaling approximately $2 billion, advances key transportation initiatives while ensuring all services, programs, and projects can be delivered to residents not only next year but well into the future.

Read More →
Ad Loading...
KC Streetcar Riverfront extension with graffiti wall
Railby StaffMay 19, 2026

KC Streetcar Expansion Strengthens Access to City’s Growing Riverfront

The project adds 0.7 miles of track to the existing KC Streetcar line, connecting north from the River Market to Berkley Riverfront Park.

Read More →
An Amtrak Cascades Airo Trainset at a station.
Railby Staff and News ReportsMay 19, 2026

First Amtrak Cascades Airo Trainset Arrives in Pacific Northwest for Final Testing

Take a closer look at the next generation of Amtrak Cascades service as the first Airo trainset prepares for passenger operations in the Pacific Northwest.

Read More →
MBTA Green Line Construction
Railby StaffMay 18, 2026

Boston's MBTA Completes Latest Green Line Work

The work took place during 12 consecutive days of shuttle bus service replacement between Kenmore and Cleveland Circle. 

Read More →
Ad Loading...
King County Metro's bus depot with Schunk Transit pantograph charging infrastructure.

Biz Briefs: King County Metro Taps Schunk Transit Systems for Charging and More

Stay informed with these quick takes on the projects and companies driving progress across the transportation landscape.

Read More →