VTA Board Approves Contractor Change for BART Silicon Valley Extension
With the change, the Santa Clara Valley Transportation Authority (VTA) aims to control costs and keep the BART extension on track.

While the change of tunnel contractors will impact the start of tunneling, VTA staff are making efforts to maintain the overall project timeline.
Photo: VTA / METRO
A recent vote by the Santa Clara Valley Transportation Authority (VTA) Board of Directors accepted the staff’s recommendation to officially off-ramp Kiewit Shea Traylor (KST) from its role in the tunnel construction of BART Silicon Valley Phase II (BSVII) due to cost proposals that significantly exceeded project budget limits.
The BSVII Oversight Committee unanimously approved the matter after reviewing the project’s current delivery strategy. According to an agency statement, the change aims to maintain this megaproject’s integrity, safety, and efficiency, bringing BART service into downtown San Jose and Santa Clara.
“As stewards of this region’s future, it is our responsibility to make decisions that ensure the success of this historic investment in public transit,” said VTA Chief Megaprojects Delivery Officer Tom Maguire. “This course correction reflects strong, proactive leadership and reinforces our commitment to delivering BART Silicon Valley Phase II in a fiscally responsible manner.”
Early BSVII Tunnel Work Progresses, Procurement Changes Ahead
KST has been completing preconstruction work in preparation for the tunnel portion of the six-mile extension, which includes a 5-mile single-bore tunnel. KST will complete the early BSVII construction activities that have been initiated, which include building the tunnel launch structure where the future tunnel will start.
While the change of tunnel contractors will impact the start of tunneling, VTA staff are making efforts to maintain the overall project timeline, as the rescheduling of construction package rebidding may be balanced by design enhancements and more efficient construction methods.
In the coming months, VTA will initiate a competitive procurement process. The staff’s preliminary industry outreach with major tunneling contractors worldwide showed great interest in the project and suggests that breaking down the scope allocated to KST into multiple contract packages will better align with price estimates.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →