To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne
1 min to read
To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne
After permanently stabilizing sections of Light RailLink track that eroded during severe storms on July 21, the Maryland Department of Transportation Maryland Transit Administration (MDOT MTA) resumed service from the Patapsco to Cromwell and BWI Thurgood Marshall Airport stations on Friday — three days ahead of the planned reopening on August 20.
“We thank the men and women of MDOT MTA for their hard work and dedication in completing these much-needed repairs caused by the severe storms and ensuring our Light RailLink system is safe for our riders,” said MDOT MTA COO Sean Adgerson.
Ad Loading...
To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks. The repair work involved cutting and removing sections of track, gravel, and soil; building a pipe; and excavating an area 40 feet wide and 16 feet deep. A 1,200-foot-long concrete drain also was constructed to minimize potential flooding.
To further stabilize the area, reinforcements were constructed along the hillside next to the tracks. Free shuttle buses were provided to accommodate passengers at all impacted stations while the repairs were being made.
Crews completed a significant portion of the testing required before commissioning the new, digital signaling system, which will bring important upgrades that strengthen Red Line service reliability for riders and provide Red Line Operations the ability to route trains more quickly, turn trains around faster, and recover from unplanned disruptions more efficiently, said MBTA officials.
In addition to new projects, progress continues on a multiyear effort to upgrade track, electrical, and signal systems on the Metra Electric Line to accommodate the expansion of service on the South Shore Line.
The Maryland Transit Administration is advancing the nearly $1.4 billion Light Rail Modernization Program, which modernizes the Baltimore Central Light Rail Line from Hunt Valley to BWI Thurgood Marshall Airport with new, low-floor vehicles and upgrades to all light rail stations, systems, and maintenance facilities.
The Peninsula Corridor Joint Powers Board recently met for a budget workshop, during which staff outlined the significant service reductions Caltrain could be forced to make without new external funding.
Funding for the purchase of the railcars comes from the nearly $220 million in additional capital dollars Gov. Josh Shapiro allocated in November 2025 to support urgent safety upgrades and infrastructure improvements.
With major events and increased travel expected across the state this summer, the Administration is focused on making sure people have a reliable, affordable alternative to driving so we can reduce congestion, support daily commuters, and keep Massachusetts moving.
The final seven-mile segment of the 2 Line includes new stations at Mercer Island and Judkins Park and connects to the 1 Line at the International District/Chinatown Station. The Link light rail system now spans 63 miles and includes 50 stations.