STV Finalizes Design for First Phase of TriMet MAX Blue Line Substation Upgrades

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

February 24, 2026
A TriMet MAX Light Rail vehicle overhead shot

Originally installed in 1983, TriMet’s 12 Type 1 traction power substations along the MAX Blue Line are nearing the end of their service life.


Credit:

TriMet

2 min to read


  • STV completed the design for the first six traction power substations in TriMet's Banfield Type 1 Substation Replacement Project, which has been approved for construction.
  • The upgrade aims to modernize the aging power infrastructure of the MAX Blue Line, initially installed in 1983, enhancing safety and reducing maintenance costs.
  • Over the last 18 months, STV managed structural, civil, electrical, and systems design tasks for this project, collaborating with a team of eight consultants.

*Summarized by AI

STV announced the completion of design for the first six traction power substations under TriMet’s Banfield Type 1 Substation Replacement Project, which also received Issued for Construction (IFC) approval.

The milestone is a significant step toward modernizing the MAX Blue Line’s power infrastructure, one of the oldest components of the region’s light rail system.

Ad Loading...

TriMet’s Upgraded Substations

Originally installed in 1983, TriMet’s 12 Type 1 traction power substations along the MAX Blue Line are nearing the end of their service life.

The 12-year replacement program will introduce state-of-the-art traction power equipment, improve equipment access and safety, reduce long-term maintenance costs, and minimize the risk of service disruptions for riders.

Over the past 18 months, STV led the structural, civil, electrical, and systems design for six substations along the Banfield corridor and is providing overall project management, leading a team of eight consultants.

“This is a foundational investment in the reliability and resilience of the region’s transit system,” said Ja-Mie Luey, PE, VP/West Coast rail and transit systems lead at STV. “STV is modernizing the critical infrastructure upgrades that strengthen the backbone of MAX service today while building capacity for future improvements that directly benefit riders and the communities they connect.”

The MAX Blue Line’s Next Phase

The MAX Blue Line is TriMet’s longest light rail route, spanning approximately 33 miles and serving 48 stations between Hillsboro and Gresham.

Ad Loading...

“Maintaining our transit system in a state of good repair is one of TriMet’s top priorities,” said Jamie Snook, executive director, capital project delivery, at TriMet. “Through our partnership with STV, we’ve advanced the replacement of our original light rail substations that are more than 40 years old, which is vital to keeping our region and our world-class light rail system moving and reliable for our riders and the Portland metro area.”

Construction of the first six substations is anticipated to begin in 2026 and continue through 2028.

STV is also scheduled to begin designing four additional Banfield substation sites in July 2026.

Quick Answers

The purpose is to modernize the MAX Blue Line’s power infrastructure, introduce state-of-the-art traction power equipment, improve equipment access and safety, reduce long-term maintenance costs, and minimize the risk of service disruptions for riders.

*Summarized by AI

Ad Loading...

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →