NTSB releases third D.C. Metro crash update
Two signal companies, Ansaldo STS USA and Alstom Signaling Inc., which designed and manufactured the automatic train control components for the Metro system, are providing technical assistance to the NTSB investigation.
The National Transportation Safety Board (NTSB) announced that it continues to make progress in its investigation of the June 22, 2009, collision of two Washington Metropolitan Area Transit Authority (Metro) trains on the Red Line in Washington, D.C.
Factual information that has been gathered by the NTSB:
Two signal companies, Ansaldo STS USA and Alstom Signaling Inc., which designed and manufactured the automatic train control components for the Metro system, are providing technical assistance to the NTSB investigation.
As previously reported, an impedance bond (#15) for the track circuit where the accident occurred was replaced on June 17th, 2009, five days before the accident. Continued review of the maintenance logs has identified that the impedance bond (#14), located on the other end of the same circuit, was replaced in December 2007. Metro records reveal that this track circuit's train occupancy signal has been intermittently fluctuating since the replacement was installed in December 2007.
The NTSB has requested trouble tickets for the last 18 months to see if these problems had been reported, and seeking records to see if any operators reported problems on this circuit.
The investigation is identifying possible sources of interference affecting the automatic train control (ATC) operation. These potential sources include Electromagnetic Interference (EMI), traction power harmonics and signal crosstalk, communication lines, and system upgrades and changes.
Following the accident, Metro began to review operations data and identified some problems at other circuits. These anomalies are being examined by NTSB and Metro to determine if they are the same kinds of problems as were found in the location of the accident site.
Testing has identified that the circuit problems are occurring more frequently during the rush hour time period. As a result, the NTSB and Metro testing at the accident location on the Red Line is continuing. These tests may result in occasional delays on the Red Line in the Fort Totten area. All testing in the Fort Totten area is closely coordinated with Metro and is scheduled to minimize delays on that area of track during rush hour.
On Saturday, July 18, the NTSB conducted a sight distance test at the accident location. Information collected from the test will be correlated with rail markings documented after the accident, the braking characteristics of the striking train, and the speed information gleaned from the Metro Operations Control Center records.
More Rail

Amtrak, NJ TRANSIT Launch Full Service on New Portal North Bridge
The completion of the two-track bridge over the Hackensack River eliminates a longstanding source of delays for NJ TRANSIT and Amtrak customers. It marks a major milestone for the Gateway Program.
Read More →
Southern California’s Metrolink Approves $508.8M Budget, Avoids Service Cuts
A $20 million state allocation allows the regional rail agency to maintain existing weekday and weekend service through fiscal year 2028, although longer-term funding challenges remain.
Read More →
NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements
The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.
Read More →
STraffic Expands North American Presence with Fare Collection Technology
John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.
Read More →
Study: Denver RTD Generates $2.1 Billion in Annual Economic Activity
An economic impact study finds the agency supports approximately 17,500 jobs, delivers $1.6 billion in annual community and mobility benefits, and generates $2.42 in economic value for every dollar invested.
Read More →
Mark Aesch Nominated to Lead Federal Transit Administration
The former Rochester transit chief and TransPro founder, who has also contributed to METRO Magazine, brings decades of industry experience and a focus on performance, accountability, and financial sustainability to the nomination.
Read More →
Transit Expands Agency Partnerships, Reaching 200 Official App Partners
COO Jake Sion discusses Transit’s growth, the success of its Transit Royale program, and how technology is helping agencies improve the rider experience.
Read More →
Trinity Metro Breaks Ground on $270M TEXRail Extension
The 2.1-mile extension will connect Fort Worth’s Medical District and Near Southside to downtown, surrounding communities, and Dallas-Fort Worth International Airport.
Read More →
Bringing Austin’s First Light Rail System to Life
Austin Transit Partnership CEO Greg Canally discusses the city's nearly 10-mile light rail project, its collaborative approach to project delivery, the importance of community engagement, and the milestones ahead as construction approaches in 2027.
Read More →
Metra Draft Plan Outlines Costs, Service Improvements for Regional Rail
The Systemwide Network Plan identifies infrastructure needs and potential investments to expand all-day, bidirectional rail service across the Chicago region.
Read More →