MBTA unveils plan to accelerate rail infrastructure projects

The projects will include additional diversions of weekend service on all rapid transit lines and several commuter rail lines.

February 10, 2020
MBTA unveils plan to accelerate rail infrastructure projects

In 2019, the MBTA delivered rail projects 2.2 years faster than originally planned.

Keolis

2 min to read


In 2019, the MBTA delivered rail projects 2.2 years faster than originally planned. Keolis

Boston’s MBTA unveiled plans to accelerate infrastructure projects for several subway and commuter rail lines during calendar year 2020 to improve service, safety, and reliability on a faster timeline. The projects will include additional diversions of weekend service on all rapid transit lines and several commuter rail lines. In addition to several weekend diversions on the Green Line, the MBTA is planning for two one-month shutdowns on the Green Line — the C Branch in July and the E Branch in August.

The 2020 Infrastructure Acceleration Plan will deliver these projects eight years faster than originally planned, and will result in track replacement, upgraded intersections, and station improvements.

Ad Loading...

In 2019, the MBTA executed a plan to expedite projects for customers, delivering projects 2.2 years faster than originally planned across the Red, Orange, and Green Lines.

  • Much of this work was completed through 10 weekend shutdowns on the Red and Orange Lines through the core of downtown Boston.

  • During those shutdowns, the MBTA was able to accelerate improvements by expanding traditional work windows and increasing the number of work activities that took place.

  • Throughout those weekends, the MBTA accommodated customers by increasing existing parallel service while also providing robust replacement service where feasible during the diversions.

In addition to the full-month C and E Branch shutdowns, as previously announced, the MBTA has scheduled an 11-month suspension of regular Green Line service between North Station and Lechmere starting in May 2020. During the closure, the T will accelerate efforts to strengthen the historic Lechmere Viaduct in coordination with the rebuilding of the elevated segment of track through East Cambridge and the realignment of the track to a new, relocated Lechmere Station, which is being completed as part of the project to extend the Green Line to Somerville and Medford.

  • During diversions of regularly scheduled rail service, the MBTA takes steps to provide replacement service to ensure customers can reach their intended destinations.

  • In certain cases, the MBTA increases the frequency of parallel services to accommodate customers displaced by a diversion.

  • In other cases, the MBTA provides accessible shuttle buses — operated by the MBTA or a private carrier — that are specially designed to account for passenger travel patterns during these diversions.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →