VTA Board Approves Contractor Change for BART Silicon Valley Extension

With the change, the Santa Clara Valley Transportation Authority (VTA) aims to control costs and keep the BART extension on track.

VTA logo surrounded by a blue border.

While the change of tunnel contractors will impact the start of tunneling, VTA staff are making efforts to maintain the overall project timeline.

Photo: VTA / METRO

2 min to read


A recent vote by the Santa Clara Valley Transportation Authority (VTA) Board of Directors accepted the staff’s recommendation to officially off-ramp Kiewit Shea Traylor (KST) from its role in the tunnel construction of BART Silicon Valley Phase II (BSVII) due to cost proposals that significantly exceeded project budget limits.

The BSVII Oversight Committee unanimously approved the matter after reviewing the project’s current delivery strategy. According to an agency statement, the change aims to maintain this megaproject’s integrity, safety, and efficiency, bringing BART service into downtown San Jose and Santa Clara.

Ad Loading...

“As stewards of this region’s future, it is our responsibility to make decisions that ensure the success of this historic investment in public transit,” said VTA Chief Megaprojects Delivery Officer Tom Maguire. “This course correction reflects strong, proactive leadership and reinforces our commitment to delivering BART Silicon Valley Phase II in a fiscally responsible manner.”

Early BSVII Tunnel Work Progresses, Procurement Changes Ahead

KST has been completing preconstruction work in preparation for the tunnel portion of the six-mile extension, which includes a 5-mile single-bore tunnel. KST will complete the early BSVII construction activities that have been initiated, which include building the tunnel launch structure where the future tunnel will start.

While the change of tunnel contractors will impact the start of tunneling, VTA staff are making efforts to maintain the overall project timeline, as the rescheduling of construction package rebidding may be balanced by design enhancements and more efficient construction methods.  

In the coming months, VTA will initiate a competitive procurement process. The staff’s preliminary industry outreach with major tunneling contractors worldwide showed great interest in the project and suggests that breaking down the scope allocated to KST into multiple contract packages will better align with price estimates.

More Rail

Railby StaffFebruary 2, 2026

Chicago Region Transit Ridership Grows in 2025

The region’s fixed-route system finished out the year with a total of 373.5 million rides. Adding 12.3 million rides over 2024 represents an increase that is equal to the annual transit ridership of Kansas City.

Read More →
Managementby StaffJanuary 29, 2026

Valley Metro Sees Strong Ridership Growth in 2025

The agency ranked top five among mid-sized U.S. transit systems, defined as agencies with 15 million to 50 million annual trips.

Read More →
Busby StaffJanuary 29, 2026

Subway Customer Satisfaction Reaches Record High, New York MTA Says

The subway system saw increases across all key metrics, with 62% of subway riders reporting they feel satisfied with the system overall.

Read More →
Ad Loading...
Managementby StaffJanuary 27, 2026

Keolis Retains Virginia Railway Express Contract

The new contract for Keolis and VRE will commence in July 2026, with the potential to expand to 15 years.

Read More →
Busby StaffJanuary 27, 2026

California's OCTA Advances 2026 Initiatives Centered on Balance and Sustainability

The priorities are outlined in the 2026 Board and CEO Initiatives and Action Plan, which serves as a roadmap to guide the agency’s work throughout the year and ensure continued progress and accountability on voter-approved transportation investments and essential mobility services.

Read More →
Railby Staff and News ReportsJanuary 26, 2026

People Movement: Virginia's DRPT Names New Director and More

In this edition, we cover recent appointments and announcements at HDR, MCTS, and more, showcasing the individuals helping to shape the future of transportation.

Read More →
Ad Loading...
ManagementJanuary 23, 2026

Seattle Sound Transit Sets Launch Date for Crosslake Connection

This final component of the 2 Line will cross Lake Washington and connect with the 1 Line at International District/Chinatown Station, creating a fully integrated regional light rail system.

Read More →
A blue and white graphic with a map of the proposed study area for the Sepulveda Transit Corridor and text reading "LA Metro Approves Underground Rail for Sepulveda Transit Corridor."
RailJanuary 23, 2026

LA Metro Approves Underground Rail for Sepulveda Transit Corridor

The agency’s selection aims to slash travel times from the San Fernando Valley to the Westside to under 20 minutes.

Read More →
TechnologyJanuary 21, 2026

Florida's Tri-Rail Taps Siemens Mobility for Modern Locomotive Procurement

Expected to enter service in 2029, these locomotives support the agency’s commitment to offer reliable and efficient rail transportation across South Florida.

Read More →
Ad Loading...
Rendering of an Austin Light Rail station.
RailJanuary 20, 2026

Austin Transit Partnership Advances Federal Funding Process for Light Rail Project

See how the agency’s transit project completed a Final Environmental Impact Statement within the federal two-year guideline.

Read More →