Fort Worth 'FLIRTs' with New Train Tech for Airport Link
The FLIRT 3 (Fast Light Innovative Regional Train) vehicles, built by Stadler Bussnang AG of Switzerland, are the first of this model type to operate in the U.S.

Once completed, Fort Worth Transportation Authority’s $1 billion TEXRail service will transport passengers to DFW Airport.
All photos courtesy FWTA

The Fort Worth Transportation Authority’s (FWTA) new 27-mile commuter rail line TEXRail will extend from downtown Fort Worth, across northeast Tarrant County, through North Richland Hills and Grapevine, and into Dallas Fort Worth International Airport’s Terminal B. This line, which will begin service in late 2018, is projected to serve more than 9,000 daily riders at nine stations by the end of the first year of operation. By 2035, nearly 14,000 daily riders are projected to ride the system.
The FLIRT 3 (Fast Light Innovative Regional Train) vehicles, built by Stadler Bussnang AG of Switzerland, are the first of this model type to operate in the U.S.
The diesel multiple unit (DMU) trains are configured with an operator cab at either end for bidirectional movement. At the center of the train is a power pack with two diesel engines. This style of train is much quieter than traditional commuter rail, according to Stadler officials. TEXRail vehicle amenities include work tables, lap trays, a quiet car, level boarding, and overhead storage for bags.
FWTA President/CEO Paul Ballard and Sr. VP Bob Baulsir spoke to us about the TEXRail project, the agency’s Master Plan for service improvements, and how it will change the region.
What are some highlights of The T Master Plan with regard to rail service improvements/projects?
Paul Ballard: Improving and enhancing rail service to help more people reach more places. In 2016, the Trinity Railway Express schedule was updated to provide great frequency and extended weekend hours. (FWTA and DART jointly own and operate the Trinity Railway Express.) Changes in the north quadrant of our service in 2017 were designed to tie in with future rail service. Routes are designed for connectivity to future TEXRail stations. TEXRail will provide an excellent opportunity to connect the workforce with better job opportunities along the line.

How will this plan be funded and what is currently being implemented?
PB: The Transit Master Plan is fully funded through the FFGA and local funds. Work continues across the 27-mile corridor with more than 1,000 workers in the field. Construction includes laying rail, installing new bridges and building new rail stations.
What is the status of the TexRail project?
PB: TEXRail is progressing extremely well. Construction all along the Cotton Belt corridor is on target for us to begin revenue service on schedule. We are planning a special service run on New Year’s Eve, with regular service beginning January 1, 2019.
Our equipment maintenance facility is nearly completed, and we will begin testing our trains in March. We have two trains in Texas, and the remaining six will be delivered in the coming months.
Discuss the initial development of the TexRail project.
PB: Much of the preliminary work occurred before I arrived in 2014, but we have hit significant milestones in the last few years. In 2015, five railroads signed an agreement for TEXRail operations on the Cotton Belt corridor. Late in 2016, we received one of the last Full Funding Grant Agreements (FFGA) from the Federal Transit Administration. The $499.39 million in federal funds completed the local and federal funding for our $1.034 billion commuter rail project. In December 2017, we signed a contract for Positive Train Control, which will enhance safety and improve communications among all trains on the corridor.

What key design/construction considerations were required for the railcars?
Bob Baulsir: We have nine stations along the route, and two of those are existing stations in Fort Worth. We currently utilize those stations for Trinity Railway Express service. Because of the unique design of the TEXRail’s Stadler FLIRT, we have been modifying those platforms for level boarding to provide easy access for riders with bikes, strollers or wheelchairs.
One of the most complicated components of the project is at what we call the “hole in the wall.” We have three levels of transportation options — a highway on top, freight trains on the middle layer and TEXRail and the Trinity Railway Express on the ground level. Part of the construction involves implementing a double shoo-fly to redirect train traffic while we work to prepare for TEXRail.
What are some key railcar features?
BB: One of the best features of our diesel multiple unit trains is that we will have a quiet car to give travelers the chance to relax, read or catch up on a project. The Swiss design is unlike the trains people are used to seeing on the tracks. TEXRail’s sleek and innovative design provides a roomy and comfortable ride. Most seats have a pull-down tray and other seats are arranged around a work table. Each seat is equipped with a USB port for charging electronic devices. We also have a roomy ADA-compliant restroom near the center of each train.
How will TexRail alleviate congestion and help bolster growth in the region?
BB: We anticipate having 8,000 passengers a day by the end of the first year of service, and our trains will run seven days a week. We won’t be able to alleviate all traffic congestion, but that level of ridership will certainly take a significant number of cars off the road. Riders will benefit by having a streamlined route to the airport and not having to be concerned about getting caught in rush hour traffic.
We are seeing significant growth in terms of transit-oriented development. Having TEXRail in place will also provide growth in terms of passenger mobility to get to better job opportunities.
Tourism will also benefit from our commuter rail line. For travelers with layovers, Grapevine is an easy eight-minute ride away. Visitors can choose from an array of shops and restaurants and get back in plenty of time to make their connections. Fort Worth will be a short train ride away for convention-goers and for travelers who want to visit the area without worrying about driving.
How will the introduction of the TexRail service improve transportation between Fort Worth and DFW Airport?
BB: Currently, riders can ride the Trinity Railway Express part of the way and then take two bus shuttles to get to the airport. TEXRail will streamline the process and deliver travelers to the airport in 52 minutes. The new commuter rail line is essential not only for people trying to catch a flight, but also for employees at the airport call centers and warehouse as well as at the airport itself.
More Rail

Biz Briefs: STV teams with Amtrak, Motorcoach Operators Boost Fleet and Land Contracts, and More
From manufacturers and suppliers to transit agencies and motorcoach operators, these updates offer a snapshot of the projects, partnerships and business moves driving the industry forward.
Read More →
Metra Celebrates 100 Years of Electric Rail, Looks to the Future
The event was also a celebration of recent reforms to public transportation in the Chicago area, changes that could be as transformative in the future as the major civic achievement a century ago, said officials.
Read More →
LA Metro Marks Banner Year, Sets Ambitious Goals for New Fiscal Year
Incoming LA Metro Board Chair and Los Angeles Mayor Karen Bass joined outgoing Board Chair Fernando Dutra and LA Metro CEO Stephanie Wiggins to review accomplishments from fiscal year 2026, which included the opening of new rail extensions, advancement of major transit projects, expanded safety programs, and new rider amenities.
Read More →
DART Taps Nathaniel P. Ford Sr. as Next President/CEO
Since 2012, Ford has served as the CEO of the Jacksonville Transportation Authority
Read More →
California High-Speed Rail Authority Signs MOU to Advance High Desert Corridor
The agreement deepens collaboration between the California High-Speed Rail Authority and the High Desert Corridor Joint Powers Agency, supporting design integration, cost savings, and faster delivery of a key Southern California rail link.
Read More →
Building the Next Generation of Transit Technology
In this edition of METROspectives, Luminator CEO Magnus Friberg discusses the company's transformation, the growing role of AI and software, and what's next for transit technology.
Read More →How Data, Strategy, and Community Engagement Are Reshaping Transit
In this edition of METROspectives, strada360 CEO Steve Lassey discusses how transit agencies can better align planning with operations, leverage data to improve decision-making, and build public trust as they prepare for the future of mobility.
Read More →
TTC Launches Camera Pilot to Curb Illegal Passing of Streetcars
During the pilot, the cameras will measure how often illegal streetcar passing occurs and test the technology's reliability for future automated enforcement.
Read More →
NJ TRANSIT Secures Capital Funding, Adopts FY2027 Budget
The budgets continue investments in infrastructure and equipment to maintain the system in a state of good repair and enhance the overall customer experience.
Read More →
Biz Briefs: Masabi Teams with St. Louis Metro and More
In METRO's latest installment, we take a look at recent news from Transdev, Hitachi, and more partnerships making headlines across the transportation sector.
Read More →