To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne
1 min to read
To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks.
Andrew Horne
After permanently stabilizing sections of Light RailLink track that eroded during severe storms on July 21, the Maryland Department of Transportation Maryland Transit Administration (MDOT MTA) resumed service from the Patapsco to Cromwell and BWI Thurgood Marshall Airport stations on Friday — three days ahead of the planned reopening on August 20.
“We thank the men and women of MDOT MTA for their hard work and dedication in completing these much-needed repairs caused by the severe storms and ensuring our Light RailLink system is safe for our riders,” said MDOT MTA COO Sean Adgerson.
Ad Loading...
To mitigate flooding and future erosion in the area of the Twin Oaks Light RailLink grade crossing, MDOT MTA constructed a 36-inch drain pipe under the tracks. The repair work involved cutting and removing sections of track, gravel, and soil; building a pipe; and excavating an area 40 feet wide and 16 feet deep. A 1,200-foot-long concrete drain also was constructed to minimize potential flooding.
To further stabilize the area, reinforcements were constructed along the hillside next to the tracks. Free shuttle buses were provided to accommodate passengers at all impacted stations while the repairs were being made.
The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.
The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.
In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.
This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.
Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.