Tunnel boring work set to begin for L.A. Metro rail extension

STV is serving as the engineer-of-record and principal design firm for the 2.6-mile-long Purple Line extension.

July 18, 2018
Tunnel boring work set to begin for L.A. Metro rail extension

Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026.

L.A. Metro

2 min to read


Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026. L.A. Metro

Two state-of-the-art tunnel boring machines (TBMs) will soon begin work on Section 2 of the Los Angeles County Metropolitan Transportation Authority’s (Metro) Purple Line Project, aided by the engineering and design services provided by STV, a transportation and infrastructure firm.

Working as part of the design-build team led by Tutor Perini and O&G Industries, STV is serving as the engineer-of-record and principal design firm for the 2.6-mile-long Purple Line Section 2 extension that will link Section 1 running through the Miracle Mile District with Section 3 connecting Century City to Westwood. Overall, the $6.3 billion Purple Line extension will run 9.1 miles from Koreatown to Westwood.

Ad Loading...

STV’s services include the design of stations at Beverly Hills and Century City along with the running tunnels. The firm also engineered and designed the so-called “launch box” in Century City where the two 400-foot-long TBMs will be lowered into excavations extending more than 70 feet below Constellation Boulevard to begin their 14- month journeys.

The construction of the Beverly Hills and Century City stations will use a cut-and-cover method to build entrances, platforms, and concourses along with additional space for power, ventilation systems, and communications. STV will also be providing engineering and design services for the trackwork, traction power, train control, and communications systems.

Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026. Once completed, the subway ride from downtown Los Angeles to Westwood is expected to take about 25 minutes.

More Rail

UTA FrontRunner vehicles.
Railby StaffFebruary 12, 2026

STV Tapped to Join Progressive Design-Build Team for UTA Rail Expansion 

The nearly $1 billion FrontRunner 2X project is a transformative investment to modernize and expand the 89-mile commuter rail corridor between Ogden and Provo.

Read More →
A rendering of Alstom's LRV for the Toronto Transit Commission.
RailFebruary 9, 2026

Alstom to Supply New Subway Trains for Toronto

Manufactured and tested in Canada, the vehicles will operate in tandem with a cutting-edge signaling system also supplied by Alstom.

Read More →
A 7000-series WMATA railcar at Navy Yard.
Railby StaffFebruary 6, 2026

WMATA and Kawasaki Resolve 7000-Series Railcar Disputes

A multiparty investigation, led by the NTSB and that included WMATA and KRC, found that wheel migration in the 7000-series railcars contributed to the derailment.

Read More →
Ad Loading...
Photo for METROspectives episode with Ana-Maria Tomlinson
ManagementFebruary 4, 2026

Establishing Standards & Codes in Canada, with CSA’s Ana-Maria Tomlinson

In this episode of METROspectives, METRO’s Executive Editor Alex Roman sits down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the Canadian Standards Association (CSA Group).

Read More →
David Carol, Baker Alloush, and Jesse Lazarus from METRO's People Movement February 4 edition.
Managementby Staff and News ReportsFebruary 4, 2026

New Rolling Stock Strategy Lead at New York MTA and More in People Movement

In this edition, we cover recent appointments and announcements at HDR, NCTD, STV, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Ad Loading...
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Ad Loading...
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →