NTSB releases third D.C. Metro crash update
Two signal companies, Ansaldo STS USA and Alstom Signaling Inc., which designed and manufactured the automatic train control components for the Metro system, are providing technical assistance to the NTSB investigation.
The National Transportation Safety Board (NTSB) announced that it continues to make progress in its investigation of the June 22, 2009, collision of two Washington Metropolitan Area Transit Authority (Metro) trains on the Red Line in Washington, D.C.
Factual information that has been gathered by the NTSB:
Two signal companies, Ansaldo STS USA and Alstom Signaling Inc., which designed and manufactured the automatic train control components for the Metro system, are providing technical assistance to the NTSB investigation.
As previously reported, an impedance bond (#15) for the track circuit where the accident occurred was replaced on June 17th, 2009, five days before the accident. Continued review of the maintenance logs has identified that the impedance bond (#14), located on the other end of the same circuit, was replaced in December 2007. Metro records reveal that this track circuit's train occupancy signal has been intermittently fluctuating since the replacement was installed in December 2007.
The NTSB has requested trouble tickets for the last 18 months to see if these problems had been reported, and seeking records to see if any operators reported problems on this circuit.
The investigation is identifying possible sources of interference affecting the automatic train control (ATC) operation. These potential sources include Electromagnetic Interference (EMI), traction power harmonics and signal crosstalk, communication lines, and system upgrades and changes.
Following the accident, Metro began to review operations data and identified some problems at other circuits. These anomalies are being examined by NTSB and Metro to determine if they are the same kinds of problems as were found in the location of the accident site.
Testing has identified that the circuit problems are occurring more frequently during the rush hour time period. As a result, the NTSB and Metro testing at the accident location on the Red Line is continuing. These tests may result in occasional delays on the Red Line in the Fort Totten area. All testing in the Fort Totten area is closely coordinated with Metro and is scheduled to minimize delays on that area of track during rush hour.
On Saturday, July 18, the NTSB conducted a sight distance test at the accident location. Information collected from the test will be correlated with rail markings documented after the accident, the braking characteristics of the striking train, and the speed information gleaned from the Metro Operations Control Center records.
More Rail

Amtrak, CN Reach Agreements to Strengthen Passenger Rail Service, Safety
The agreement resolves a more than decade-long proceeding before the Surface Transportation Board concerning the terms and conditions for Amtrak services, such as the City of New Orleans, Illini/Saluki, and Wolverine.
Read More →
New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →